Gibson v. Hardy

706 P.2d 1358, 109 Idaho 247, 1985 Ida. App. LEXIS 728
CourtIdaho Court of Appeals
DecidedSeptember 18, 1985
Docket14875
StatusPublished
Cited by9 cases

This text of 706 P.2d 1358 (Gibson v. Hardy) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibson v. Hardy, 706 P.2d 1358, 109 Idaho 247, 1985 Ida. App. LEXIS 728 (Idaho Ct. App. 1985).

Opinion

SWANSTROM, Judge.

Ned and Marne Hardy appeal from a district court judgment awarding damages to plaintiffs Gibson and Swallow caused by the Hardys in negligently performing a slash piling contract for the United States Forest Service (USFS). The Hardys assert that the judgment must be set aside because of the following errors: first, that plaintiffs had no justiciable interest in the property which was admittedly damaged or destroyed by the Hardys; second, that the trial court erred in concluding the Hardys breached a legal duty to plaintiffs to exercise due care not to damage or destroy wood materials being salvaged by plaintiffs; third, that the court’s findings as to damages are not supported by substantial, competent evidence. We affirm the judgment as to liability but we vacate and remand on the issue of damages.

In July 1978 Marne Hardy signed a contract with the USFS for slash piling several designated “units” or areas of forested land in the Island Park area of eastern Idaho. Marne’s husband, Ned, actually performed the contract. For convenience, we will simply refer to one or both of these parties as “Hardy.” The contract work involved cutting down or pushing over standing trees and piling them along with all other logs, treetops and limbs within certain unit boundaries for later disposal by burning. The work was to be fully performed in ninety days.

At approximately the same time, Gibson and Swallow, as salvage operators, contracted with the USFS to purchase all salvageable trees which were to be cut and removed from what we will call the Meadow Creek unit. The Gibson-Swallow salvage operation involved cutting small diameter lodge pole pines to form poles and posts for sale in Nevada. The salvage contract, in Gibson’s name, carried a termination date of October 30, 1978. However, the contract further provided that the “sale may terminate prior to above date due to slash piling.” The Meadow Creek unit, where Gibson and Swallow were allowed to cut and remove trees, was included in the Hardy contract to be slash piled. The Hardys had no contractual obligation with Gibson and Swallow.

*249 Gibson and Swallow worked the Meadow Creek unit for approximately twenty-four days and claimed they had many poles and posts cut and lined up in preparation for loading. On July 30, 1978, Gibson, Swallow and their crew left the Meadow Creek unit unattended and traveled to Nevada for a three-day weekend. On August 3, after completing work at his first location, Hardy proceeded to the Meadow Creek area and slash piled the unit where Gibson and Swallow had been working. The salvage operators returned to find that all salvageable material, including cut and piled posts and poles, had been destroyed by being bulldozed into large piles of debris for burning. The USFS offered Gibson and Swallow an alternative area to work, which they refused. Subsequently, Gibson and Swallow filed this action against the Hardys, seeking damages for the loss of their property.

Hardy first asserts that the salvage operators had “no justiciable interest” in the property that was destroyed. He relies on a provision of Gibson’s salvage contract to support his argument. The provision states that “[tjitle to all timber included in this contract shall remain in the United States until it has been scaled or measured, paid for and removed from sale area.” Hardy argues that this provision does not provide Gibson and Swallow an interest in the trees that had been standing or in the cut poles and posts because the material had not been removed, resulting in the title still vesting in the Forest Service. We find this contention to be without merit. It was established beyond dispute at trial that Gibson fully paid the USFS for the salvage on the Meadow Creek unit in advance. In spite of the printed contract language, no scale or measurement of the material had to be made before its removal by the salvage operators. The salvage contract gave Gibson and Swallow the right to cut and remove all salvageable material on the unit. They were prevented from doing this only by the destruction caused by Hardy. We hold that Gibson and Swallow had a sufficient interest to bring a cause of action for damages.

Hardy next argues that even if the salvage operators had a justiciable interest in the standing trees and in the cut material on the unit, that interest was inferior to Hardy’s interest. This assertion is again based in part on Gibson’s salvage contract with the USFS. A prospectus furnished by the USFS to Gibson and to other potential timber purchasers specifically stated: “The [salvage] sales will be terminated when [slash] piling commences on that specific unit. Slash piling will not be delayed by the pole salvage sales.” (Emphasis original.) The contract itself stated “Sale may terminate prior to [the stated termination date] due to slash piling.” It is undisputed that this language provided Hardy’s slash piling operation with priority over the salvage operation. However, as we explain later, it does not necessarily follow that Hardy’s slash piling contract gave him the right to arbitrarily terminate the rights Gibson and Swallow had acquired under their contract.

Pursuant to his contract, Hardy furnished the USFS with a work schedule which showed the proposed sequence of his slash piling operation on the various units he was to clear. The work schedule was by no means an inflexible condition of the contract, but it did set forth the order in which the USFS desired the slash piling to proceed on the several units. The evidence indicates that had Hardy followed this schedule he would not have moved onto the Meadow Creek unit until approximately August 27. Instead, as the trial court found, because “it suited his convenience,” Hardy moved his equipment onto the Meadow Creek unit on August 3 and proceeded to “slash pile” the unit. One of the “general provisions” of Hardy’s contract stated:

It will be [Hardy’s] responsibility to plan his work in such a way that it will be completed in accordance with the established work progress plans and within the contract period.
The Contracting Officer [of the USFS] or his authorized representative may specify priority of work by items, units or *250 blocks within the bid item during the course of the contract. Such priorities specified will not be a cause for change in contract time or price.

Thus, we think it is clear that Hardy’s contract did not give him an unqualified right to terminate Gibson and Swallows’ salvage rights by simply moving his slash piling operation to their unit because “it suited his convenience.”

Hardy next asserts that he did not breach any duty to Gibson and Swallow and, therefore, was not negligent in destroying the trees, poles and posts. We recognize that negligent conduct and breach of contract are two distinct theories of recovery. “Ordinarily, breach of contract is not a tort, although a contract may create the circumstances for the commission of a tort.” Just’s Inc. v. Arrington Construction Co., 99 Idaho 462, 468, 583 P.2d 997, 1003 (1978). Negligence arises out of some duty imposed by law, irrespective of any contract. Taylor v. Herbold, 94 Idaho 133,

Related

Sorensen v. Saint Alphonsus Regional Medical Center, Inc.
118 P.3d 86 (Idaho Supreme Court, 2005)
Bromley v. Garey
979 P.2d 1165 (Idaho Supreme Court, 1999)
Mugavero v. A-1 Auto Sales, Inc.
944 P.2d 151 (Idaho Court of Appeals, 1997)
Latham Motors, Inc. v. Phillips
851 P.2d 985 (Idaho Court of Appeals, 1992)
Hudson v. Cobbs
797 P.2d 1322 (Idaho Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
706 P.2d 1358, 109 Idaho 247, 1985 Ida. App. LEXIS 728, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibson-v-hardy-idahoctapp-1985.