Gibson Co. v. Morton

148 N.E. 430, 88 Ind. App. 685, 1925 Ind. App. LEXIS 213
CourtIndiana Court of Appeals
DecidedJune 30, 1925
DocketNo. 11,984.
StatusPublished
Cited by4 cases

This text of 148 N.E. 430 (Gibson Co. v. Morton) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibson Co. v. Morton, 148 N.E. 430, 88 Ind. App. 685, 1925 Ind. App. LEXIS 213 (Ind. Ct. App. 1925).

Opinion

McMahan, J.

Complaint by appellee, in two paragraphs, upon two contracts for the rental of advertising boards, and for damages for an alleged breach of contract.

The first paragraph alleges, in substance, that in April, *687 1919, the parties entered into a written contract whereby appellee agreed to erect, paint and maintain forty-five field bulletin boards and to rent the same to appellant for a term of three years from the average date of completion, appellant agreeing to pay an annual rental of $75 for each board, the rental to be paid in monthly installments of $6.25; that in May of the same year the contract was modified with respect to cancellation and rental on additional signs contemplated; that appellee fulfilled all the requirements of the contract, except wherein appellant made it impossible for him to do so, by reason of appellant’s repudiation of the contract in August, 1920; that appellee made diligent effort to erect the boards, but that, while he was engaged in such effort, appellant repudiated the contract and notified him that it would not perform the conditions of the contract; that appellee had erected and completed twenty boards near Indianapolis, the average date of completion being September 16,1919; that he completed five near Muncie in May, 1920, five near Terre Haute in July, 1920, and five near Vincennes in June, 1920; that, at the date when appellant repudiated the contract, appellee had completed and painted at his factory ten boards to be erected at Lafayette and Danville, and had shipped the same, but that appellant refused to approve locations for these boards, for which.reason they were not erected; that, owing to conditions arising by reason of the World War, appellee was prevented from erecting such boards as soon as he would have done had it not been for the war, but that in view of the war conditions he erected the boards as rapidly as possible and within a reasonable time; that appellant had defaulted in the payment of the rental for the boards erected, by reason of which default the rental for the entire term of the contract (three years) was due and payable, and asking judgment for the rental for the boards for the entire term of the con *688 tract and for damages for breach of the contract. The second paragraph is, in substance, the same as the first and alleges that in June, 1919, the parties entered into a second contract for the erection of eighteen boards.

The contracts were for three years from the average date,of the completion of the boards, and provided that, if there should be a default in the payment of the rent for three months, the rental for the remainder of the rental period should become due and payable. Appellant filed an answer of denial and of payment. A trial by jury resulted in a verdict and judgment for appellee for $6,000. Appellant’s motion for a new trial being overruled, it appeals, and insists that the verdict is not sustained by sufficient evidence, and is contrary to law; that the amount of the verdict is excessive and that the court erred in giving and refusing to give certain instructions.

The contracts required that all boards should be of first-class workmanship and construction, and painted in an artistic and workmanlike manner, with the best quality of oil and lead, from a design submitted to and approved by appellant, and about once each year thereafter be repainted. The contracts failed to fix the time within which the boards should be erected. The law, however, required that they should be erected within a reasonable time.

The boards were not all erected, and in August, 1920, appellant, claiming there had been unreasonable delay in the erection of the boards and that many of those erected did not comply with the requirements of the contracts, in that they were not made of good material, that the paint used was of an inferior quality, and that some of them were to be of a style known as “de luxe,” but that none of them was of that style, notified appellee that it had cancelled the contract and refused to be further bound thereby..

*689 The evidence shows that the advertising boards were made in sections at appellee’s factory in Cincinnati, Ohio, and shipped to the cities where they were to be erected, and is sufficient to sustain a finding that there was an unreasonable delay in the erection of the boards; that they were not ¡constructed of first-class materials and that the paint used was not of the quality called for in the contract. In August, 1920, when appellant refused to carry out the contract, nineteen of the boards had been erected at or near Indianapolis, five at Muncie, five at Terre Haute, five at Vincennes, four at Shelbyville, three at Sullivan and two at Seymour.

Lawrence A. Brook, the receiving and shipping clerk employed by appellee, testified that the boards were shipped as follows: On August 20, 1919, ten boards to Indianapolis; September 6, 1919, ten boards to Indianapolis; September 10, 1919, two boards to North Vernon; September 18, 1919, one board to Seymour; September 19, 1919, three boards to Sullivan; October 4, five boards to Champaign, Illinois; November 26, 1919, five to Muncie; June 5, 1920, five boards to Terre' Haute; June 10,1920, five boards to Vincennes, and August 6, 1920, five boards to Lafayette.'

The boards shipped to Lafayette were returned to Cincinnati, but it seems they remained in possession of the railroad for several months. What became of these boards is somewhat uncertain. It appears that the railroad company brought suit against' appellee for the freight and storage charges* on them, and claimed $189.66 for sixty-seven days storage at Lafayette, $770.63 for storage at Cincinnati from November 5, 1920, to May 5, 1921, and for auctioneer’s fees and newspaper advertising,, thus indicating that the boards were sold to pay the charges, although there is no evidence to show to whom they were sold or the amount *690 for which they were sold. The railroad recovered a judgment against appellee for $1,250, which was settled by appellee’s paying $796.46.

The boards were erected at the several places as follows: At Indianapolis; nine in August, three in September and seven in October, 1919; four at Shelbyville, in October, 1919; one at Seymour in October, 1919; five at Muncie in May, 1920; five at Vincennes in June, 1920; three at Sullivan and five at Terre Haute in July, 1920.

The real questions involved in this appeal relate to the amount of the recovery, and the rule by which it is to be governed. As heretofore stated, appellee sued for three years’ rental for the boards actually erected and for damages by reason of appellant’s repudiation of the contracts. Forty-four of the sixty-three boards called for in the contracts were erected. The annual rental for these forty-four boards is $3,210. For the three years it would be $9,630. How the jury arrived at the amount of the verdict ($6,000) is not clear, and the parties have not aided us in solving that question.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCormick Piano & Organ Co., Inc. v. Geiger
412 N.E.2d 842 (Indiana Court of Appeals, 1980)
First National Bank v. Stoyanoff
349 P.2d 1016 (Montana Supreme Court, 1960)
Albright v. Hughes
26 N.E.2d 576 (Indiana Court of Appeals, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
148 N.E. 430, 88 Ind. App. 685, 1925 Ind. App. LEXIS 213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibson-co-v-morton-indctapp-1925.