Gibbs Corp. v. United States

127 Ct. Cl. 280, 1954 U.S. Ct. Cl. LEXIS 46, 1954 WL 6075
CourtUnited States Court of Claims
DecidedJanuary 5, 1954
DocketNo. 49553
StatusPublished
Cited by2 cases

This text of 127 Ct. Cl. 280 (Gibbs Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibbs Corp. v. United States, 127 Ct. Cl. 280, 1954 U.S. Ct. Cl. LEXIS 46, 1954 WL 6075 (cc 1954).

Opinion

Jones, Chief Judge,

delivered the opinion of the court:

Plaintiff sues for $88,470.48, which it alleges is the value of three tugs which were requisitioned by the defendant during the war period.

Between November 24, 1942, and May 28, 1948, the defendant requisitioned 12 harbor tugs described as G. Y. T. (Gibbs Yard Tugs) upon the completion of their construction at the instance of the defendant.

During this period the plaintiff was engaged in carrying out numerous extensive construction contracts for the Navy. It was informally authorized to construct the 12 tugs and was told that they would be requisitioned upon completion.

From time to time plaintiff submitted its costs and price on the first nine of these tugs, the total for the nine being $235,844.96.

The War Shipping Administrator had authority to make determination of just compensation for small vessels requisitioned. As a matter of procedure, however, the Small Vessel Appraisal Committee submitted its appraisals as a recommendation to the Assistant Deputy Administrator for Fiscal Affairs of the War Shipping Administration, who in turn made recommendation to the Administrator.

[282]*282By July 2, 1943, the price as to the first nine tugs as submitted by plaintiff had been approved, with some slight modifications, and by that time or soon thereafter paid.

By letter dated June 29,1943, plaintiff submitted invoices on tugs Nos. 10, 11, and 12, the amounts being $34,344.90, $36,073.47, and $32,332.29, respectively.

WSA had an audit made of plaintiff’s books. Thereafter plaintiff submitted corrected invoices showing that the amounts for tugs Nos. 10, 11, and 12 should be $24,835.82, $28,092.13, and $25,350.95, respectively. There is no evidence that plaintiff had seen the auditors’ report before making the correction.

The Committee recommended payment of $78,278.90 for these three tugs.

This recommended determination was approved by the Assistant Deputy Administrator for Fiscal Affairs, and on January 12, 1944, the Assistant Deputy Administrator for Small Vessels wrote plaintiff offering it the sum of $78,278.90 in full settlement for these three tugs, which offer was accepted by plaintiff on January 17,1944.

On March 7, 1944, the Assistant Deputy Administrator for Small Vessels wrote the War Shipping Administrator advising him of the recommendation of the Committee as to tugs Nos. 10 and 12, and recommended that $24,835.82 be paid for No. 10, and $25,350.92 for No. 12. These sums were approved by the War Shipping Administrator on March 15, 1944, and thereafter paid.

Tug No. 11 was not mentioned in the recommendation to the War Shipping Administrator, and no action was taken by him on that tug at that time.

There followed some discussion as to certain items that had been included in the price. In July 1944 WSA officials suggested to plaintiff that it discuss the problem of costs with the WSA auditors. A conference was held and on September 4,1944, plaintiff wrote WSA as set out in finding 20, making certain explanations and asking for additional items of cost.

No further action was taken until January 1948 when plaintiff wrote again asking for payment for tug No. 11.

[283]*283Then on March 31,1949, the Secretary of the United States Maritime Commission, as successor to the War Shipping Administration, wrote plaintiff a letter which is set out in finding 21, and which offers plaintiff an allowance of $28,929.72 for tug No. 11, but undertakes to redetermine some items in connection with the other 11 tugs, winding up with a net offer of a balance of $250.63 on the whole contract. This offer was not accepted.

Defendant pleads the statute of limitations. However, no final determination by anyone having authority was made as to just compensation for tug No. 11 until March 31, 1949. By the terms of the Merchant Marine Act of June 29, 1936, 49 Stat. 2015, it is made the duty of the Commission to determine the value of any vessel requisitioned, and if the owner is dissatisfied with the award he may sue for such additional amount as shall constitute just compensation. Under the doctrine announced in Schaefer and Robbins v. United States, 114 C. Cls. 568, 570, that act provides for suit after such finding has been made.

The letter of the United States Maritime Commission under date of March 31, 1949, gave $28,929.72 as the value of tug No. 11. This is manifestly an error, since plaintiff had agreed to a valuation of $28,092.13.

The prices of all the tugs have been agreed upon, the prices approved by the proper authority and paid, except as to tug No. 11, for which compensation has not been paid. There are numerous collateral issues, but they finally narrow down to payment for the one tug No. 11.

Plaintiff is given judgment for $28,092.13, plus interest on that amount at the rate of four percent per annum from May 28,1943, to January 31,1948, plus interest at the same rate on $27,904 from January 31, 1948, to the time of payment, all interest being allowed not as interest but as a part of just compensation.

Defendant’s plea for a setoff is denied.

It is so ordered.

Madden, Judge; Whitaker, Judge; and Littleton, Judge, concur.

[284]*284FINDINGS OF FACT

The court, having considered the evidence, the report of Commissioner C. Murray Bernhardt, and the briefs and argument of counsel, makes findings of fact as follows:

1. Plaintiff is a corporation organized and existing under the laws of the State of Florida, with its principal place of business at Jacksonville, Florida. It was reincorporated as Gibbs Gas Engine Company of Florida on December 29, 1941. On September 29,1945, its name was changed to Gibbs Corporation.

2. During 1942 and 1948, the plaintiff constructed 12 harbor tugs described as G. Y. T. (Gibbs Yard Tug) Nos. 1 to 12.' Each of these tugs was requisitioned by the War Shipping Administration (hereafter referred to as WSA) from the builder upon completion of construction, as follows:

TUG DATE OF REQUISITION
G. Y. T. No. 1_ -November 24, 1942
2_ _January 6, 1943
_ January 22, 1943
4ZIZIIZI _ _February 12,1943
5_ _ February 12,1943
6_ _March 8, 1943
7_ _March 8, 1943
8_ _April 2, 1943
9_ _April 2,1943
10_ _April 30, 1943
11_ _April 30, 1943
12_ _May 28,1943

3. a. In 1942 plaintiff was performing approximately nine fixed-price contracts for the Navy Department. Its yards were engaged in naval construction substantially 100 percent. Most of this work involved vessels larger than the tugs and the Navy furnished engines and other equipment.

b. Plaintiff was informally authorized to construct the tugs and was told that they would be requisitioned by the WSA upon completion. Plaintiff was furnished the necessary priority rating to acquire the material, engines and other equipment.

4. a.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
127 Ct. Cl. 280, 1954 U.S. Ct. Cl. LEXIS 46, 1954 WL 6075, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibbs-corp-v-united-states-cc-1954.