This text of Gilbane Building Company (Gilbane Building Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gilbane Building Company, (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Gilbane Building Company ) ASBCA No. 57206 ) Under Contract No. W9126G-07-C-0043 )

APPEARANCE FOR THE APPELLANT: Paul H. Sanderford, Esq. Sanderford & Carroll, P.C. Temple, TX

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Lloyd R. Crosswhite, Esq. District Counsel Kendra M. Laffe, Esq. Dawn-Carole Harris, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Ft. Worth

OPINION BY ADMINISTRATIVE JUDGE JAMES

This appeal arises from the contracting officer's (CO's) February 2010 decision which denied the $167,275 certified claim of Gilbane Building Company (Gilbane) that alleged the wrongful government rejection of Gilbane's first elevator subcontractor, PKD, Inc. (PKD). The Board has jurisdiction of the appeal under the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109. The parties have agreed to submit the appeal on the written record under Board Rule 11. The record includes the government's Rule 4 file and the declarations submitted with the parties' briefs. We decide entitlement only.

FINDINGS OF FACT

1. On 11 June 2007, the U.S. Army Engineer District, Fort Worth (USACE) issued Solicitation No. W9126G-07-R-0072 for completion of design and construction of the Battlefield Health and Trauma (BHT) Research Facility, Fort Sam Houston, Texas (R4, tab 4 at 11).

1 Rule 4 cites are to Bates numbers less extra Os, e.g., page "4-000002" is "R4, tab 4 at 2." 2. On 29 September 2007, the USACE awarded Contract No. W9126G-07-C-0043 (BHT contract) to Gilbane for the BHT Research Facility for a $91,998,321 "Guaranteed Maximum Price" (R4, tab 4 at 2-4, 6).

3. The BHT contract included, inter alia, the FAR 52.233-1, DISPUTES (JUL 2002}-ALTERNATE I (DEC 1991) and 52.243-4, CHANGES (AUG 1987) clauses (R4, tab 4 at 90, 116, 121, 128).

4. The BHT contract specifications,§ 01 33 00, "SUBMITTAL PROCEDURES," provided in pertinent part:

1.4 APPROVED SUB MITTALS

The [CO' s] approval of submittals shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory. Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor ... is responsible for ... the satisfactory construction of all work. ...

1.5 DISAPPROVED SUBMITTALS

The Contractor shall make all corrections required by the [CO] and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause "Changes" shall be given promptly to the [CO].

1.9 SCHEDULING

Submittals covering component items forming a system or items that are interrelated shall be ... coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 21 calendar days exclusive of mailing time) shall be allowed ... for review and approval. ...

2 1.11.2 Deviations

For submittals which include proposed deviations requested by the Contractor, the column "variation" of ENG Form 4025 [TRANSMITTAL] shall be checked ....

a. Contractor-proposed deviations, including variations and other departures from the contract requirements, shall be noted/marked in red on each copy of the submittal data and shall be provided with a letter attachment to the ENG Form 4025 summarizing the proposed variation, deviation, or departure. Variations, deviations, or departures shall contain sufficient information to permit complete evaluation.. . . At the minimum the information shall include:

(1) An explanation in detail of the reason for the variation and how it differs from that specified; (2) The cost difference; and (3) How the variation will benefit the Government.

(R4, tab 4 at 222, 224, 226)

5. The BHT contract specifications,§ 14 21 23, "ELECTRIC TRACTION PASSENGER AND SERVICE ELEVATORS,"~ 1.2, "SUBMITTALS," required government approval of shop drawings, product data, design data calculated by a "Registered Professional Engineer," test reports, and certificates of all required state and local licenses of individuals performing for elevators and accessories "Quality Assurance for Elevator Inspector ... Qualifications." Section 14 21 23, ~ 1.3, "ELEVATOR SYSTEM," stated:

Provide pre-engineered elevator system, by manufacturer regularly engaged in the manufacture of elevator systems, that complies with ASME Al 7.1 in its entirety, ASME Al 7.2l2l in its entirety, and additional requirements specified herein.

Submit detail drawings including:

2 ASME Al 7.1, Al 7.2 and Al 7.3 are not in the appeal record. 3 dimensioned layouts in plan and elevation showing the arrangement of elevator equipment, accessories, and data sheet showing all:

a. [S]upporting systems, b. Anchorage of equipment, c. Clearances for maintenance and operation; d. Details on hoistway, e. D

Paragraph 1.4.1 provided in pertinent part:

Elevator Specialist

Work specified in this section must be performed under the direct guidance of the Elevator Specialist in compliance with ASME Al 7.3Y1 The Elevator Specialist must be regularly engaged in the installation and maintenance of the type and complexity of elevator system specified in the contract documents, and served in a similar capacity for at least three systems that have been performed in the manner intended for a period of not less than 24 months. Elevator system manufacturer must provide a letter of endorsement certifying that the Elevator Specialist is acceptable to manufacturer ....

BHT contract § 14 21 23 described the elevator system performance characteristics in ii 2.1. (R4, tab 7 at 9-11, 13-15) 6. In 2008-2009, Paulette K. Daniels was president of PKD, located in Boerne, Texas, and David D. Daniels of Total Systems Contracting· (TSC), co-located at the same Boerne, Texas street address, was vice president of PKD (R4, tab 10 at 3, 5, tab 12 at 12).

7. By 9 July 2008, Gil bane received elevator subcontract proposals from ThyssenKrupp Elevator and from PKD (R4, tab 8 at 1, 24 ).

4 8. Effective 26 August 2008, Gilbane subcontracted with PKD at the price of $597,000.00 for BHT facility elevators in accordance with the BHT contract drawings and specifications (R4, tab 3 at 38-39, 46).

9. On 16 October 2008, Gilbane sent USACE Transmittal No. 14 21 23-1 3 for elevator system item Nos. 1-6, 15-16, with detailed drawings, passenger elevators, accessories, supporting systems, machinery and controls, heat and reaction loads, and TSC shop drawings 090108-1, -2, and -3 drawn by Charles E. Hempel of Tannersville, Pennsylvania, for PKD (R4, tab 10 at 1-2, 9-11).

10. On 14 November 2008, USACE noted on Transmittal No. 14 21 23-1 code "E" ("disapproved," R4, tab 4 at 237), "RESUBMISSION REQUIRED," and set forth technical comments on this submittal, including each ofTSC's shop drawings, and did not question whether PKD was a "manufacturer regularly engaged in the manufacture of elevator systems" (R4, tab 10 at 7-8).

11. On 20 January 2009, Gilbane sent USACE Transmittal No. 14 21 23-3 for elevator item No. 18, Quality Assurance, with Texas Department of Licensing and Regulation registrations for Elevator Inspector Paul E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 7101-7109
41 U.S.C. § 7101-7109
§ 7101
41 U.S.C. § 7101

Cite This Page — Counsel Stack

Bluebook (online)