Gilbert /March v. Dept. of Energy

566 P.3d 627, 373 Or. 289
CourtOregon Supreme Court
DecidedMarch 27, 2025
DocketS071487
StatusPublished

This text of 566 P.3d 627 (Gilbert /March v. Dept. of Energy) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gilbert /March v. Dept. of Energy, 566 P.3d 627, 373 Or. 289 (Or. 2025).

Opinion

No. 8 March 27, 2025 289

IN THE SUPREME COURT OF THE STATE OF OREGON

Irene GILBERT, Petitioner, v. OREGON DEPARTMENT OF ENERGY, Oregon Energy Facility Siting Council, and Idaho Power Company, Respondents. (SC S071487)

Irene GILBERT, Petitioner, v. OREGON DEPARTMENT OF ENERGY, Oregon Energy Facility Siting Council, and Idaho Power Company, Respondents. (SC S071520)

Kevin MARCH, Petitioner, v. OREGON DEPARTMENT OF ENERGY, Oregon Energy Facility Siting Council, and Idaho Power Company, Respondents. (SC S071521)

En Banc On judicial review from a final order of the Energy Facility Siting Council. Petitioner Irene Gilbert, La Grande, filed the petitions and briefs pro se; submitted on the briefs December 4, 2024 (S071487) and on December 24, 2024 (S071520). 290 Gilbert/March v. Dept. of Energy

Petitioner Kevin March, La Grande, filed the petition and brief pro se; submitted on the briefs December 24, 2024 (S071521). Jordan R. Silk, Assistant Attorney General, Salem, filed the answering briefs for respondents on review Oregon Department of Energy and Oregon Energy Facility Siting Council. Also on the answering briefs were Ellen F. Rosenblum, Attorney General, and Benjamin Gutman, Solicitor General, Salem. Sara Kobak, Schwabe, Williamson & Wyatt, P.C., Portland, filed the answering briefs for respondent on review Idaho Power Company. Also on the answering briefs were Andrew J. Lee, Schwabe, Williamson & Wyatt, P.C., Portland, and Jocelyn C. Pease, McDowell, Rackner & Gibson, P.C., Portland. BUSHONG, J. The final order of the Energy Facility Siting Council is affirmed. Cite as 373 Or 289 (2025) 291

BUSHONG, J. Two petitioners challenge an amendment to the energy facility site certificate that we addressed in Stop B2H Coalition v. Dept. of Energy, 370 Or 792, 525 P3d 864 (2023), regarding the construction of a high-voltage electrical transmission line from Boardman, Oregon, to Hemingway, Idaho.1 In Stop B2H, we affirmed the Energy Facility Siting Council’s (EFSC) order granting Idaho Power Company’s (Idaho Power) request for a site certificate to construct that transmission line. EFSC subsequently approved Idaho Power’s request to amend that site certificate. Petitioners challenge the process that EFSC followed in addressing Idaho Power’s requested amendment, and, in two respects, the substance of that amendment. Regarding process, petitioners contend that they were entitled to a contested case proceeding to address the substantive issues they have raised, and petitioner Gilbert also contends that the circuit court—not this court—has jurisdiction to decide that issue.2 Petitioners contend in their substantive challenges that: (1) the amended site cer- tificate does not comply with the rules governing the form and amount of the required bond; and (2) the amendment could allow construction within the expanded area without requiring Idaho Power to comply with legal protections for watersheds and fish and wildlife habitats. As we will explain, we conclude that we have juris- diction to address petitioners’ process challenge, and we reject that challenge. We also reject petitioners’ substantive challenges because: (1) the challenge to the form and the amount of the required bond is untimely, because the bond was set in the original site certificate that we approved in Stop B2H and was not changed by the recent amendment; 1 Two petitioners have filed three different petitions challenging the approval of the amended site certificate: case numbers S071487 and S071520, both filed by petitioner Irene Gilbert (Gilbert), and case number S071521, filed by petitioner Kevin March (March). The Energy Facility Siting Council and the Department of Energy have appeared in opposition. We consolidate the three petitions for purposes of this opinion, and, except where noted, refer to Gilbert and March collectively as “petitioners.” 2 Gilbert indicated that she did not dismiss her petition in this court and file in the circuit court because EFSC and Idaho Power insisted that she had to file her petition in this court. 292 Gilbert/March v. Dept. of Energy

and (2) under the governing rules and EFSC’s order, Idaho Power is not permitted to engage in any construction activ- ity in the additional areas that the amendment added to the site boundary. Accordingly, we affirm EFSC’s order approv- ing the amended site certificate. I. BACKGROUND Oregon law provides for “a comprehensive system for the siting, monitoring and regulating of the location, construction and operation of all energy facilities in this state.” ORS 469.310. Under that system, a party who seeks to build an “energy facility” must obtain authority—known as a “site certificate”—from EFSC before it can proceed. See ORS 469.300(11) (defining “energy facility”); ORS 469.320 (site certificate requirement). Because a high-voltage elec- tricity transmission line is generally considered an “energy facility” under ORS 469.300(11), Idaho Power was required by Oregon law to obtain a site certificate from EFSC before it could construct the line. In Stop B2H, we summarized the statutory scheme that governed EFSC’s decision to approve Idaho Power’s request for a site certificate, see 370 Or at 795-97 (discussing statutes), and the process that led EFSC to issue a site certificate for this transmission line, id. at 797-800. Specifically, as we explained in Stop B2H, the site certificate process began when Idaho Power gave notice of its intent to seek a site certificate in 2008. Id. at 797-98. That was followed by years of public meetings and the participa- tion of 17 different public agencies, id. at 798; a contested case proceeding with about 50 petitioners, id. at 799; and, ultimately, a final order by EFSC approving the site certif- icate, id. at 799-800. Three parties petitioned this court to review the final order, and we ultimately affirmed EFSC’s order approving the site certificate. Id. at 795, 821. Idaho Power subsequently asked EFSC to approve an amendment to the site certificate to expand the site boundary and make other changes. Petitioners filed sepa- rate objections and requested contested case proceedings to address their concerns. EFSC denied their requests for con- tested case proceedings and approved Idaho Power’s request Cite as 373 Or 289 (2025) 293

to amend the site certificate.3 Petitioners challenge those decisions in this court. II. DISCUSSION As noted above, petitioners assert process and sub- stantive challenges to EFSC’s orders denying them contested case proceedings and approving Idaho Power’s request to amend the site certificate. We review EFSC’s orders for errors of law in its legal decisions, for lack of substantial evi- dence in its factual findings, and for abuse of discretion in any exercises of discretion. ORS 469.403(6); ORS 183.482(7), (8); see Stop B2H, 370 Or at 800 (so noting). We begin with petitioners’ process challenge. A. Petitioners’ Request for a Contested Case Proceeding As noted above, petitioners contend that they were entitled to contested case proceedings to address their var- ious concerns about Idaho Power’s amendment request. An EFSC rule, OAR 345-027-0371, sets out the process for par- ties to seek a contested case proceeding in connection with a proposed amendment to a site certificate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Save Our Rural Oregon v. Energy Facility Siting Council
121 P.3d 1141 (Oregon Supreme Court, 2005)
Blue Mountain Alliance v. Energy Facility Siting Council
300 P.3d 1203 (Oregon Supreme Court, 2013)
Friends of Columbia Gorge v. Energy Fac. Siting Coun.
498 P.3d 875 (Court of Appeals of Oregon, 2021)
Stop B2H Coalition v. Dept. of Energy
525 P.3d 864 (Oregon Supreme Court, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
566 P.3d 627, 373 Or. 289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gilbert-march-v-dept-of-energy-or-2025.