Gibson v. Carlin

81 Tenn. 440
CourtTennessee Supreme Court
DecidedSeptember 15, 1884
StatusPublished
Cited by2 cases

This text of 81 Tenn. 440 (Gibson v. Carlin) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibson v. Carlin, 81 Tenn. 440 (Tenn. 1884).

Opinion

Cooper, J.,

delivered, theopinion of, the court.

Bill to enforce the mechanic’s lien upon the following writing-:

“ Chattanooga, Tenn., December 29, 1881.
Mr. D. B. Carlin, City. Dear Sir — We will furnish the material, and put on good tin and give it two coats of mineral paint and boiled oil, and put on your roof on your building on Ninth street, 40x44, for one hundred and thitty-three dollars. This will inelude'taking off the tar roof.
Very respectfully, Gibson, Lee & Co.
The above contract is accepted, Dec. 29, 1881. D. B. Cables’.
And work to be done in ten or twelve days from date.”

In addition to the amount specified in the writing, the complainants claim $13.35 for extra work in capping the side or fire walls of the building. The defendant in his answer contends that the writing produced does not contain the entire contract, and that the* capping of the walls, for which extra compensation is claimed, was included in the contract. He further, insists that the contract has never been complied with — the work being so negligently and badly, done that the roof has always leaked, and still continues to leak when it rains, to the great damage of the building. He claims a deduction from the contract price by way of recoupment. The chancellor granted the complainants all the relief sought without deduction. The Referees, upon Carlin’s appeal-, have sustained his defenses. The complainants except to their report.

The new roof was put on within the ten or twelve days’ limitation of the written contract made an ex-[442]*442Mbit to the bill, but the complainants’ foreman admits that some leaks were found which were not closed for several days, and some leaks it is otherwise clearly shown have never .been remedied. The' capping of the-side parapet or fire walls was not done before February 6th, and perhaps later. The foreman of complainants testifies that he left their service in May, at which time one coat of paint, and the- second coat on half the roof had been put on, the other half of the second coat being finished, he says, sometime after-wards. There was therefore no compliance by the complainants with the contract in point of time.

It clearly appears that the written proposition and acceptance exhibited with the bill do not contain the entire concract of the parties. The complainant, Gibson, who carried on the negotiations and made the contract with the defendant, testifies himself that the defendant, as a part of the contract, agreed to have a brick-mason present when the old roof was taken off to repair and cap the side walls of the building, without which he admits the roof could not be made tight unless the walls were capped with tin. He further testifies that it was a part of the agreement that the contract price was to be paid by the defendant by a cash payment of $25 when the work was completed, and the residue in monthly installments of $25 each -for which the defendant was to give his notes with a certain specified person as surety. It is also shown by the proof that the defendant, as his part of the contract, was to furnish new sheeting for the roof and a workman to put it on as it might be [443]*443needed when the tin was laid, and that he did furnish the workman and the sheeting, and that the new sheeting was put on as directed by the complainants’ workman. A contract partly in writing and partly in parol is an oral contract: Smith v. O’Donnell, 8 Lea, 468.

The parties differ as to. whether the capping of the fire walls was embraced in the contract. The complainant, Gibson, testifies that he and the defendant discussed the matter, and that the agreement reached was that the walls were to be rebuilt to their original height by the defendant, and cemented on top. In another place he says' that the defendant had agreed to have a mason present when the old roof was taken off to repair the walls. The defendant denies that any such agreement was made. On the contrary, he testifies that, owing to his frequent and unavoidable absences from the city, he requested the complainants to make him a proposition covering all necessary work on the parapet walls so as' to make a good roof. He adds, in support of his assertion, that complainant Gibson had offered to put on a tin roof for |96, if defendant would take off the old roof aud do the other work. Gibson admits that he may have made that offer, as plain roofing without painting was then at $6 a square, which would have amounted to the sum mentioned. It elsewhere appears that the cost of taking off the old roof was about $3, and the cost of painting about $16. The defendant insists that the difference between these sums and the contract price is what was agreed upon for the work on the walls. [444]*444The inference, as the Referees say, was a fair one. The written proposition of the complainants is that they “will furnish the material, and put on good tin, * * and put on your roof on your building, * * 40x44.” The. meaning would seem to be that the complainants would “ furnish the material,” and do the work necessary to make a good roof. And this would be a legitimate construction to put upon the- language unless it is otherwise shown that the defendant was to furnish new sheeting and a workman to put it on, and that he complied with this part of the contract. There is nothing, except complainant Gibson’s testimony, to show that- defendant was to do anything about the parapet walls. And a most significant fact is that while the defendant did, through his son as his agent, he himself being absent from the city, furnish new sheeting and a workman, not a word was said by the complainants’ workman to the son about any expected mason. The contract describes the roof as 40x44 feet. The building fronts 40 feet from outside wall to outside wall, and runs back 42 feet. The esti- ■ mate of the contract covers the walls. ’ And the complainants’ principal workman, who was the acting boss of the work,’ testifies that on the evening of the day the roof was put on, he told the foreman of the complainants that the walls had to be capped, that there was soldering to do, and gutters to be put up, and the foreman replied that he would have 'it done. The ’ circumstances sustain the defendant’s contention, and we concur with the Referees in thinking, that the necessary work on the parapet walls was included in the contract.

[445]*445The front parapet wall was run up three feet above the roof, and covered originally with plank. One of the side walls is said by the defendant to have been twelve inches high, and the other six inches for about half its length. The other testimony shows that these side walls were down to the roof in some places; in others two or three inches high, and one and one-half feet in others. When the new roof was put on the tin was run up about three inches on the front parapet, and “flashed” or inserted between the brick. The same process was pursued on the side walls for three or four feet from the front wall. As to the residue of the side walls nothing was done, and the water, whenever it rained, ran down between the tin and these walls. The flashing on the front wall was not properly done. It should, according to the testimony of an impartial tinner, have been pointed with cement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Correspondence School, Inc. v. Crabtree
34 S.W.2d 447 (Tennessee Supreme Court, 1931)
Barlow Brothers v. Lunny
128 A. 115 (Supreme Court of Connecticut, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
81 Tenn. 440, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibson-v-carlin-tenn-1884.