Glavin v. Commonwealth Trust Co.

295 F. 103, 1924 U.S. App. LEXIS 3153
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 21, 1924
DocketNo. 4086
StatusPublished
Cited by1 cases

This text of 295 F. 103 (Glavin v. Commonwealth Trust Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glavin v. Commonwealth Trust Co., 295 F. 103, 1924 U.S. App. LEXIS 3153 (9th Cir. 1924).

Opinion

ROSS; Circuit Judge.

The assignment of errors upon which the appellants rely is as follows:

“The court erred in allowing the plaintiff interest from April 1, 1911, at the rate of 8 per cent, per annum upon the water contracts or water rights sought to be foreclosed in this action:
“First. For the reason that said water contracts and each of them contained a provision as follows: ‘AH interest accruing prior to the date notice is given to the entrymen that the company is prepared to furnish water under the terms of this contract is hereby waived.’ The evidence in the case conclusively establishes the fact that Ore company was never at any time prepared to furnish water under the terms of said contract.
“Second. For the reason that the evidence establishes the fact that plaintiff’s claim against said defendants was unliquidated and uncertain, and not capable of computation by fixed values or prices, and that by reason thereof the defendants, prior to the entry of the decree herein were unable to tender or pay to the plaintiff an amount certain or definite and stay the running of interest upon said contracts.
“Third. If the plaintiff was entitled to any interest upon these contracts, the rates should have been 8 per cent, per annum, as called for by the terms, of the water contracts and the court erred in aUowing interest at any greater rate.”

The liens sought to be foreclosed by the suit and which were foreclosed by the decree appealed from were authorized by the Act of Congress of June 11, 1896 (Comp. St. § 4686) — the case growing out of the establishment and construction of an irrigation system known" as the “Salmon River project,” under and in pursuance of the Act of Congress approved August 18, 1894 (28 Stat. 372, 422 [Comp. St. § 4685]), and amendments thereto, known as the Carey Act, and of certain legislation of the state of Idaho. The history of the project [104]*104and the numerous and complicated facts connected with the undertalcing were fully set out in the opinions of this court rendered in cases heretofore brought here, namely, Twin Falls Salmon River Land & Water Co. v. Caldwell, 242 Fed. 177, 155 C. C. A. 17; Twin Falls Oakley Land & Water Co. v. Martens (C. C. A.) 271 Fed. 428, and Twin Falls Salmon River Land & Water Co. v. Caldwell (C. C. A.) 272 Fed. 356.

In the Martens’ Case, 271 Fed. 428, while this court held that the liens created by the Idaho statute, acting under the authority conferred by the amendment to the Carey Act approved June 11, 1896 (29 Stat. 413, 434), are founded upon the contract for the water right, and that the right of foreclosure upon default must be “according to the terms and conditions of the contract granting and selling to the settler the water right,” yet that where the furnishing “company failed to deliver a quantity of water sufficient to comply with its contract and to enable the defendant to reclaim his land, it cannot rely upon the contract as ground of foreclosure for the full amount of deferred payments.” But we further said that where as in that case—

“defendant lias had the use of a substantial quantity of water furnished by the company since 1913, and although such quantity is less than he was entitled to have, and less than his land required for good husbandry, still it was furnished to him, and used by him according to the general provisions of the contract, and in view of his default in payments he ought not to be permitted to defeat foreclosure of the lien to an extent commensurate with the quantity of water furnished; hence a decree that, inasmuch as defendant will only receive seven-ninths of the water agreed to be furnished, the lien should be foreclosed accordingly, and that the settler should only be required to pay seven-ninths of the contracted for -price is equitable and proper.”

In the preceding case, reported in 242 Fed. 177, in explaining the scheme devised to taire the benefit of the congressional grant, we said, among other things:

“The construction of the system necessarily required the furnishing from some source of the money with which to do the work; the compensation to the construction company for the liability assumed by it in procuring the required money and in doing the work must of necessity come from the sale of the lands and of rights to the appropriated water; and of that fact both Congress and the state -were, of course, well aware, as is shown by the legislation that has been referred to. In the execution of the project, the contract between the state and the construction company, and the contract between that company and the settlers, were made. Manifestly, they are to be read together and in connection with the statutes of Congress and of the state, to which the contracts expressly referred. The construction company, the settlers, and the parties who furnished the money for the building of the system, receiving as security therefor the liens authorized both by Congress and the state, are therefore, each and all, charged with full knowledge of the laws and of the provisions of the contracts. The difficulties that have arisen grow out of the fact, discovered, unfortunately, too late, that, instead of the appropriation of the waters of the stream amounting in fact to 1,500 cubic feet per second, the supply, as shown by the record and according to the practical concession of the parties, was only about one-third of that 'amount — wholly insufficient for the reclamation and irrigation of the entire tract segregated by the Secretary of the Interior, and also insufficient, it is claimed, for at least the proper irrigation of all of the lands covered by contracts of sale actually issued by the construction company to settlers.”

The issues made by the pleadings in the present case are narrow and simple. According to the allegations of the bill, the lands against which [105]*105the appellee sought to foreclose its alleged liens, and the amount thereof at the price specified in the settlers’ contracts remaining unpaid against each legal subdivision, are as follows:

“Swt4 SE% of section 9, township 11 south, range 16 east; number of shares dedicated to said lands, 40; amount due on principal $1,480, with interest thereon from the 1st day of April, 1911.
“S.W% NW% KW14 SW% of section 10, township 11 south, range 16 east; number of shares dedicated to said lands, SO; amount due on principal, $2,-900 with interest thereon from the 1st day of April, 1911.
“XW’i SE}4 NE% SE% of section 9, township 11 south, range 16 east; number of shares dedicated to said lands, 80; amount due on principal, $2,-800, with interest thereon from the 1st day of April, 1911.”

And the appellee alleged that, according to the terms of the appellants’ contracts, the aforesaid sums bear interest at the rate of 8 per cent, per annum. It is not denied that by the terms of the contract the rate of interest was fixed at 8 p.er cent, per annum, but the defendants to the suit set up by answer that the amount of water to which, under the contracts, they were entitled was 2% acre feet per acre, and here insist that they should not be required to pay any interest until that amount of water is so furnished them, and in no event should they be required to pay interest in excess of 6 per cent, per annum.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sallee v. Commonwealth Trust Co. of Pittsburgh
8 F.2d 227 (Ninth Circuit, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
295 F. 103, 1924 U.S. App. LEXIS 3153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glavin-v-commonwealth-trust-co-ca9-1924.