Glen Johnson, Inc. v. Resolution Trust Corp.

598 So. 2d 81, 1990 Fla. App. LEXIS 4083, 1990 WL 77241
CourtDistrict Court of Appeal of Florida
DecidedJune 6, 1990
DocketNo. 89-00411
StatusPublished
Cited by2 cases

This text of 598 So. 2d 81 (Glen Johnson, Inc. v. Resolution Trust Corp.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glen Johnson, Inc. v. Resolution Trust Corp., 598 So. 2d 81, 1990 Fla. App. LEXIS 4083, 1990 WL 77241 (Fla. Ct. App. 1990).

Opinion

DANAHY, Judge.

The trial court in this mortgage foreclosure suit entered final judgments in favor of the mortgagee, City Federal Savings Bank f/k/a City Federal Savings & Loan Association, a federally chartered savings bank with an office in Boca Raton, Florida (City Federal). During the pendency of this appeal, the Office of Thrift Supervision, Department of the Treasury, declared City Federal insolvent and appointed Resolution Trust Corporation as its receiver for the purpose of liquidation. We have concluded that our disposition of this appeal requires us to consider the consequences of that event under the provisions of the Financial Institutions Reform, Recovery and Enforcement Act of 1989 (FIRREA), Pub.L. No. 101-73, 103 Stat. 183 (1989). There are no issues of fact concerning the receiver’s status which require determination.

For purposes of this opinion, we will recite the facts of this case as alleged by the appellant. The scenario here involved the construction of a hotel in Pinellas County. The appellant (the contractor) was the owner of the property on which the hotel was to be constructed. It entered into a contract with North Redington Beach Associates Limited (the owner) calling for the purchase of the property by the owner and the engagement of the contractor as general contractor for the construction of the hotel.

Construction financing was required. Accordingly, the owner applied for an acquisition and construction loan from City Federal. For purposes of closing that loan, the contractor delivered its executed deed to its agent with instructions that the deed should not be released until the receipt of a “set aside letter” from City Federal confirming that the loan had closed, that the contractor was approved as the general contractor, and that City Federal would set aside funds in the amount of $4,722,882 for payment to the contractor. The contractor says that sum represented $1,000,000 for the balance of the purchase price and $3,700,000 for the costs of construction.

[82]*82City Federal’s attorney presented a set aside letter to the contractor’s agent stating that the letter was to evidence and confirm to the contractor and its surety that the contractor was approved by City Federal as the general contractor for the project and that City Federal would provide funds to the owner in the amount of $4,722,822 for payment to the contractor over the term of the construction period provided in the contract of construction, and in accordance with the terms of City Federal’s construction loan agreement with the owner. The contractor’s agent contacted the contractor to verify the acceptability of the language in the set aside letter. The contractor agreed to the language contingent upon receipt of a copy of the construction loan agreement. The contractor’s agent released the contractor’s executed deed to City Federal’s attorney, but the agent was not shown a complete copy of the construction loan agreement. Several months later, the contractor learned that one of the provisions deleted from the copy of the construction loan agreement shown to the contractor’s agent was a requirement by City Federal that a $1,000,000 letter of credit be provided by the owner at closing. The contractor insists that had it known of this requirement, it would not have continued with the project and would have demanded the return of its executed deed.

Thereafter, City Federal, without notifying the contractor, unilaterally modified the terms of the construction loan agreement by partially funding the loan. City Federal then proceeded to have the contractor’s deed recorded. City Federal informed the owner, but not the contractor, that City Federal “shall not be obligated to make any further advances under the loan until such time as a letter of credit has been received and approved and all other relevant terms and provisions of the loan agreement have been satisfied.”

The contractor performed in accordance with its contract for construction through January of 1986. After submitting the pre-approved first application for payment, which was denied by the owner due to a lack of funds, the contractor learned for the first time of the events surrounding the $1,000,000 letter of credit and that City Federal was refusing to disburse any loan proceeds until receipt of that letter of credit. The contractor then attempted to assist the owner in obtaining the letter of credit, but those efforts were unsuccessful. Finally, City Federal agreed to cure the owner’s default if it received $600,000 in certificates of deposit in place of the $1,000,000 letter of credit. The owner would fund the certificates of deposit in part by the sum of $250,000 withheld from the contractor’s first application for payment in the amount of $988,718 which had been due since January 28, 1986. The contractor gave its consent to the withholding of $250,000 from its first application for payment. As security for its pledge, the contractor received a third mortgage on the property. After the $600,000 in certificates of deposit were placed, City Federal proceeded to disburse loan proceeds to the owner and to the contractor. Construction on the hotel project continued for approximately one year without any complications.

On June 5, 1987, the contractor made its final application for payment in the amount of $546,747.70. Thereafter the contractor received a check from the owner in the amount of $300,000 as partial payment toward the balance due. City Federal notified the contractor that in order to pay the remainder of the final application for payment, money would have to be withdrawn from the $600,000 placed in certificates of deposit, since the balance of the loan proceeds had been used to pay the costs of converting the construction loan into a permanent loan. On August 4, 1987, the contractor received a check from the owner in the amount of $236,746.70 representing the balance of the final draw request. City Federal depleted the entire $600,000 in order to meet the owner’s payment obligations, including the contractor’s final application for payment. Neither City Federal nor the owner paid the contractor any sum as reimbursement for the $250,000 pledge of the contractor included in the certificates of deposit for $600,000.

[83]*83This action basically represents the effort of City Federal to foreclose the first mortgage on the hotel property given by the owner to secure the loans made by City Federal to the owner. The owner defaulted under the terms of the mortgage and subsequently filed for bankruptcy. The contractor was made a defendant in the foreclosure proceedings because it held a third mortgage for $250,000. The contractor filed affirmative defenses and a counterclaim, seeking to have its third mortgage declared superior to City Federal’s mortgage or, alternatively, to recover damages on the theory of promissory estoppel. All of the contractor’s legal theories of defense or for affirmative relief arise from the alleged misrepresentation of City Federal in not revealing to the contractor that it required a $1,000,000 line of credit in order to make the construction loan; or stated otherwise, City Federal’s representation that it had agreed to make the loan without requiring a $1,000,000 line of credit. That requirement, of course, was reflected in the construction loan agreement between City Federal and the owner.

The trial court conducted a nonjury trial on the affirmative defense of the contractor that City Federal’s first mortgage should be equitably subordinated to the contractor’s third mortgage because of City Federal’s alleged misrepresentation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conlen v. National Credit Union Administration Board
104 So. 3d 1208 (District Court of Appeal of Florida, 2012)
Castelo Developments, LLC v. Rawls
118 So. 3d 831 (District Court of Appeal of Florida, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
598 So. 2d 81, 1990 Fla. App. LEXIS 4083, 1990 WL 77241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glen-johnson-inc-v-resolution-trust-corp-fladistctapp-1990.