Gibson v. Heiman

547 S.W.2d 111, 261 Ark. 236, 1977 Ark. LEXIS 2060
CourtSupreme Court of Arkansas
DecidedMarch 7, 1977
Docket76-324
StatusPublished
Cited by16 cases

This text of 547 S.W.2d 111 (Gibson v. Heiman) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibson v. Heiman, 547 S.W.2d 111, 261 Ark. 236, 1977 Ark. LEXIS 2060 (Ark. 1977).

Opinion

Frank Holt, Justice.

In an action on a written contract, appellant sought recovery of fees for his engineering and construction manager services provided to Max Heiman, deceased, in connection with the construction of a project known as Country Club Manor Apartments. Appellees, administrators of the estate of Heiman, denied liability on the basis that the contract was unreasonable and unconscionable. Also appellant had breached the contract by substantial nonperformance and, therefore, any recovery should be on a quantum meruit basis. The chancellor found that appellant did not completely perform his contractual duties and appellant, on a quantum meruit basis, was adequately paid for his services. Appellant first contends that the findings of fact and conclusions of law and the judgment rendered by the chancellor are unsupported by the evidence and are contrary to the law and the facts.

According to the contract between appellant and Heiman, owner of the apartment project, the appellant was to render engineering services in the nature of planning, designing, assistance in construction loans, including costs and market studies, furnish and submit contract forms to bidders, construction observation and construction management for a fee of ten and one-half percent of the project construction costs, which eventually approximated $4,000,000. The total fee consisted of six and one-half percent for engineering services and four percent for construction management. He claimed he was due the sum of $417,861.93 and interest which represented his fee and additional services. Appellant had been paid $110,000 by Heiman before his death and appellant had also received $80,000 on his fee in settlement of his claim against the mortgagees of the project (a total of $190,000). Appellant argues that he fully performed the services required by the contract and is entitled to be paid according to the contract. The record indicates that the appellant, in the planning stage of his contractual duties, performed various duties of designing, providing specifications and preparing the necessary documents and data. However, there is evidence that appellant’s performance was faulty. Through certain design flaws, there developed problems with various apartments of the 210 apartment complex, such as sewage disposal when a storm occurred, lack of usable wall and closet space, improper door hangings, faulty locations of circuit breakers and electrical switches, lack of outside electrical receptacles and a maintenance storeroom, inadequate parking spaces (373 of 406 exist) and other complaints. These deficiencies were a result of poor design and lack of supervision and rendered the apartments difficult to rent.

Under the construction management phase of the contract, appellant’s duties were not specified. The contract does not define the term construction management and is admittedly ambiguous. Since the contract is ambiguous, it is construed most strongly against the party preparing it, here the appellant, and its meaning becomes a question of fact. Manhattan Factoring Corporation v. Orsburn, 238 Ark. 947, 385 S.W. 2d 785 (1965). Appellant argues that his duties as construction manager involved such things as surveys, obtaining information and governmental approval where necessary and negotiation of subcontractor bids for the general contractor’s approval. He contends that the majority of appellant’s duties as construction manager were complete at the time of the letting of the general contractor’s contract.

Appellant introduced a report of the American Council of Consulting Engineers as an aid in defining the scope and duties of construction management. This document provides, however, that, in addition to design duties in the planning stage, as soon as the construction contract is let, “the construction manager, working as the Owner’s Agent, provides general coordination and direction of the work of the various contractors.” Although appellant considered his duties as construction manager to deal primarily with financing the project and negotiations of bids, the chancellor felt, and we agree, that the term here, without being limited, requires supervision of construction in a position of authority between the contractors and the owner.

Mr. C. V. Barnes, a real estate developer, defined construction management as “the construction manager would be someone who in effect took the place of an owner, entrepreneur. He would do all the functions that normally an owner-developer would do if such a construction manager were not employed or engaged.” According to Jack Morgan, the general contractor for the project, a construction manager should supervise the project personally or his staff personnel on a fulltime basis. This conclusion is supported by a provision in the agreement between Morgan and Heiman wherein it states: “All work shall be done under the general supervision of the engineer.”

It is at this stage of his contractual duties that appellant’s nonperformance is most evident from the evidence. He admits that he did not supervise the construe-don. “I did not supervise. I observed for compliance with the plans and specifications. Mr. Morgan [the general contractor] does the supervising.” Further, it appears that appellant has neither the operational facilities nor the staff for day to day management on a project of this magnitude (210 apartments — approximately $4,000,000 in construction costs). Appellant operates alone from a small office and has no fulltime employees.

Mr. Maurice Mitchell, an attorney and co-administrator of Heiman’s estate, testified that appellant was uncooperative, incorrect in his information and more interested in financing the project than anything else. He felt that appellant delayed the project for four to five months by his lack of decision making. Tenants were waiting to occupy apartments. He had difficulty in getting appellant’s plans for a recreational facility which it appears was never built. He testified: “Every time he [appellant] got between us and a supplier, or a subcontractor, or the contractor, Jack Morgan, we had trouble.” Donna McClelland, resident manager of the apartments, testified she had problems in getting appellant to accomplish what was needed of him. There was evidence that she made a punch list consisting of twenty to thirty pages of legal size sheets “of items that were wrong and omitted, that had not been finished.” She herself had to ride “herd” on the contractor to get these items corrected and removed from her punch list. Sandra Morrison, an agent for the estate, testified that she had difficulty in getting appellant to act on complaints from the contractor, and she would sometimes have to follow up on them herself. There were problems about the recreational room plans, landscaping and the elevators. A storm caused sewage to back up in some bath tubs and appellant was unresponsive to the situation. Consequently, she had it corrected by calling one of the contractors.

It is well settled that the chancellor’s findings of fact will not be reversed unless clearly against the preponderance of the evidence. Titan Oil & Gas v. Shipley, 257 Ark. 278, 517 S.W. 2d 210 (1974); Minton & Simpson v. McGowan, 256 Ark. 726, 510 S.W. 2d 272 (1974); and Bollen v. McCarty, 252 Ark. 442, 479 S.W. 2d 568 (1972).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion No.
Arkansas Attorney General Reports, 2001
Precision Steel Warehouse, Inc. v. Anderson-Martin MacHine Co.
854 S.W.2d 321 (Supreme Court of Arkansas, 1993)
Karnes v. Trumbo
770 S.W.2d 199 (Court of Appeals of Arkansas, 1989)
Biniores v. State
701 S.W.2d 385 (Court of Appeals of Arkansas, 1985)
Robinson v. State
624 S.W.2d 312 (Supreme Court of Arkansas, 1981)
Bowman v. McFarlin
615 S.W.2d 383 (Court of Appeals of Arkansas, 1981)
Don Gilstrap Builders, Inc. v. Jackson
601 S.W.2d 270 (Court of Appeals of Arkansas, 1980)
Wilson v. Lester Hurst Nursery, Inc.
598 S.W.2d 407 (Supreme Court of Arkansas, 1980)
Winkle v. Grand National Bank
601 S.W.2d 559 (Supreme Court of Arkansas, 1980)
DeClerk v. Johnson
596 S.W.2d 359 (Court of Appeals of Arkansas, 1980)
Young v. Young
593 S.W.2d 72 (Court of Appeals of Arkansas, 1980)
McAway v. Holland
599 S.W.2d 387 (Supreme Court of Arkansas, 1979)
Newberry v. McClaren
575 S.W.2d 438 (Supreme Court of Arkansas, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
547 S.W.2d 111, 261 Ark. 236, 1977 Ark. LEXIS 2060, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibson-v-heiman-ark-1977.