Gilbert v. Murray Paving Co., Inc.

147 S.W.3d 736, 2003 Ky. App. LEXIS 286, 2003 WL 22519537
CourtCourt of Appeals of Kentucky
DecidedNovember 7, 2003
Docket2002-CA-000160-MR
StatusPublished
Cited by3 cases

This text of 147 S.W.3d 736 (Gilbert v. Murray Paving Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gilbert v. Murray Paving Co., Inc., 147 S.W.3d 736, 2003 Ky. App. LEXIS 286, 2003 WL 22519537 (Ky. Ct. App. 2003).

Opinion

OPINION

JOHNSON, JUDGE.

Clarence Gilbert and his wife, Ozella Gilbert, have appealed from an order entered by the Calloway Circuit Court on December 21, 2001, which granted Murray Paving Co., Inc.’s motion for summary judgment. Having concluded that the trial court erred in determining that there was no genuine issue as to any material fact and that Murray Paving was entitled to judgment as a matter of law, we reverse and remand.

Pursuant to a contract dated March 4, 1999, the Commonwealth of Kentucky, Department of Highways (Department) awarded a highway construction contract to Murray Paving for the purpose of resurfacing portions of two highways in Callo-way County, Kentucky. The Department established the standards for Murray Paving’s work, designed and laid out the work, and provided the project engineer, state *738 inspector and final inspector. The contract required Murray Paving to resurface portions of Highway 94 and Wisewell-Har-ris Road. The resurfacing of Highway 94 1 extended east from Lynn Grove to Murray, for a total distance of 6.493 miles. It is this highway work that is the subject of this appeal.

Murray Paving’s work consisted of applying an additional layer of asphalt to the surface of the pre-existing paved road and paved shoulder wedge. The contract did not provide for any earth work or shoulder work on the side of the roadway adjacent to the paved shoulder or “wedge” 2 of Highway 94. The contract specifically provided that Murray Paving was not to “construct a shoulder for placing the wedge unless specified elsewhere in the Contract.” There is evidence in the record that proper construction methods provide for the wedge to be applied on top of the existing shoulder and the wedge is to be tapered as it proceeds from the roadway’s driving surface to the earthen shoulder. There was no provision under the contract for any work to widen Highway 94 or to extend the paved shoulder. All of the work under the contract was to be performed in accordance with the Department of Highways’ Standard Specifications for Road and Bridge Construction.

Murray Paving began resurfacing the section of Highway 94 on June 28, 1999. The Department assigned its Cadiz field office to supervise the project. Robert Burchett, the resident engineer who supervised the project, furnished Murray Paving with the necessary plans, engineering, and inspection for the resurfacing project. Burchett assigned Cindy Gray, an inspector for the Kentucky Transportation Cabinet, to handle the daily field inspection of Murray Paving’s work. Gray was present at the work site each day as Murray Paving’s work progressed. Gray’s duties included measuring the distance to be resurfaced and staking out the project. Gray’s additional duties included ensuring that the contract specifications were met, ensuring that the proper safety signs were in place, measuring the quantities of the asphalt applied, checking the amount of asphalt being deposited on the roadway, and ensuring that the shoulder edges were as low and as tapered as possible. Gray submitted daily inspection reports as the resurfacing progressed. Gray had the authority to reject any of Murray Paving’s work that did not satisfy the contract specifications.

After the resurfacing was completed, the safety signs, which were the property of Murray Paving, were removed from that work zone and placed on Highway 121, where Murray Paving was to begin work on another highway construction project. Burchett testified that after a project was completed, the Department preferred that the contractor remove the road construction signs within a day or two of the project’s completion date because otherwise, motorists may come to assume that no construction is occurring at any site and hence, ignore the signs.

Pursuant to the contract, Murray Paving initially applied additional asphalt to low spots on the existing paved surface of Highway 94. This process, known as leveling and wedging, requires the application of asphalt to lower spots in the existing roadway so that the roadway’s traveled surface will be smooth when the final resurfacing is applied. The Department directed which low spots were to be filled. *739 As the resurfacing work proceeded, Gray would walk alongside the roadway with the paving machine to examine Murray Paving’s work. Gray testified that she would check the entire resurfacing project from side to side, which presumably included the pavement wedge. Gray testified that in order for the work to comply with the specifications, the goal was to get the shoulder edge, adjacent to the earth, down to a height of one inch “where existing conditions permit.” Gray also stated that in some areas, Murray Paving could not get the roadside edge down to a height of one inch because it “was going down into a ditch,” adding that “[tjhere’s not much you can do about that if we don’t have earth and shoulder to lay on.” Gray further testified that Murray Paving tried everything to get the shoulder down as low as possible, and that in her opinion, “there was nothing else we could do” under the existing conditions. When Murray Paving stopped the resurfacing of Highway 94 on July 10, 1999, based on its belief that the work was completed, the safety signs that had been placed on the right-of-way in the work zone during the work on this portion of the contract were removed.

On July 30, 1999, Clarence Gilbert was operating a tractor-trailer owned by his employer, ABF Freight Systems, on Highway 94 traveling west from Murray, Kentucky, in route to Union City, Tennessee. The weather was clear and the pavement was dry. Gilbert testified that a pickup truck pulling a trailer loaded with hay approached him in the eastbound lane. Although the pickup truck never crossed the highway’s center line, the trailer was weaving and the hay extended six to twelve inches into Gilbert’s lane. In order to avoid the approaching trailer and hay, Gilbert steered his tractor-trailer to the right onto the highway’s rumble strip. 3 Gilbert did not apply his brakes, but he did let off the accelerator. The tractor-trailer’s tires were still on the rumble strip when the pickup truck and trailer passed Gilbert, but immediately thereafter, Gilbert lost control of his tractor-trailer and it left the right side of Highway 94.

Gilbert alleged that he lost control of his tractor-trailer because it dropped off the shoulder. He testified that as he attempted to steer his tractor-trailer back onto the paved surface, its wheels suddenly bounced back onto the highway. As the tractor-trailer returned to the highway, it crossed both lanes of Highway 94 and left the roadway on the south side of the highway. Gilbert was injured as a result of the accident.

On February 2, 2000, Gilbert filed this action in Calloway Circuit Court against Murray Paving, alleging that it had negligently performed the resurfacing of Highway 94 and that it had failed to warn of the dangerous condition on the roadway. 4 On October 29, 2001, Murray Paving filed a motion for summary judgment, which the trial court granted on December 21, 2001.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peters v. Forster
804 N.E.2d 736 (Indiana Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
147 S.W.3d 736, 2003 Ky. App. LEXIS 286, 2003 WL 22519537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gilbert-v-murray-paving-co-inc-kyctapp-2003.