Gill v. Bickel

30 S.W. 919, 10 Tex. Civ. App. 67, 1895 Tex. App. LEXIS 18
CourtCourt of Appeals of Texas
DecidedApril 13, 1895
DocketNo. 788.
StatusPublished

This text of 30 S.W. 919 (Gill v. Bickel) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gill v. Bickel, 30 S.W. 919, 10 Tex. Civ. App. 67, 1895 Tex. App. LEXIS 18 (Tex. Ct. App. 1895).

Opinions

WILLIAMS, Associate Justice.

Appellee sued appellant for a balance alleged to be due upon a building contract, by which appellant employed the firm of Bickel & Wellman, of which appellee was a member, to perform for appellant the brick work of a house in the city of Galveston.

The petition alleged, that the contract was made July 9, 1892, by which Bickel & Wellman agreed to perform the brick work, and by which Gill agreed to pay them the sum of $3144; that after the work was partially completed, Wellman, plaintiff’s copartner, received from defendant on account of the contract a sum largely in excess of any to which he was entitled under the contract, and with it fled the country; that he was still beyond the limits of the State, and that his residence was unknown; that the firm was, upon the happening of these facts, dissolved, and that plaintiff on his own account completed the work for defendant in accordance with the contract; that after the completion of the work a controversy arose between plaintiff and defendant as to the amount due plaintiff for the work, and at defendant’s instance they agreed in writing to submit their differences to arbitration, and defendant agreed to pay to plaintiff whatever sum the arbitrators should find to be due; that three arbitrators were named in the agreement, and the matters in dispute were submitted to them, and that after duly considering same they agreed upon and stated their award in writing, which was a full adjustment of all matters submitted, and by which they found to be due to plaintiff the sum of $1231.06, which was greatly less than the amount to which plaintiff was actually entitled. The agreement to submit to arbitration and the award were attached to the petition, and so far as necessary to the decision, their terms will be stated further on. A mechanic’s lien upon the property was also set up. It was further alleged, that both plaintiff *70 and defendant had ratified the award, plaintiff agreeing to accept, and defendant to pay, the amount awarded. Plaintiff further declared upon the original contract, and alleged the doing of extra labor not called for therein, and claimed a balance of $1340.26 was due, for which judgment was asked in case the award should not be upheld. By his original answer defendant excepted to the petition, on the ground that the award was void upon its face, because it did not conform to the agreement of submission, in that it failed to determine defendant’s claim for damages, and in that it failed to dispose of all of the parties to the contract of submission, stating only an alleged indebtedness to A. A. Bickel, and failing to dispose of the claims or rights of Bickel & Wellman.

As defenses, the answer pleaded:

1. A release of the cause of action set up by plaintiff, made October 13, 1893, by John W. Bainbridge, alleged to have been an equal copartner of the firm of Bickel & Wellman.

2. Special denial of any indebtedness to or dealing with plaintiff individually, and of any dissolution of the partnership, with further allegations, that all transactions were with the firm of Bickel & Well-man, and that such firm, prior to July" 30, 1892, was composed of plaintiff and Hiram Wellman, and after said date, and still was composed of those persons and John W. Bainbridge.

3. A plea setting up the terms of the building contract, alleging violations of it and failure to comply with its specifications in many particulars by the builders, and claiming in reconvention several items of damage as resulting to defendant, which were specifically stated. This plea also charged gross misconduct and partiality in the arbitrators in refusing to consider or investigate defendant’s claims, though the same were presented to them in writing; and in finding an indebtedness to Bickel individually, when defendant owed him nothing, and when no claim of his was presented to them.

It was further alleged, that defendant did not agree to arbitrate with Bickel individually, but only with Mm as one of the partners; that the agreement was drawn by Bickel’s attorney, defendant being unrepresented by counsel, and was led to believe that he was contracting to arbitrate with the firm of Bickel & Wellman alone.

To the plea setting up the release of Bainbridge, plaintiff replied that Bainbridge was admitted into the partnership after the building contract was executed, as a silent partner, without authority to collect or expend any money, and had no authority to execute the release, of which defendant had knowledge; and that the release was obtained without consideration, and for the purpose of defrauding plaintiff; that both Wellman and Bainbridge abandoned the work about October 3, 1892, and the partnership was dissolved; or if not then, was so dissolved November 11, 1892, when the work upon the building, for the doing of which alone a partnership existed, was completed.

*71 To the plea attacking the award plaintiff replied, denying the facts alleged, and averred that defendant, subsequent to its return, had, in order to secure an extension of time for payment, ratified it and promised to pay the sum awarded, thereby securing the indulgence. Many facts were also alleged concerning the claim of defendant for damages, which it is unnecessary to state.

There was a prayer, in case plaintiff be not entitled to recover for his own use and benefit, that he recover for the use and benefit of the partnership.

The defendant excepted to the allegations concerning the abandonment by Wellman of the work as not affecting his rights. He also excepted to the allegations concerning Bainbridge’s authority to make the release, and as to the completion of the contract by plaintiff, as irrelvant to the controversy. Defendant also denied that he had ever promised to pay plaintiff individually the amount of the award; but that, misled by plaintiff and his attorneys as to the facts then existing, he promised to pay to Bickel & Wellman, through their attorneys, the amount awarded, upon the giving of a release of the mechanic’s lien; that he was ignorant, without fault or loches on his part, of the facts previously alleged by him invalidating the award; that the gross errors and mistakes of the arbitrators were not, when he promised to pay the award, known to him, but were known to plaintiff and his attorneys, in whom he was placing confidence, and were concealed from him; and that after he learned the facts he refused to abide by the award.

February 19, 1894, the exceptions to plaintiff’s pleadings were overruled. March 22, 1894, plaintiff and Hiram Wellman filed a joint pleading making themselves parties as partners, and adopted the pleadings previously filed by Bickel, and asked that, if Bickel was not entitled to recover individually, plaintiffs be allowed to recover the indebtedness sued for.

The case was tried before a jury, and evidence was heard upon all of the issues made by the pleadings. The testimony as to the right of defendant to damages from faulty work and delay in the completion of the building was conflicting, there being evidence which would have warranted a conclusion that in these and other particulars he sustained damage to a large amount, which had not been allowed him by the arbitrators.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maverick v. Maury
15 S.W. 686 (Texas Supreme Court, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
30 S.W. 919, 10 Tex. Civ. App. 67, 1895 Tex. App. LEXIS 18, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gill-v-bickel-texapp-1895.