This text of 981 So. 2d 609 (Gilbert v. Florida Power & Light Co.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Dany Katz GILBERT and Lawrence Gilbert, Appellants,
v.
FLORIDA POWER & LIGHT COMPANY, a Florida corporation, Appellee.
District Court of Appeal of Florida, Fourth District.
*611 John N. Buso, West Palm Beach, for appellants.
Rebecca Mercier Vargas and Jane Kreusler-Walsh of Kreusler-Walsh, Compiani & Vargas, P.A., West Palm Beach, and Cheryl A. Kempf of Florida Power & Light, Juno Beach, for appellee.
SHAHOOD, C.J.
Dany Katz Gilbert and Lawrence Gilbert ("Gilbert") appeal three non-final orders in favor of the Florida Power & Light Company ("FPL"). The Gilberts also appeal a separate final judgment in favor of FPL. The issues arise from the removal and payment of such removal of an electric transformer owned by FPL. We consolidate these appeals (case numbers 06-4645 and 07-1274) for purposes of this opinion, affirm two of the non-final orders, reverse the remaining non-final order, and reverse and remand the final judgment.
The Gilberts live in a home next to an easement which FPL owns. On the easement is an electrical transformer that was emitting noise. On May 4, 2004, the Gilberts filed a complaint against FPL, alleging that the sounds from the transformer were "making it virtually impossible for the Plaintiffs to sleep in the subject home, and as a direct result of the sounds the Plaintiffs are suffering both physical and mental damage." The Gilberts further alleged "a clear legal right to use their property without the harm that the transformer is causing them." In relief, the Gilberts sought "a temporary and permanent injunction enjoining FPL from using the offending transformer as well as such other and further relief the Court deems just and proper."
An evidentiary hearing was held on the Gilberts' motion for temporary injunctive relief. At the hearing Dany Gilbert testified that a transformer was placed on the property when she closed on the home. The transformer was eventually replaced for a larger one with a bigger capacity and it made a lot of noise.
On October 18, 2004, the trial court granted the Gilberts' motion and required FPL to move the transformer at the Gilberts' expense. The court reserved jurisdiction to determine the amount of "the land form bond."
The Gilberts filed a motion to set the amount of the bond. After an evidentiary hearing, the trial court set the bond at $16,712 and ordered the Gilberts to post this amount, which they paid into the court registry.
On May 30, 2006, the Gilberts filed a motion for leave to amend the complaint in order to add a count for damages. The trial court denied this motion without explanation on July 12, 2006.
The Gilberts next filed a Motion to Establish a Schedule to Move the Transformer. The trial court granted this motion and ordered FPL to move the transformer within ninety days.
On July 31, 2006, the Gilberts filed another complaint against FPL seeking recovery for damages to the property and for personal injuries.
In response, FPL filed a motion for judgment on the pleadings, arguing that the second lawsuit was barred by the rule against splitting a cause of action. A hearing was conducted on the motion and the trial court granted the motion. The trial court subsequently filed an amended order granting the motion and entered a final judgment.
*612 FPL moved the transformer and, in October of 2006, filed a motion to compel payment of the relocation cost. After a hearing, the trial court granted the motion, directing the clerk to pay FPL the $16,712 deposited in the court registry.
The Gilberts first appeal the following three non-final orders by the trial court: the order granting the Gilberts' motion for temporary injunctive relief, which required the Gilberts to pay for the removal; the denial of the Gilberts' motion for leave to amend the complaint in order to add a count for damages; and the order granting FPL's motion to compel payment of the relocation cost. We reverse the order denying the Gilberts' motion for leave to amend and affirm the remaining orders.
Refusal to allow an amendment is an abuse of the trial court's discretion "unless it clearly appears that allowing the amendment would prejudice the opposing party, the privilege to amend has been abused, or amendment would be futile." State Farm Fire & Cas. Co. v. Fleet Fin. Corp., 724 So.2d 1218, 1219 (Fla. 5th DCA 1998); Carr ex rel. Estate of Grushka v. PersonaCare of Pompano E., Inc., 890 So.2d 288, 289 (Fla. 4th DCA 2004). None of the above factors are present here. The motion to amend was made before the transformer was moved and included a viable claim for damages. We find that the trial court abused its discretion in not allowing the Gilberts to amend their complaint. See Ohio Cas. Ins. Co. v. MRK Constr., Inc., 602 So.2d 976, 978 (Fla. 2d DCA 1992) ("The law favors the trial of cases on their merits and, therefore, a liberal policy of allowing litigants freedom to amend their pleadings exists.").
The remaining non-final orders concern the payment for the relocation of the transformer in satisfaction of the bond for the injunction. The trial court correctly found that the Gilberts must pay this expense based on FPL's tariff, which regulates the provision of electric services. The relevant tariff provides:
5.3 Relocation of Company's Facilities. When there is a change in the Customer's operation or construction which, in the judgment of the Company, makes the relocation of Company's facilities necessary, or if such relocation is requested by the Customer, the Company will move such facilities at the Customer's expense to a location which is acceptable to the Company.
"It is well established that a limitation of liability contained in a tariff is an essential part of the rate, and that the consumer is bound by the tariff regardless of his knowledge or assent thereto. Tariffs are even recognized as having the force and effect of law." Landrum v. Fla. Power & Light Co., 505 So.2d 552, 554 (Fla. 3d DCA 1987) (internal citations omitted); see also Fla. Power Corp. v. Cont'l Testing Labs., Inc., 243 So.2d 195, 197 (Fla. 4th DCA 1971) (holding that a power company's tariff regulation, "having been approved by the Public Service Commission, when enforced without discrimination is binding upon the consumer unless it is plainly unreasonable or outrageous in its general operation").
The trial court had initially set the bond on the basis that it was to pay for the relocation expenses as required by the tariff:
[T]his Court hereby enters an Order Granting Plaintiffs' Motion for Temporary Injunctive Relief, directing the Defendant to remove and relocate the transformer from Plaintiffs' property at the reasonable expense to be borne by the Plaintiff conditional upon the Plaintiff posting a bond to cover the cost of the move.
*613 The Court reserves ruling as to the amount of the land form bond which needs to be posted by Plaintiff pending further testimony.
After the bond was set and FPL relocated the transformer, FPL filed a motion to compel payment, which the trial court correctly granted, explaining:
The Court finds that the Order Granting Temporary Injunctive Relief (the Court construes it as a permanent injunction) specifically required the Plaintiffs to bear the cost of removing and relocating the transformer as mandated by the Florida Power & Light Company tariff.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
981 So. 2d 609, 2008 WL 2038035, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gilbert-v-florida-power-light-co-fladistctapp-2008.