Gibbs Corp. v. Arundel Corp.

209 F.2d 561
CourtCourt of Appeals for the Fifth Circuit
DecidedMarch 22, 1954
Docket14322_1
StatusPublished

This text of 209 F.2d 561 (Gibbs Corp. v. Arundel Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibbs Corp. v. Arundel Corp., 209 F.2d 561 (5th Cir. 1954).

Opinion

RUSSELL, Circuit Judge.

This appeal arises from a suit by The Arundel Corporation against the Gibbs Corporation to recover compensation claimed to be due it for the dredging of a new dry dock basin and approach channel in the Gibbs Corporation shipyard on the south side of the St. Johns River at Jacksonville, Florida. The dredging operation had been instituted and carried on under the terms of a letter agreement between Gibbs Corporation and The Arundel Corporation by the provisions of which Arundel rented to Gibbs the fully manned and equipped dredge Admiral to perform the work. The parties were in agreement that Arundel had earned the maximum compensation which Gibbs had agreed to pay as rental for the dredge and that this sum should be reduced by certain stated credits. The point at controversy was whether Gibbs was obligated to respond to claims of Arundel for “extra” or additional compensation over and above the rental specified by the contract. Also present is the counterclaim by Gibbs *563 against Arundel seeking recovery for damage to its marine installations which had resulted from Arundel’s alleged negligence during the course of the operation.

The court, having tried the case without a jury, found that Arundel was entitled to recover the balance due under the basic agreement plus additional rental at the rate of $130 per hour for 221 hours, consisting of “7 days of dredging in lieu of blasting”, 29 hours delay occasioned by a bent dolphin and idle time of 24 hours due to a shutdown order issued by Gibbs. The counterclaim was in part allowed, but Gibbs was denied recovery for damages to its two bulkheads, Gibbs appeals from the portion of the judgment which granted the additional compensation to Arundel and denied it recovery for the damages to the bulkheads.

As to Arundel’s claims for extra or additional compensation for the delay occasioned by a bent dolphin and the idle time of 24 hours due to a shutdown order issued by Gibbs, the facts were not in substantial dispute, and answer to Gibb’s claim of error in the findings imposing liability for these items rests for final analysis upon the construction and effect to be given to the letter agreement of the parties. Arundel’s suit is predicated upon the theory that this contract in effect implies an assurance by Gibbs that Arundel would be provided opportunity for continuous and uninterrupted dredging operations in the performance of the contract so that interruptions, even when occasioned by events reasonably and normally to be expected; in the course of such operation, should be compensated the same as was provided for actual dredging work. The findings of the trial court evidence an acceptance of this view. In this, we think the trial court fell into error, for it is. our conclusion that the contract may not. be so construed.

By the contract in question, Arundel rented to Gibbs the hydraulic dredge, Admiral, fully manned and equipped for the purpose of dredging a specified area. For this service, Gibbs agreed to pay as. rent $150 per operational hour 1 for the first 600 operational hours and $130 for each additional operational hour in excess of 600, provided that the total “cost” of the “job” to Gibbs would not exceed the sum of $150,000, of which amount $10,000 was attributable to mobilizing and demobilizing the dredge. In other words, the maximum amount Gibbs was required to pay under the express terms, of the agreement, excluding the fixed incidental fee, was $140,000, and this, amount was to be paid only in the event the total operating time equalled or exceeded 984.6 hours. 2 The contract makes no provision for the payment of rent or compensation for non-operating time, but, in fact, limits the payment to actual operational time not to exceed the maximum provided. We find in the record no basis for the allowance of $130 per hour for non-operating time and the provisions of the contract will not properly bear the construction that Gibbs impliedly warrants that there will be no interruptions of operations or that if there *564 are such interruptions Arundel will be compensated the same as if the dredge had been accruing actual operating hours during such period. Especially is this true since the contract specified an upset price and provided that even this full sum would not be paid in the event the total operating time did not exceed that provided in the contract.

Arundel’s third claim for additional compensation relates to the dredging of an area in which rock was encountered in the approach channel between November 15th and 25th, just before the completion of the contract. As to this, the court allowed the claim for “7 days of dredging in lieu of blasting.” In the approach area, Arundel encountered a ledge of hard rock which it determined should be blasted instead of dredged. 3 This was discussed with Gibbs and, at Gibbs’ request, an estimate was made as to the comparative cost of blasting and of dredging the material without blasting. Arundel’s superintendent estimated that it would cost about $12,000 to drill and blast the 12,-000 cubic yards of rock and would take about three days to clear it out after it had been blasted. He further estimated that if the rock were not blasted it would be necessary to operate the dredge at a slower rate of speed and it would take about seven days to dredge the rock out. 4 The estimated cost in either event would be about the same amount. Since it appeared that there would be no appreciable difference in the cost of removing the rock whether it were drilled and blasted or dredged without blasting, Gibbs elected not to blast and so instructed Arundel. Thereafter, the entire approach channel, including the 12,000 cubic yards of rock, was dredged without blasting.

In its complaint, Arundel alleged that due to this agreement with Gibbs it undertook to, and did, remove the rock entirely by dredging and that it was required to, and did, operate its dredge under this agreement for seven additional days over and above the time it would have been necessary to use the dredge if blasting had been resorted to. The trial court found that ten days’ dredging was required to finish the job after the date Gibbs notified Arundel of its election not to blast and, subtracting the three days estimated to be the time which would have been required if the rock had been blasted, found that seven days additional dredging time was necessitated by the failure to accept Arun-del’s recommendation to drill and blast. Based upon this finding the court allowed this claim.

An examination of the record discloses that this finding is based upon Arundel’s estimate made prior to the actual dredging of the approach area upon which the decision not to blast was made. The fact is, however, that it did not take ten days operational time to dredge the entire approach channel and actual experience proved that the estimate was incorrect. The approach channel, including the 12,000 cubic yards of rock, was dredged of 29,598 cubic yards of material in a total of less than 6 days operational time. This exceeded the time estimated for the removal of the rock if it had been drilled and blasted by only 2 days and a few hours. The record furnishes no basis for a finding of how much of *565

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
209 F.2d 561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibbs-corp-v-arundel-corp-ca5-1954.