Gilmore's Farm, Inc. v. Herc Rentals, Inc.

District Court, E.D. North Carolina·Decided November 5, 2021·No. 5:20-cv-00578·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF NORTH CAROLINA WESTERN DIVISION No. 5:20-CV-578-BR GILMORE’S FARM, INC., ) ) Plaintiff, ) ) - v. ) ) HERC RENTALS, INC., ) ORDER ) Defendant/Third-Party Plaintiff, ) ) v. ) ) ASIA EXCAVATING SERVICE, INC., et al., ) ) Third-Party Defendants. ) This matter is before the court on Plaintiff Gilmore Farm Inc.’s motion to modify the scheduling order and to inspect equipment, [DE-48], and Defendant Herc Rentals, Inc.’s motion for a protective order, [DE-50]. Responsive briefing is complete, [.DE-52, -53], and the motions are ripe for decision. For the reasons that follow, the motion to modify the scheduling order and to inspect equipment is denied and the motion for protective order is allowed. I. BACKGROUND This action, asserting claims for breach of contract, unfair and deceptive trade practices, and negligence after a piece of equipment Gilmore’s Farm rented from Herc Rentals caught fire, was removed to this court on November 3, 2020. [DE-1]. Following removal, Herc Rentals filed a motion to dismiss, [DE-5], which the court subsequently denied, [DE-47], and a third-party complaint, [DE-8]. On January 29, 2021, the parties filed an amended status report on scheduling that set forth a two-phased discovery plan to allow for early mediation, [DE-20], and the court

subsequently entered a scheduling order setting, among other things, a March 1, 2021 deadline to inspect the damaged equipment, [DE-21]. Herc Rentals filed a First Amended Third-Party Complaint, [DE-23], and a Second Amended Third-Party Complaint, [DE-32], but later dismissed all claims against third-party defendant Komatsu America Corp., [DE-42]. The parties engaged in mediation on August 16, 2021, which resulted in an impasse, [DE-43], and they subsequently filed a supplemental phase two discovery plan, [DE-45]. The court entered its Phase II Scheduling Order on September 20, 2021, which approved the parties’ plan and set, among other things, expert witness deadlines. [DE-46]. On October 7, 2021, Gilmore’s Farm filed the instant motion to modify the court’s scheduling order to allow it to inspect the equipment at issue in this case and to extend expert deadlines. [DE-48]. Herc Rentals opposes Gilmore’s Farm’s motion and sought a protective order prohibiting both the equipment inspection and the disclosure of an expert witness by Gilmore’s Farm. [DE-50]. If. DISCUSSION Plaintiff's request to inspect the equipment and to disclose an expert requires amendment of the scheduling order. Under Fed. R. Civ. P. 16(b)(4), an amendment to a scheduling order requires a showing of “good cause” and leave of court. See Fed. R. Civ. P. 16(b)(4). The good cause standard does not focus on the prejudice to the non-movant or bad faith of the moving party, but rather on the moving party’s diligence. Franklin Livestock, Inc. v. Boehringer Ingelheim Vetmedica, Inc., No. 5:15-CV-63-BO, 2016 WL 7613690, at *2 (E.D.N.C. Sept. 26, 2016). However, here the inspection deadline sought to be extended has already run and, thus, the more specific requirements of Fed. R. Civ. P. 6(b)(1)(B) applies. See Colony Apts. v. Abacus Project Memt., Inc., 197 F. App’x 217, 222-24 (4th Cir. 2006). Rule 6(b)(1)(B) provides in pertinent part □

that “[w]hen an act may or must be done within a specified time, the court may, for good cause, extend the time . . . on motion made after the time has expired if the party failed to act because of excusable neglect.” See also Harrison v. City of Greenville, No. 4:15-CV-17-BO, 2016 WL 4523901, at *3 (E.D.N.C. Aug. 22, 2016) (“A finding of excusable neglect is required in order to extend the time for filing where a motion to do so has been filed beyond the prescribed period.” (citing Fed. R. Civ. P. 6(b)(1)(B))). Whether neglect is excusable is “at bottom an equitable [inquiry], taking account of all relevant circumstances surrounding the party’s omission[.]” Thompson v. E.I. DuPont de Nemours & Co., Inc., 76 F.3d 530, 533 (4th Cir. 1996) (quoting Pioneer Invs. Serv. Co. v. Brunswick Assoc. Ltd. P’ship, 507 U.S. 380, 395 (1993)). ““Excusable neglect’ is not easily demonstrated, nor was it intended to be.” Jd. at 534. “In determining whether a party has shown excusable neglect, a court will consider: (1) the danger of prejudice to the non-moving party; (2) the length of delay and its potential impact on judicial proceedings; (3) the reason for the delay; and (4) whether the movant acted in good faith.” Colony, 197 Fed. App’x at 223 (citing Thompson, 76 F.3d at 533). The most important factor is the reason for the delay, but merely establishing these factors does not entitle the moving party to relief. Jd Instead, “whether to grant an enlargement of time still remains committed to the sound discretion of the district court.” Jd. Furthermore, a court for good cause may issue a protective order forbidding or limiting the scope of disclosure or discovery into certain matters. Fed. R. Civ. P. 26(c)(1)(A), (D). Plaintiff asserts that it refrained from retaining an expert to inspect the equipment because it was optimistic to resolve the case at early mediation and avoid protracted litigation costs. Pl.’s Mot. [DE-48] at 1. Plaintiff claims that during mediation it became apparent that the retention of

an expert was vital to resolving the case at trial or otherwise, but that Defendant has denied Plaintiff and its expert access to the equipment for purposes of inspection. Jd. Finally, Plaintiff asserts that Defendant will not be prejudiced by Plaintiffs expert inspecting the equipment and the time for discovery has not expired. Jd. Defendant opposes the motion and seeks a protective order prohibiting the inspection and preventing Plaintiff from engaging an expert. Def.’s Mem. [DE-51]; Def.’s Resp. [DE-53]. Defendant asserts it relied on Plaintiff's representation that Plaintiff would not inspect the equipment or hire an expert when Defendant performed its own destructive testing of the equipment, agreed to the proposed bifurcated discovery plan, conducted discovery, and participated in mediation. Def.’s Resp. [DE-53] at 4. Defendant contends Plaintiff’s change in strategy is not good cause to alter the scheduling order, and Defendant would be prejudiced by allowing Plaintiff's inspection and retention of an expert at this late stage because Defendant would have to reinspect the equipment, which has been exposed to the elements for eight months since Defendant conducted destructive testing. Id. at 3. The court finds that Plaintiff has failed to demonstrate excusable neglect to reopen the inspection deadline or good cause to extend the expert deadline. The parties’ amended status report, filed on January 29, 2021, belies Plaintiff’s assertion that it did not ascertain the vital importance of inspecting the equipment until after mediation.

Free access — add to your briefcase to read the full text and ask questions with AI

Gilmore's Farm, Inc. v. Herc Rentals, Inc., (E.D.N.C. 2021).

Gilmore's Farm, Inc. v. Herc Rentals, Inc. (Gilmore's Farm, Inc. v. Herc Rentals, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.