Gilbert v. United States

4 Ct. Cl. 290
United States Court of Claims·Decided December 15, 1868·Published·Cited by 1 cases

Opinions

Loring-, J.,

delivered the opinion of the court.

The petitioners in this case are Gilbert & Secor, claiming in their own right, and Courbland Palmer, who claims as assignee and executor of Samuel Dakin, deceased, and as assignee and administrator of Rutherford Moody and Eunice Moody, admin-istratrix of said Rutherford Moody.

The petitioners claim compensation for their dispossession by the United States, on the 1st November, 1856, of a floating dry dock at Mare Island, in the State of California, leased to them by the United States on the 17th March, 1856, for the term of three years therefrom.

And the court find the facts to be that, in pursuance of the acts of Congress of September 28,1850, (9 Stat. L., 516,) and of March 3,1851, (9 Stat. L., 622,) the Hon. William A. Graham, Secretary of the Navy, on behalf of the United States, on the 19th day of May, 1851, contracted in writing with John T. Gilbert, S. D. Dakin, Rutherford Moody, and Zeno Secor, that they, in consideration of the covenants and agreements in said [302]*302contract contained, should furnish all the materials and construct a floating dry dock of ten sections, with all the machinery, fixtures, and appurtenances necessary for working the same, according to the plans and specifications annexed to said contract, to be completed in two years from said 19th day of May, 1851, and placed at such site or point in the bay of San Francisco as the United States should designate.

And the contract provided, among other things, that the' contractors might construct the dock at such place on the coast of the Atlantic or Pacific Ocean as they might prefer, but that all the parts of the dock should be delivered to the United States put together complete, and in every respect ready for use in raising vessels at such point in the bay of San Francisco as the United States should designate before the dock was ready for use; and that the work should be forthwith commenced and progress in its several stages and periods of construction in proportion to the time stipulated for its completion, and should be completed in all respects within two years from and after the date of the contract; and that the contractors warranted the dock should be capable of successfully raising and sustaining for repairs a ship of the line of five thousand and three tons displacement, or a steamer of three hundred and fifty feet in length; and that the experiment for testing the power and capacity of the dock should be performed by and at the expense of the contractors, with a vessel to be furnished by the United States within three months after notice of the completion of the dock.

And, in the language of said contract, it was “further agreed that if the parties of the first part shall fail to comply in each and every particular with the specifications and provisions of this instrument, all the materials of every kind delivered and used upon the work shall be held and used by the United States as their property, as collateral security for advances made, or until a satisfactory adjustment of the case shall be concluded.”

And it was further agreed that all the materials and work of every description, shipped on the Atlantic coast for the said dock in California, should be fully insured and the policies of the insurance should be made payable in case of loss to the United States; and, in case ■ of loss, the insurance for loss or damage paid by or recovered from [303]*303the assurers should be held by the United States until the said materials, lost or damaged, shall have been replaced or the United States fully satisfied that they would be replaced ; and that if any default was made in progressing with the work and in the execution thereof, and especially if the said dock, after completion, should prove insufficient to dock successfully the vessels of the navy according to the warrant aforesaid, the contractors should forfeit and pay to the United States, as liquidated damages, the sums of money which may have been paid to them under the contract, with interest at six per centum, which liquidated damages might be recovered from time to time as they accrued; and the materials were not to be removed until the moneys and interest so advanced should have been refunded, but the said materials were to be held and used as the property of the United States as an additional security for the performance of the contract in all its parts ; and that the said dock should be constructed under the supervision of a competent naval constructor or other person, appointed by the United States, who should have power to reject any materials or workmanship from said dock which in his judgment were not suitable for their purpose, and who should see that said dock was constructed in conformity to said plans and specifications y and the United States covenanted and agreed, in consideration of the premises and of the covenants and agreements in said contract contained on the part of the said contractors, to pay to them, their heirs, executors, administrators, and assignees, the sum of $610,000, at the times and in the sums and manner specified in said contract.

The contractors having, according to the requirement of said contract, prepared the materials of the dock in the city of New York ready for shipment to California, on the 21st of November, 1851, notified the department of the fact, and asked that the place or site in the bay of San Francisco to which the materials should be sent might be designated 5 and, on the 22d November, 1S51, they were informed by the department that the materials might be shipped to San Francisco, and before their arrival there the site for the dock should be designated.

At this time the United States contemplated the construction of a basin or pier at the site of the dock, without which it could not be set up or worked. The vessels laden with the materials of the dock arrived at San Francisco, but the site of the [304]*304dock bad not been fixed nor a basin or piers constructed, and tbns tbe contractors were prevented from unlading and discharging tbeir vessels, and from proceeding in tbe execution of tbeir contract, and incurred expenses in demurrage, &c.

Tbe contractors then proposed to tbe Secretary of tbe Navy that they should select a site for tbe dock and construct a basin or piers for working it, in consideration that they should be allowed to use tbe dock in docking private vessels for tbeir own profit for three years from tbe completion of tbe dock. Tbe Secretary of tbe Navy submitted this proposition to Congress, and, by tbe act of July 21, 1862, (10 Stat. L., 16,) it was provided as follows: “And said dock may be used for tbe purpose of repairing merchant ships when not in use for the government, in such manner and for such compensation, and upon such terms and conditions, as shall be prescribed by tbe Secretary of tbe Navy.77

And, on tbe fourth day of August, 1852, another contract was made by tbe Hon. John P. Kennedy, Secretary of tbe Navy, on behalf of tbe United States, with S. D. Daken, Rutherford Moody, John T. Gibert, and Zeno Secor.

Free access — add to your briefcase to read the full text and ask questions with AI

Gilbert v. United States, 4 Ct. Cl. 290 (cc 1868).

4 Ct. Cl. 290 (Gilbert v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Delaney v. United States
31 Ct. Cl. 44 (Court of Claims, 1895)