Glading v. Frick

88 Pa. 460, 1879 Pa. LEXIS 79
CourtSupreme Court of Pennsylvania
DecidedJanuary 6, 1879
StatusPublished
Cited by8 cases

This text of 88 Pa. 460 (Glading v. Frick) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glading v. Frick, 88 Pa. 460, 1879 Pa. LEXIS 79 (Pa. 1879).

Opinion

Mr. Justice Paxson

delivered the opinion of the court, January 6th 1879.

Wliat the precise ground was on which the verdict was set aside and judgment entered on the point reserved in favor of the plaintiffs below the record does not show. Against the mechanic’s ¡lien of the plaintiffs the defendants set up a written contract between Glading, the owner, and Franklin .Cassel, the contractor, for the erection of the building against which the lien was entered. The object of the evidence was to secure for the owner the benefit of the provisions of the Act of Assembly of 3d of April 1872, that where any building or buildings should'be erected in whole or in part by contract in writing, such building or buildings, and the land or lands whereon it or they shall stand, should be liable to the contractor alone for work done or materials furnished in pursuance of such contract, provided the contract should be acknowledged and duly recorded in the office for recording deeds within fifteen days after its execution. It was agreed at the trial on the part of the defendants that the book of original entries of the plaintiffs was correct; that the materials charged were delivered and used in the construction of the building; and that there were certain specifications for reference by both parties which were not recorded. And it was admitted on behalf of the plaintiffs that the house was not built according to the specifications ; that all extra work had been paid for; and that the contractor had been fully paid.

When it was proposed to give the contract in evidence the plaintiff's objected to it, because “1. The whole contract was not offered, the specifications referred to in it, and made part of it, not being offered with the contract; 2. The whole contract was not recorded as required by the Act of Assembly, the specifications, being a part of the contract, not having been recorded; and 3. The contract was not properly recorded, having been recorded in a deed-book and not in a miscellaneous book.” The paper was admitted, and a verdict directed for the defendants, the question whether the evidence was properly received being reserved by the court for subsequent consideration. Judgment was afterwards entered in favor of the plaintiffs, notwithstanding the verdict for the defendants. It would have been a more correct practice for the court to have directed a verdict for the plaintiffs. The defendants could then have moved for judgment in their 'favor non obstante veredicto. It was held in [462]*462Robinson v. Myers, 17 P. F. Smith 9, that a judgment could not be entered upon a reserved point for the plaintiff when the verdict was for the defendant, for the reason that such judgment would have no verdict to support it. In the case in hand the admissions, of record by the parties to some extent supply the place of a verdict, and it is possible the judgment might be sustained were-there nothing else in the ease.

Regard being had to the object of the defendants in offering the contract, it is not apparent how that object would have been promoted by accompanying it with proof of the specifications to which it referred. The owner of a lot of land, and the contractor for the erection of a building on it, were the only parties by whom it had been executed. The plaintiffs did not need the omitted evidence, for the accuracy of their books and the use of their materials for the purposes of the defendants had been admitted. The defendants were invoking the protection of the Act of 1872, and proposed to show that the building had been erected under a written contract. Evidence is essential when its production is required to bring out the whole of the special subject of dispute. If it bears upon the point in issue, it is relevant. If the point in issue cannot be determined without it, then its absence is a defect fatal to the case of which it should form a part. The question here was, whether Mr. Glading’s house had been built under a written contract with Mr. Cassell. The question of the compliance by either party with the specifications was between them alone. They were a part of the contract by reference only, and their production could have added no strength to the proof of the principal fact involved. They were not necessary to construe the contract, for the plaintiffs had no such interest as gave them the right to demand its construction. They were not necessary to adjust equities or settle accounts, for they could have exhibited no equities and explained no accounts with which the plaintiffs could have had any concern. The instrument was offered to establish the immunity of the defendants under the statute, and for that purpose the production of the specifications was not essential.

In the second place, it was objected that the contract was not “duly recorded,” because the specifications were not placed on record.' The purpose of the legislature was to afford notice to mechanics and material-men of the existence of a written contract, which would bar their claims against a property on which a building should be erected, and leave them to such remedy against the contractor as they could enforce. This purpose was adequately gained by the record of the contract without the specifications. An inspection of the contract was all that was needed to show the existence of the specifications, which were referred to as being “ in the possession of Solomon A. Kneedler.” Such a reference was enough to put all persons who could be interested upon inquiry. While [463]*463they formed, as to the immediate parties, essential parts of the contract, they could have no bearing upon agreements into which other parties should afterwards enter. A peculiar state of facts ought to exist to make the recording of auxiliary documents like this indispensable. It is possible to conceive of specifications that would contain plans, drafts or models of a kind to render their transfer to the record impossible, or at least intolerably inconvenient. A contract could provide for the duplicate of a house already built. It might stipulate for tho production of machinery identical with machinery already finished and in operation. And it would in either instance be an instrument no more complete in itself than this instrument. The rule that annuls the effect of an unrecorded agreement, which forms a part of a single transaction, has no room to operate in such a case as this. Friedley v. Hamilton, 17 S. & R. 70, and the line of cases following it, do not apply.

In the final objection to the admission of the contract in evidence, the ground was taken by the plaintiff that the record was defectivo because it was entered in one of the deed-books instead of the miscellaneous book, and Luch’s Appeal, 8 Wright 519, was relied upon to sustain this position. The particular point decided in that case was that the record of a mortgage in any other than a “ mortgage-book” was valueless and void as against a later lien ; in other words, that in view of the immemorial usage under the statutes, a mortgage thus entered was not recorded at all. It is but just to the learned court below to say that it required no strain to bring this caso within the spirit and reasoning of Luch’s Appeal. A careful consideration of the subject, however, has led us to seriously doubt the soundness of the principles upon which Luch’s Appeal was decided. No one of the present bench was a member of the court at the time that case was ruled, and we have hesitated in disturbing what appears to have been a unanimous decision of our predecessors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prouty v. Marshall
74 A. 550 (Supreme Court of Pennsylvania, 1909)
Casey v. Canning
39 Pa. Super. 94 (Superior Court of Pennsylvania, 1909)
Prouty v. Marshall
36 Pa. Super. 527 (Superior Court of Pennsylvania, 1908)
Slover v. Bailey
90 P. 665 (Oregon Supreme Court, 1907)
Mohr v. Scherer
30 Pa. Super. 509 (Superior Court of Pennsylvania, 1906)
Schenck v. Burgess
37 A. 258 (Supreme Court of Pennsylvania, 1897)
Farabee v. McKerrihan
33 A. 583 (Supreme Court of Pennsylvania, 1896)
Ringle v. Penna. R. R.
30 A. 492 (Supreme Court of Pennsylvania, 1894)