Gist v. Johnson-Carey Co.

147 N.W. 1079, 158 Wis. 188, 1914 Wisc. LEXIS 289
CourtWisconsin Supreme Court
DecidedOctober 6, 1914
StatusPublished
Cited by7 cases

This text of 147 N.W. 1079 (Gist v. Johnson-Carey Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gist v. Johnson-Carey Co., 147 N.W. 1079, 158 Wis. 188, 1914 Wisc. LEXIS 289 (Wis. 1914).

Opinion

The following opinion was filed June II, 1914:

BjeewiN, J.

It is assigned as error that the court erred in refusing to answer question number 2 of the special verdict $107,728.10, and in refusing to instruct the jury in reference to question number 2 as requested, and in refusing to include in the special verdict questions proposed by counsel for defendant.

These assignments of error go to the point insisted upon by counsel for appellant, namely, that the plaintiffs were bound by the alleged contract set up in the complaint as having been executed on April 25, 1910, and remade afterwards, and also by estoppel. It was conceded, after plaintiffs rested, that this contract, although alleged to have been executed on April 25, 1910, and bearing that date, was in fact fully executed and delivered on April 24, 1910, which was Sunday, and was therefore void. The defendant, however, contends that, since the plaintiffs set up this contract in their complaint and made proof of the execution of the work under it, they adopted it, and that their acts amounted to the making of a neAV contract on the terms of the Sunday contract, therefore they are bound by it. This contention is not consistent with counsels position on the trial, since he insisted there, after plaintiffs had made their proof, that the contract set up in the complaint was void because executed on Sunday, therefore no recovery could be had on it.

The contract having been made and delivered on Sunday was void and incapable of ratification. King v. Graef, 136 [195]*195Wis. 548, 117 N. W. 1058; Pearson v. Kelly, 122 Wis. 660, 100 N. W. 1064; Sherry v. Madler, 123 Wis. 621, 101 N. W. 1095. It is insisted, however, by counsel for appellant that a new contract was made by the parties on the same terms as the Sunday contract and that their acts in execution of the Sunday contract and in performing the work under it show this. We cannot agree with counsel in this contention. We think the evidence not only fails to show a new contract, but on the contrary shows that no new contract was made. In order to make a contract on the terms specified in the Sunday contract the minds of the parties must meet on the terms of the contract. The acts shown in execution of the work were clearly done, and so understood by the parties, under the Sunday contract. And it further appears that in the execution of the work and performance under the Sunday contract the parties did not agree upon its terms, especially on the terms respecting classification and estimates. Neither party, upon the undisputed evidence, had any thought of making a new contract on the terms of the Sunday contract, but both were operating under the Sunday contract, the construction of which they did not even agree upon.

Even if acts of the parties under a void contract could have the effect of infusing into it life by way of creating a new contract, the execution must be such as to bring the minds of the parties in accord upon all terms of the contract. This clearly was not the case here. The Sunday contract was not even fully executed or the terms of it either agreed upon or performed, at least as to payment or amount due, after the day of its execution, April 24, 1910.

The court below was asked to change the answer of the jury to the second question of the special verdict from $130,000 to .$107,728.10, the theory of counsel for appellant being that, if a new contract was made on the terms of the Sunday contract, the amount of plaintiffs’ recovery would be limited to $107,728.10 less the amount paid. No issue of new con[196]*196tract was made by tlie pleadings or insisted upon, before tbe plaintiffs rested, and as soon as the question was raised that the contract was made on Sunday, therefore void, further proceedings were had on quantum meruit. No request was made to submit to the jury the question whether a new contract had been made, and the court below was therefore authorized to find on the subject under sec. 2858m, Stats. The evidence was ample to show no new contract was made; indeed it is very doubtful whether there was sufficient evidence to support a finding that a new contract on the terms of the Sunday contract was made. But we need not and do not decide that question.

Partial payments made under a Sunday contract are not sufficient to import a new contract. Vinz v. Beatty, 61 Wis. 645, 21 N. W. 781; Troewert v. Decker, 51 Wis. 46, 8 N. W. 26; Reeves v. Butcher, 31 N. J. Law, 224; Pillen v. Erickson, 125 Mich. 68, 83 N. W. 1023; Melchoir v. McCarty, 31 Wis. 252; Williams v. Lane, 87 Wis. 152, 58 N. W. 77. Moreover, the payments made were made under monthly estimates, and were not final estimates, but subject to change both as to estimates and classification of material.

A contention is made by counsel for appellant that prior to the date of the Sunday contract and on April 20; 1910, plaintiffs sent a telegram to defendant offering to do the work, and because it afterwards did the work there was created a contract prior to the Sunday contract, similar substantially to the Sunday contract. This contention cannot be sustained for many reasons. It is clear from the evidence that the work was not done under such alleged contract and that the parties never understood that it was; that no contract similar in terms to the Sunday contract ivas made prior to April 24, 1910. The defendant did not even request the siibmission to the jury of a question as to whether such a contract was made.

After the work had been partially performed a controversy arose between plaintiffs and defendant as to classification of material being removed by plaintiffs, the plaintiffs claiming [197]*197a different classification than that being made by defendant in its monthly estimates. Thereupon defendant sent to George T7. Gist, one of the plaintiffs, the following telegram: “In case no classification is given you, do you wish to pull off that work ? Would like to know it now as we have outfit and organization ready to install. Answer.” Defendant claims plaintiffs did 'not answer, as Carey, of defendant company,' testified that he did not receive any reply. Carey further testified that after sending the telegram he had a talk with Gist, of plaintiff company, about pulling off the work, and asked him if he did not want to pull off, and that Gist said he had been to great expense getting on’there and did not feel like pulling off. That Carey then offered him $1,000 or $2,000 if he would pull off. Carey testified: “I told him if it was not satisfactory to him he could pull off. I don’t remember just what he said, but he didn’t want to.” Gist testified that he replied to the telegram and that about eighty per cent, or more of cut number 1 had been excavated when the telegram was received.

It is quite obvious from the evidence that defendant did not consider it had the right to discharge plaintiffs. The evidence merely shows that defendant was endeavoring to get an agreement with plaintiffs to discontinue the work. Even if it be conceded that defendant had the right to force terms or require plaintiffs to quit, the evidence does not show that it did so. Had the defendant given plaintiffs peremptory orders to “pull off” or continue under classification as claimed by defendant, the situation would he different.

Plaintiffs continued on the work to completion, and it is clear from the evidence that no agreement was made as to classification or terms of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perry v. Milwaukee Board of School Directors
388 N.W.2d 638 (Court of Appeals of Wisconsin, 1986)
Rosenbush Feed Co. v. Garrison
37 So. 2d 106 (Supreme Court of Alabama, 1948)
Smith v. Mills
24 So. 2d 864 (Mississippi Supreme Court, 1946)
Welch v. Land Development Co.
16 N.W.2d 402 (Wisconsin Supreme Court, 1944)
Krueger v. Groth
209 N.W. 772 (Wisconsin Supreme Court, 1926)
Seifert v. Dirk
184 N.W. 698 (Wisconsin Supreme Court, 1921)
Gist v. Equitable Surety Co.
151 N.W. 382 (Wisconsin Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
147 N.W. 1079, 158 Wis. 188, 1914 Wisc. LEXIS 289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gist-v-johnson-carey-co-wis-1914.