This text of 1996 OK CIV APP 12 (Gilbert v. Powder River Natural Gas, Inc.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gilbert v. Powder River Natural Gas, Inc., 1996 OK CIV APP 12, 917 P.2d 1009, 1996 Okla. Civ. App. LEXIS 34, 1996 WL 297417 (Okla. Ct. App. 1996).

Opinion

MEMORANDUM OPINION

GARRETT, Judge:

Keith Gilbert and Iva Gilbert (Appellees or Gilbert) gave Powder River Natural Gas, Inc. (Appellant or Oil Co) an oñ and gas lease dated November 10, 1990. Gübert owned the minerals underlying the property upon which the lease was given. The lease was for a primary paid up term of one year (or until November 10, 1991). Oñ Co completed a well within the primary term and sold production from it until September, 1992, when it was “shut-in”. By letter dated February 15,1995, Gübert made demand on Oü Co that it release the oü and gas lease. Oü Co refused, and did not remove its machinery and fixtures. On April 17,1995, Gübert filed this action to cancel the lease. They also aUeged that Oü Co’s faüure to remove its machinery and fixtures constituted an abandonment. Oñ Co aUeged the lease was valid and in force as a shut-in weü and was capable of producing gas in paying quantities.

Gübert filed a motion for summary judgment and contended the lease had expired by its own terms; and, the lease was not saved by a “cessation of production clause”.1 Gü-bert attached a copy of the lease as eviden-tiary material and an affidavit stating the lease did not produce income. Oü Co objected and contended the weü was capable of producing in paying quantities; and, it had acted prudently in seeking to market production from the weü. Oü Co contended the [1011]*1011shut-in royalty clause2 operated to keep the lease in effect. Therefore, Oil Co contended, there were factual issues in dispute and a jury trial was required. As evidentiary materials, Oil Co attached an affidavit from its president, which stated it had paid royalties to Gilbert until November 1992.

The parties stipulated to certain facts: (1) they had entered into the lease; (2) Gilbert’s were owners of the minerals; (3)' Oil Co claimed an interest as lessee; (4) the lease contained the clause “annual 'payments of shut-in royalty shall not extend this lease for more than three years past the primary term, at which time lease will terminate”; (5) the well produced through September 1992 at which time it was shut-in. The court sustained Gilbert’s motion and entered summary judgment. The court found the lease had terminated in November 1994 by its own terms and, Oil Co’s right to remove its machinery had expired in February 1995. Oil Co appeals.

The evidentiary materials show the lease was to expire upon certain conditions and those conditions occurred. That is, the well was shut in and therefore the lease would terminate no later than three years after the primary term, even if shut in royalties were paid. The cessation of production clause would allow the Oil Co to complete the well or complete reworking of the well past the term of the lease, if it had begun to do so. There was no evidence Oil Co was reworking the lease, only that it had shut in the well due to marketing conditions. Therefore, the cessation of production clause is not applicable.

The lease was a printed form for a paid up lease. It contained a shut-in royalty clause. Attached was a typewritten Exhibit “A” containing fourteen paragraphs of special provisions. It is elementary that the attached special agreements supersede the printed form provisions if a conflict exists.

The shut-in royalty clause generally provides the lease will remain in effect upon the payment of $1.00 per acre per year for an indefinite period. Under this clause, such a payment would be due in November 1992, which was made, and then again in November 1993. There was no evidence of payment. Assuming arguendo such royalties had been properly paid, the general shut-in royalty clause is superseded by the specific clause in paragraph 2 of Exhibit “A” which provided that even if such royalties were paid, the lease could not be extended for more than three years past the primary term. There were no material disputed facts. Summary judgment for Gilbert and against Oil Co was proper.

AFFIRMED.

CARL B. JONES, P.J., and JOPLIN, J., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
1996 OK CIV APP 12, 917 P.2d 1009, 1996 Okla. Civ. App. LEXIS 34, 1996 WL 297417, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gilbert-v-powder-river-natural-gas-inc-oklacivapp-1996.