Gile v. Albert Construction
This text of Gile v. Albert Construction (Gile v. Albert Construction) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
STATE OF MAINE SUPERIOR COURT CIVIL ACTION YORK, ss. DOCKET NO: CV-05-355
NORMAN C. GILE and ANNE B. GILE,
Plaintiffs
ORDER
KENNETH ALBERT, D/B/A ALBERT CONSTRUCTION,
Defendant
This case comes before the Court on Defendant Kenneth Albert d / b / a Albert
Construction's motion. for summary judgment on all counts of Plaintiffs Norman and
Anne Gile's complaint.' After hearing, the motion is Granted.
FACTS
On or about March 18, 1998, Norman and Anne Gile (the "Giles") contracted
with Defendant, Albert Construction ("Albert"), to build an addition at their Eliot,
Maine residence. The contract provided no start or completion date. Building
commenced in early May of 1998. Shortly thereafter, the Giles experienced difficulty in
financing the project. Consequently, Albert stopped work until satisfied that payment
schedules would be met.
A series of informal discussions between the parties occurred during the
following weeks and culminated with Albert promising to finish the job. The Giles were
under the impression that construction would resume in the late summer of 1998. In
I The motion originally came before the Court on a motion to dismiss. However, both parties agreed to transform the motion into one for summary judgment because matters outside of the pleadings were presented to the Court. See M.R. Civ. P. 12(b)(6). late May or early June of 1998, the Giles were informed by a h r d party that Albert had
no intention of finishung the addition. On August 29, 1998, Albert confirmed that it
would do no further work at the Gile site. The Giles engaged attorney Gary Reiner to
facilitate a settlement.
On May 21, 15399, attorney Reiner, on behalf of h s clients, drafted and sent a
letter to Albert, alleging that Albert's Construction promised to complete the project
and that by failing to do so, had breached the contract. Additionally, the letter claimed
that the Giles had not received proper accounting for the work performed. Attorney
Reiner stated that no 1.egal action would be pursued if the Giles were provided with the
requested accounting, but failure to comply would result in a lawsuit. In a letter dated
November 23,1999 and received three days later, Albert made h s first and only attempt
to provide the requested accounting to the Giles. Attorney Reiner acted as a conduit, as
the information was passed through him to the Giles. The Giles allege that the
proffered accounting i.s incomplete and fraudulent.
The Giles filed a complaint on November 23,2005 allegng breach of contract and
Unfair Trade Practices.
DISCUSSION
The only issue in dispute is the date on whch the cause of action accrued, thus
commencing the six-year statute of limitations time period. The Giles assert that no
judicially cognizable j.njury was sustained prior to obtaining conclusive evidence that
Albert could, or would, not account properly for the material and labor payment. The
Giles claim that Reir~er's letter dated November 23, 1999, indicating that no more
invoices would be forthcoming, marks the occasion. In support of h s motion, Albert
argues that by May 23, 1999, the Giles were aware of their claims for breach of contract and unfair trade practices. Consequently, Albert asserts that the cause of action accrued
on that date.
In Maine a cause of action is commenced by filing the complaint with the Court
or by serving the defendant. M.R. Civ.P. 3. Maine law mandates that a cause of action
for breach of contract be commenced within six years of the date of accrual. 14 M.R.S.A
752. An action accrues when a "judicially cognizable injury is sustained." Dugal v.
Martel, 588 A.2d 744, 7'46 (Me. 1991). In tort, a "judicially cognizable injury is sustained"
when the tortfeasor's "wrongful act produces an injury for whch a plaintiff is entitled
to seek judicial vindication." Id. Under contract law, a cause of action accrues when the
aggrieved party learns the binding obligation has been breached. Jackson v. Borkowski,
627 A.2d 1010,1014 (Me. 1993).
In reviewing a motion for summary judgment, the Court considers the evidence
in the light most favorable to the non-moving party to ascertain whether the record
discloses a genuine dispute concerning a material fact. Parish v. Wright, 2003 ME 90, ¶
8,828 A.2d 778,781. Granting summary judgment is permissible when the resolution of
the dispute depends solely on questions of law. Tisei v. Town of Opnquit, 491 A.2d 564,
568 (Me. 1985). Generally, a determination on a statute of limitations issue is made
either on a motion to dismiss or for summary judgment. Townsend v. Chute Chem. Co.,
1997 ME 46, 9, 691 ,4.2d 199, 202. However, occasionally, the existence of a genuine
issue of material fact as to the date of injury will preclude such rulings. Id.
In the present case, the only issue is when the Giles were aware of a judicially
cognizable injury. The Court finds that the May 21,1999 letter, from attorney Reiner to
Albert, demonstrates i~nequivocallythat the Giles were aware of the alleged breach of
contract and their righ~tto pursue the dispute in a court of law. Most notably, attorney
Reiner threatened Albert with a lawsuit if the project's invoices were not made available, saying "[[tlhe Plaintiffs] contend that you have failed to perform your
contractual obligation for which they are entitled to seek damages amounting to the
differences between what you contracted to do and what it will cost to have the work
completed." A plain reading of the letter establishes that as of May 21, 1999, the Giles
were aware of their right to seek "judiaal vindication." As a result, their cause of action
accrued at that time if not before. See Dugal, 588 A.2d at 746.
Accordingly, the commencement of the cause of action, on November 23,2005, is
more than six years after the accrual date, and thus barred by Albert's statute of
limitations defense.
The entry is:
Defendant Kenneth Albert d / b / a Albert Construction's motion for summary judgment is Granted. Plaintiffs failed to commence their cause of action within the statutorily mandated period.
DATE: A- [ . Ar r Brennan Justice, Superior Court
Norman C . G i l e - I'ro s e - PL Anne B. G i l e - Pro s e - l'L P a t r i c k S. Bedard, E s q . - DEFS
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Gile v. Albert Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gile-v-albert-construction-mesuperct-2006.