Glacial Plains Cooperative v. Chippewa Valley Ethanol Co.

897 N.W.2d 834, 2017 WL 2535725, 2017 Minn. App. LEXIS 72
CourtCourt of Appeals of Minnesota
DecidedJune 12, 2017
DocketA16-1626
StatusPublished
Cited by1 cases

This text of 897 N.W.2d 834 (Glacial Plains Cooperative v. Chippewa Valley Ethanol Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glacial Plains Cooperative v. Chippewa Valley Ethanol Co., 897 N.W.2d 834, 2017 WL 2535725, 2017 Minn. App. LEXIS 72 (Mich. Ct. App. 2017).

Opinion

OPINION

KIRK, Judge

We affirm the district court’s entry of judgment against appellant following a court trial of respondent’s breach-of-contract claim because the district court did not err by (1) rejecting appellant’s argument that the parties’ contract was terminable at will or (2) ordering appellant to specifically perform the contract.

FACTS

This appeal arises out of a contractual dispute between appellant Chippewa Valley Ethanol Company LLLP (CVEC) and respondent Glacial Plains Cooperative (GPC). The parties’ relationship stems from a grain-handling contract (the contract) executed on November 8, 1994.1 At that time, CVEC anticipated opening an ethanol plant and was seeking additional equity to support the operation. The parties came to an arrangement, memorialized in the contract, whereby GPC would invest in CVEC in exchange for property next to the plant on which to build a grain-processing facility and the exclusive rights to handle grain for the plant.

The terms of the contract created an ongoing relationship between the parties after the ethanol plant and grain-processing facility were built. Paragraph 1 of the contract expressly provides: “It is the intent of the parties that this agreement shall continue indefinitely until either terminated by the terms of this agreement, or by the mutual agreement of both parties.” Consistent with that expressed intent, numerous provisions of the contract provide for continuous performance by both parties. Paragraph 1 provides an initial per-bushel grain-handling fee of 3.2 cents, effective for the first three years of operations, with future fees to be negotiated for successive three-year periods. Paragraph 2 provides for GPC to purchase 200,000 shares of CVEC for $400,000, resulting in its part ownership of CVEC. Paragraph 3 provides for CVEC to transfer to GPC an eight-acre parcel for construction of the grain-handling facility and for the parties to share road-construction costs. Under paragraph 4(H) of the contract, GPC [837]*837agreed “to keep the facility operational, always maintaining the ability to provide enough grain to keep the ethanol plant at full capacity, in a timely manner.” And under paragraph 6(B), CVEC agreed that GPC “shall be the exclusive grain handler to the-... plant, as long as it is complying with all warranties and agreements” and “continue[s] to be able to handle the full capacity of corn required to run the ... plant.”

The contract does not include an express termination clause. However, paragraph 5 of the contract provides that, if GPC fails to perform its obligations under the contract, “[CVEC] shall have the right to declare that this contract has been breached.” In the event of a declared breach, GPC has 30 days to cure. If the breach is unresolved, GPC must deed the real estate and grain-processing plant to CVEC in exchange for compensation determined by formula under the contract. Disputes over breaches by GPC under paragraph 5 are subject to arbitration.

The parties commenced operations in 1996 and proceeded under the contract for more than a decade before their relationship began to sour, resulting in litigation. In 2011, CVEC sued GPC, alleging breaches of the contract and seeking its termination. The 2011 action was submitted to arbitration, and a panel of arbitrators awarded damages to CVEC for one material breach but found that GPC did not otherwise materially breach the contract and did not order termination of the contract. In February 2015, the district court issued an order confirming the arbitrators’ determinations in relation to the alleged breaches of the contract, but vacating the arbitrators’ ruling on an exclusivity provision of the contract not subject to the arbitration clause.

In June 2014, after the arbitration panel issued its final award but before the district court issued an order affirming in part and vacating in part that award, CVEC notified GPC of CVEC’s intent to terminate the contract. In response, GPC initiated this- action to .preclude CVEC from repudiating the contract.

CVEC moved for summary judgment, arguing, inter alia, that the contract was one for an indefinite duration that could be terminated by either party at will. GPC opposed summary judgment, arguing that the contract was for a perpetual duration, unless and until GPC breached the contract and CVEC took oyer the operations under paragraph 5 of the contract. The district court denied CVEC’s summary-judgment motion, reasoning that the contract was intended to continue indefinitely and that the parties’ intent overcame the general rule that a contract of indefinite duration is terminable at will. The district court concluded that “the only way the Contract can terminate under its terms is if GPC defaults on its duties to CVEC. In other words, it is written so as to continue so long as GPC performs satisfactorily.”

The district court subsequently held a bench trial and issued findings of fact, conclusions of law, and an order for judgment, requiring CVEC’s. specific performance of the contract. The district court found that CVEC, through its general manager who assumed that role in 2009, had engaged in a course of conduct aimed at “escaping] its obligations under a contract it felt was no longer to its economic advantage.” The district court concluded that CVEC had “breached the contract by its unilateral attempt to terminate [it],” and that specific performance was the'appropriate remedy because it could not “accurately determine the value of GPC’s expectancy under the Contract.”

CVEC appeals, challenging both the district court’s determination that the con[838]*838tract is not subject to termination at will and it’s order for specific performance.

ISSUES

I. Did the district court err by determining that the contract is not subject to termination at will?

II. Did the district court err by granting the remedy of specific performance?

ANALYSIS

I. The district court did not err by determining that the contract is not terminable at will.

CVEC argues that the district court erred by entering judgment for GPC because the contract was for an indefinite duration and thus subject to termination at will by either party. On appeal from judgment following a bench trial, this court reviews findings of fact for clear error and conclusions of law de novo. In re Distrib. of Attorney’s Fees, 855 N.W.2d 760, 761 (Minn. App. 2014), aff'd, 870 N.W.2d 755 (Minn. 2015). “The primary goal of contract interpretation is to determine and enforce the intent of the parties.” Travertine Corp. v. Lexington-Silverwood, 683 N.W.2d 267, 271 (Minn. 2004). Where there is a written contract, this court must look to the language of the contract to determine intent. Storms, Inc. v. Mathy Constr. Co., 883 N.W.2d 772, 776 (Minn. 2016). We “construe a contract as a whole and attempt to harmonize all of its clauses.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glacial Plains Coop. v. Chippewa Valley Ethanol Co., LLLP
912 N.W.2d 233 (Supreme Court of Minnesota, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
897 N.W.2d 834, 2017 WL 2535725, 2017 Minn. App. LEXIS 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glacial-plains-cooperative-v-chippewa-valley-ethanol-co-minnctapp-2017.