Gielow v. Eastern Shore Shipbuilding Corp.
This text of 265 F. 845 (Gielow v. Eastern Shore Shipbuilding Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
The Eastern Shore Shipbuilding Corporation was put in receivers’ hands in this court during March last. Sub[846]*846sequently, bankruptcy proceedings were instituted against it in New York, and it has there been adjudicated a bankrupt, and a trustee has been elected. Of these facts there is no question, although the adjudication has never been in any formal manner brought to the attention of this court. It has, however, been agreed between the parties that the issues raised by the petition of the Erie Basin Towing & Hoisting Company, hereinafter called the “Erie” and by the petition of the United States Shipping Board Emergency Fleet Corporation, hereinafter called the “Fleet Corporation,” shall be dealt with as they would-be if the proceedings were now, as they shortly will be, in bankruptcy. For brevity, the Eastern Shore Shipbuilding Corporation will he called the “bankrupt.”
The bankrupt contracted to build four wooden tugs for the Erie. Three of these were unfinished at the time receivers were appointed. For their completion the bankrupt had accumulated at its yard material to which the Erie claims to be entitled under the contract, the pertinent provisions of which read as follows:
“(e) That the title in ana to the said hull, together with all materials purchased or intended for use in the construction of said vessel, shall be vested in and become the property of the purchaser, subject only to lien of builder for contract value of labor and materials over and above installments paid by purchaser.
“(f) That if the builder shall fail to carry out any of the material or substantial provisions of this contract and shall continue in default for a period of 30 days after notice thereof by the purchaser and demand for performances, the purchaser shall have the power to enter and take possession of said hull and all materials in connection therewith and in a reasonable and economical and efficient manner with no unnecessary expense to the account of the builder, complete the work called for in this contract, either at the works of the builder or elsewhere, and if the purchaser shall expend less than the balance remaining of the contract price in completing this contract, he shall pay to the builder, and the builder shall receive such balance as final and complete payment, and that if the purchaser shall expend more than the balance remaining of the contract price in completing contract, the purchaser shall receive from the builder and the builder shall pay to the purchaser on demand, ‘as liquidated damages, the difference between the amount expended and the remainder of the contract price.’ ”
“It is agreed that title to all vessels, either completed or under construction, in so far as they shall have been inspected and approved by the owner, shall be in the United States of America, and that the title to all material for the furtherance of work under this contract, however and by whomsoever contracted for or assembled or set up in the shipyard, or used in the construction of the work under this contract, shall be in the owner at all times. Nothing [847]*847contained herein, however, shall be construed as a waiver by the owner of its right to direct the replacement of unsatisfactory workmanship ana/or materials at the contractor’s expense.”
At the time of the bankruptcy, none of the hulls were completed. The Fleet Corporation claims the materials on the premises of the bankrupt, and says that, even if it would not be entitled to them if it were a private corporation, it is really an agency of the government, and as such is not subject to the Fien Faws of the states. The cases relied on by it have no application to the facts of the one at bar. Some of them rule that specific liens imposed by Congress to further the collection of taxes are not subject to state regulations, and others merely reaffirm the well-known principle that the sovereign is not bound by general statutes, unless the intent so to do is clear.
In what has already been said, it has, for the purpose of this discussion only, been assumed that the Fleet Corporation is correct in asserting that it has all the rights of the government. It is not intended thereby to intimate any opinion one way or the other as to whether it has those rights in fact.
It follows that the petitions of both the F/rie and the Fleet Corporation must be 'dismissed, except in so far as relates to such materials claimed by either of them, as prior to the appointment of receivers, had been placed on board the ships under construction.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
265 F. 845, 1919 U.S. Dist. LEXIS 669, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gielow-v-eastern-shore-shipbuilding-corp-mdd-1919.