Gibson Concrete Construction v. Shrode, 5-08-11 (10-27-2008)

2008 Ohio 5537
CourtOhio Court of Appeals
DecidedOctober 27, 2008
DocketNo. 5-08-11.
StatusPublished
Cited by1 cases

This text of 2008 Ohio 5537 (Gibson Concrete Construction v. Shrode, 5-08-11 (10-27-2008)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibson Concrete Construction v. Shrode, 5-08-11 (10-27-2008), 2008 Ohio 5537 (Ohio Ct. App. 2008).

Opinion

OPINION
{¶ 1} Defendant-Appellant, Rebecca Shrode, et al., appeals the judgment of the Hancock County Court of Common Pleas dismissing her counterclaim for negligent workmanship and breach of contract against Plaintiff-Appellant, Gibson Concrete Construction, Ltd. On appeal, Shrode asserts that the trial court's judgment was against the manifest weight of the evidence. Specifically, Shrode asserts that the weight of the evidence demonstrates that Gibson Concrete Construction did not perform in a workmanlike manner and exercise ordinary care and skill, and that she did not fail to mitigate damages. Based on the following, we affirm the judgment of the trial court.

{¶ 2} The case before us arose from the following sequence of events. In 2004, Shrode was in the process of building a new home and was acting as her own contractor. She entered into a contract with Gibson Concrete Construction ("GCC") to perform the concrete work in the home, including pouring of a basement floor. At some point, Shrode elected to install a radiant heating system designed by Radiantec within the concrete floor. A radiant heating system is a system of polymer tubing installed within a floor, through which heated water passes to supply heat to the room above it. Shrode hired John Steen, a plumber, to install the heating system. During completion of the concrete floor, Clinton *Page 3 Gibson, a GCC employee, cut a polymer tube with a floor saw. The following action ensued.

{¶ 3} In April 2005, GCC filed a complaint against Shrode, the Hancock County Treasurer, Wells Fargo Bank, Delbert P. Dehnhoff, and John Steen.1 The complaint alleged, in part, that GCC completed the work contracted for in December 2004; that Shrode failed to pay for certain work and materials valued at $6,200; and, that, in January 2005, it filed an affidavit for a mechanic's lien with the Hancock County Recorder's Office. GCC's complaint requested: (1) an order that its lien on Shrode's property was valid and for the lien to be foreclosed, (2) judgment against Shrode in the amount of $6,200, and (3) reasonable attorney's fees, interest, and costs.

{¶ 4} In June 2005, Shrode filed an answer to GCC's complaint, claiming, in part, that it did not complete the contracted work in a workmanlike manner. Additionally, Shrode filed a counterclaim alleging breach of contract, breach of warranty, negligence, and violations of the Ohio Consumer Sales Practice Act. Shrode alleged that GCC's faulty workmanship in installing the concrete damaged the radiant heating system and that her cost of repair was $13,186.24. As relief, *Page 4 Shrode requested: (1) damages for cost of repair in the amount of $13,186.24, (2) incidental and consequential damages, (3) actual damages, triple damages, and attorney's fees for violation of the Ohio Consumer Sales Practice Act, and (4) costs and interest.

{¶ 5} In July 2006, the case proceeded to a hearing before a magistrate, at which the following testimony was heard.

{¶ 6} Clinton Gibson ("Clinton") testified that he is a manager of GCC and has been an employee for ten years; that his father, Albert Gibson, owns GCC; that GCC entered into a contract with Shrode for concrete work in a new home, including installation of a basement floor; that the contract specified that the floor would be four inches thick with saw control joints, which is within the industry standard; that a saw control joint is a cut made with a saw that prevents a concrete floor from cracking; that saw control joints are typically one-quarter of the thickness of the concrete; that, accordingly, Shrode's four inch thick floor required a minimum one inch saw control joint; and, that he reviewed the specifications of the project with Shrode, specifically informing her that the floor would be four inches thick.

{¶ 7} Clinton continued that, after they entered into the contract, Shrode informed him that she intended to install a radiant heating system designed by Radiantec within the basement floor; that GCC did not contract to install the *Page 5 heating system, but John Steen, a plumber, contracted for this part of the project; that neither Shrode nor Steen gave him any information from Radiantec about the heating system; that Steen did not provide him with any instructions as to any modification of his job specifications for pouring of the floor; that he was not supplied with any specifications as to the heating system or new blueprints; that the only modification to the project that Shrode requested in light of the heating system was that GCC install wire mesh as part of the floor in place of rebar, which he typically used; that the wire mesh was required so that the polymer tubing for the heating system could be tied to something; that the tubing is tied to the wire mesh to prevent it from floating upward while the concrete is poured; that the heating system did not require a change in the thickness of the floor, but that he discussed pouring a thicker floor with Shrode "for extra insurance as far as depth or clearance between the top of the floor and the tubing" so that, during the saw cut, the tubing would be further down in the floor" (hearing tr., p. 34); and, that, had Shrode requested a thicker floor, he would have issued a written "change order," because this would increase the cost of the project.

{¶ 8} Clinton then described the process of installing the floor. Clinton explained that, after GCC laid the wire mesh, Steen laid the tubing in a pattern; that he watched Steen lay the tubing, but no employees of GCC were involved in this process; that Steen tied the tubing to the wire mesh with plastic "zip ties" as *Page 6 he laid it; that zip ties are very strong and do not break easily; that, after laying the tubing the first time, Steen and his crew realized that the spacing was off, removed 90 percent of the zip ties, and respaced the tubing; that, when Steen finished, GCC commenced pouring the concrete; that the GCC crew used a hook to lift the wire mesh to suspend it into the bottom third of the concrete floor; that he lifted the wire mesh to an appropriate point during the pour, approximately three-quarters of an inch from the bottom; and, that it is important to lift wire mesh or rebar to suspend it within the concrete, otherwise it will not reinforce the concrete.

{¶ 9} Clinton continued that, prior to saw cutting the floor, neither Shrode nor anyone else requested him to make the saw control joint cut at one-half inch instead of one inch to avoid nicking the tubing; that he had a discussion with Shrode and Steen prior to cutting the floor, during which he told them the saw cut would be one inch; that he cut the saw control joints into the floor using a floor saw at a depth of exactly one inch; that, within the first six or eight feet of cutting, he struck a tube; that, after cutting the tube, he stopped the saw and called Shrode; that Shrode directed him to call Steen; that Steen told him to cut an eight-by-eight inch square out of the floor so he could repair the tubing in that area; that, with Shrode's consent, he cut out the piece Steen directed him to; that, after he struck the tube and removed the eight-by-eight inch section, Shrode requested him to raise the depth of the saw cut to one-half inch for the remainder of the floor; that a *Page 7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reamensnyder v. Marino
127 N.E.3d 340 (Court of Appeals of Ohio, Eleventh District, Trumbull County, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2008 Ohio 5537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibson-concrete-construction-v-shrode-5-08-11-10-27-2008-ohioctapp-2008.