GIW Industries, Inc. v. JerPeg Contracting, Inc.

530 F. Supp. 2d 1323, 2008 U.S. Dist. LEXIS 2051, 2008 WL 110618
CourtDistrict Court, S.D. Georgia
DecidedJanuary 10, 2008
DocketCV 106-127
StatusPublished
Cited by3 cases

This text of 530 F. Supp. 2d 1323 (GIW Industries, Inc. v. JerPeg Contracting, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GIW Industries, Inc. v. JerPeg Contracting, Inc., 530 F. Supp. 2d 1323, 2008 U.S. Dist. LEXIS 2051, 2008 WL 110618 (S.D. Ga. 2008).

Opinion

ORDER

LISA GODBEY WOOD, District Judge.

This matter comes before the Court on Defendants’ motions for summary judgment. (Doc. nos.41, 57.) Upon the following, Defendants’ motions are GRANTED IN PART and DENIED IN PART.

I. STATEMENT OF THE CASE

GIW Industries, Inc. (“GIW”) brought this dispute against its former employee, Alvin Charles Quackenbush, its former contractor, JerPeg, Inc. (“JerPeg”), and JerPeg’s owners, Jerry and Margaret (“Peg”) Soultz. In its complaint, GIW alleges that JerPeg breached nineteen purchase order (“PO”) contracts by failing to perform, either partially or entirely, under the terms of the contracts. (CompU 23.) Next, GIW alleges that JerPeg and the Soultzes committed fraud by submitting invoices and otherwise making representations that the work was completed satisfactorily under the aforementioned PO contracts. (Id. ¶¶ 27-29.)

As to Defendant Quackenbush, GIW alleges two claims. First, GIW alleges Quackenbush defrauded GIW by approving the JerPeg invoices for payment on projects he knew or should have known were incomplete or not done. (Id. ¶¶ 30-31.) In addition, GIW alleges that, by approving these invoices, Quackenbush breached his duty of loyalty and good faith. (Id. ¶ 36.) As required at this stage in the proceedings, the following facts are viewed in a light most favorable to GIW, the nonmovant.

II. FACTUAL BACKGROUND

On April 15, 2003, GIW, a slurry pump manufacturer, hired Quackenbush as Plant Engineer for its Grovetown and Thomson Georgia plants. In this capacity, Quacken-bush was charged with overseeing various capital projects involving plant maintenance. Quackenbush was also authorized to prepare bid documentation and contracts to carry out this work. (See Harris Dep. at 10-11, Ex. 1.) For a service contract, because the work performed does not normally go through receiving, Quack-enbush was required to sign the invoices to attest that the work was completed in a workmanlike manner. (Harris Decl. ¶¶ 5, 14.) Quackenbush’s signature directed GIW’s accounting employees to pay the invoice. (Harris Dep. at 121.)

JerPeg is an Indiana corporation owned by Jerry and Peg Soultz. Mr. and Ms. Soultz are the only officers of JerPeg, and they are JerPeg’s sole shareholders. *1327 (Soultz Dep. at 18-19. 1 ) Quaekenbush first worked with JerPeg on a project around 1986. Since that time, Quacken-bush and the Soultzes maintained an ongoing social relationship. The Soultzes attended a Quaekenbush wedding and graduation. (Id. at 40.) After taking the job as Plant Engineer with GIW, Quack-enbush contacted Mr. Soultz about some of the projects he was in charge of for GIW. (Id. at 32.) As a result, from July 2003 until November 2005 JerPeg worked on multiple projects at GIW, including the nineteen POs which are at issue in this case. (See Compl. ¶¶ 10-16.)

GIW’s PO contracts contain language explicitly stating: “MODIFICATION OF AGREEMENT. This purchase agreement may not be modified except by a writing signed by both Buyer and Seller.” 2 (Harris Decl. ¶ 11, Ex. A.) Thus, pursuant to the plain terms of the POs, any modifications to the PO contracts were required to be in writing. Nevertheless, during the course of JerPeg’s performance, there were times when Quaekenbush would change the scope of the work after the purchase order had been issued and “trade out” work of equivalent value. (Soultz Dep. at 81; Quaekenbush Dep. at 121-22.) Quaekenbush believes that all swapped work “balanced out.” (Quaekenbush Dep. at 270-71.)

For example, PO G-45886 called for Jer-Peg to “remove gantry across driveway and install air compressor dense phase sand system.” (Defs.’ Ex. 1.) Mr. Soultz acknowledged that JerPeg did not do the work on this PO “in whole or in part.” (Soultz Dep. at 76-77.) Instead, JerPeg invoiced for work to “fabricate and install additional transporter; tie B tank together & all remedial work necessary as per [engineering.” (Defs.’ Ex. 2.) The amount JerPeg invoiced under this PO matches precisely the amount set forth in the PO, even though JerPeg performed completely different work. (Soultz Dep. at 80-81.) Quaekenbush testified that he did not issue change orders for this work because he claims no one at GIW ever “told me to do a change order or how to do a change order.” (Id. at 144-45.) Charles Harris, Quackenbush’s supervisor, filed an affidavit which contradicted Quackenbush’s testimony. Specifically, Harris stated:

I informed Quaekenbush that if the scope of the work changed he had to get a revised quote from the vendor. I also informed Quaekenbush that if a change was outside the original amount of the [pjurchase [ojrder, a change order should be issued.

(Harris Decl. ¶ 12.)

Another disputed issue with respect to the PO contracts involves invoicing. According to JerPeg, Quaekenbush suggested it use the language on the invoices that followed the language of the PO, even when the actual work performed varied from the PO description. (Quaekenbush Dep. at 121-22 (“[W]e traded off some work, and I told them to just follow the wording on the purchase order.”)) Contrarily, GIW points to the fact that Quack-enbush also testified that “I never told [JerPeg] how to actually word an invoice. It was normally just copied off the purchase order.” (See id. at 121.) In fact, when asked why he would tell contractors *1328 to follow the language of the PO, Quacken-bush clarified, “I [ ] would tell them, hey, write down what we did, write it down.” (Id.) Regardless, JerPeg’s invoice description usually mirrored that of the PO, even if the work performed was different than the PO description. 3 In many instances, JerPeg also noted on its invoices that the work had been done “AS PER AL QUACKENBUSH” (or some similar language) to indicate that Quackenbush had directed what was to be done. (See generally Defs.’ Ex.App.)

For example, PO G-52473 called for Jer-Peg to “fabricate four load stands certified for 35,000 lbs each to be used for Toshiba tablet[.][T]able weight 105,000,” which is exactly what JerPeg invoiced. (See Defs.’ Exs. 20, 21.) However, the stands JerPeg provided were never certified to hold the requisite weight. In fact, Mr. Soultz acknowledged in deposition that anyone at GIW relying solely on the PO or invoice would have no way of knowing that the stands were not certified. (Soultz Dep. at 118-19.)

One of GIW’s biggest projects with Jer-Peg, encompassing seven of the nineteen POs at issue in this case, concerned the foundation required for installation of a specific machine. (See Defs.’ Exs. 23-35.) Mr. Soultz acknowledged that JerPeg (1) invoiced GIW for “preparatory work on drawings and PE stamp for Toshiba machine foundation as per our proposal”; (2) charged $67,750 for that work; (3) received payment; and (4) never provided a PE stamp to GIW. (Soultz Dep. at 130, Defs.’ Ex. 26.) Although Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
530 F. Supp. 2d 1323, 2008 U.S. Dist. LEXIS 2051, 2008 WL 110618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/giw-industries-inc-v-jerpeg-contracting-inc-gasd-2008.