Getma International v. Republic of Guinea

862 F.3d 45, 2017 WL 2883755, 2017 U.S. App. LEXIS 12138
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 7, 2017
Docket16-7087
StatusPublished
Cited by3 cases

This text of 862 F.3d 45 (Getma International v. Republic of Guinea) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Getma International v. Republic of Guinea, 862 F.3d 45, 2017 WL 2883755, 2017 U.S. App. LEXIS 12138 (D.C. Cir. 2017).

Opinion

SRINIVASAN, Circuit Judge:

This case arises from a contract dispute between two foreign entities: Getma International, a French company, and the Republic of Guinea. After Guinea terminated a concession agreement between the two parties, an arbitral tribunal issued a €39 million award (plus interest) in favor of Getma. Guinea appealed the award to the Common Court of Justice and Arbitration of the Organization for the Harmonization of Business Law in Africa (CCJA), a court of supranational jurisdiction for Western and Central African States. The CCJA set aside Getma’s award. Getma nonetheless seeks to enforce the annulled award in the United States.

For us to intervene in this quintessentially foreign dispute, we would need to find the CCJA’s annulment of the award to be repugnant to the United States’s most fundamental notions of morality and justice. The district court held that Getma failed to satisfy that stringent standard, and we agree.

I.

In 2008, Guinea sought bids to expand and operate a port in Conakry, the country’s capital. Getma submitted the winning bid. Getma and the Republic of Guinea then entered into a twenty-five-year Concession Agreement. Their partnership was short-lived. In December 2010, Guinea elected a new president, who quickly terminated the Agreement. Getma, protesting that the government’s sudden about-face violated the contract, demanded a termination fee. Guinea denied any breach of the contract, alleging among other complaints that Getma had won the bidding process by bribing the previous Guinean administration.

The Agreement’s dispute-resolution provision stipulated that the parties could “irrevocably settle[]” any disputes through “arbitration proceedings subject to the Arbitration Rules of the [CCJA].” J.A. 249. The parties selected a tribunal of three arbitrators, all of whom were based in France. The CCJA fixed the arbitrators’ fees at approximately €61,000. After 14 months of arbitration, the arbitrators contacted the CCJA’s Office of the Secretary General (which served as a liaison between the arbitrators and the CCJA) about increasing the fees to €450,000. In an e-mail, a representative responded that the office would “contact the [CCJA] soon to adjust the fees.” J.A. 1408.

The CCJA denied the request by written order, citing precedent establishing that an “arbitrator’s fees and expenses are set exclusively by” the CCJA. J.A. 541-42, 554. The arbitrators did not take no for an answer. Immediately after the decision, the arbitrators wrote the CCJA two letters renewing their request for increased fees. Likewise, Getma sent its own letter urging the CCJA to reconsider its decision. The CCJA remained unmoved. By April 2014, the CCJA had apparently informed the arbitrators on four separate occasions that the €61,000 fee would stand.

Disregarding the CCJA’s decision, the arbitrators told the parties they would withhold the arbitral award until the parties paid them €450,000. When the CCJA’s Secretary General learned about the arbitrators’ demand, he reprimanded them and told them that their fee request was void. In a written letter, the Secretary warned Getma that the award would be “subject to invalidation” if it included an “invalid arrangement” for arbitrator fees. J.A. 839.

*48 A few days later, the arbitrators issued a decision in favor of Getma, awarding the company €39 million plus interest. Although the award contained no mention of any demand for increased arbitrators’ fees, the tribunal continued pursuing payment. And despite the CCJA’s warning that an invalid fee arrangement could jeopardize any award, Getma paid the arbitrators €225,000. The arbitrators later filed suit in the Paris Court of Appeals to collect the remaining €225,000 ostensibly owed by Guinea. The Court ordered Getma to pay the balance (plus interest) on a theory of joint and several liability.

Meanwhile, Guinea filed an annulment petition with the CCJA, asking the court to set aside the arbitral award. Sitting en banc, the CCJA annulled the award. The court concluded that the arbitrators “breached [their] duty by deliberately ignoring the mandatory provisions” governing fees. J.A. 1468. It added, however, that “the arbitral proceedings may be reopened.” J.A. 1471. To date, Getma has not sought to reopen the proceedings.

Getma instead pursued relief in the United States, seeking enforcement of its now-annulled award under the Federal Arbitration Act, 9 U.S.C. §§ 201-208. The Act implements the Convention on the Recognition and Enforcement of Foreign Arbi-tral Awards, better known as the New York Convention. Under the New York Convention, a district court may refuse to enforce a foreign award if “a competent authority” has set it aside under the law of the country in which the award was made. New York Convention art. V(1)(e), June 10, 1958, 21 U.S.T. 2517. The district court refused to enforce the annulled award on that ground. In re Arbitration of Certain Controversies Between Getma Int'l & Republic of Guinea, 191 F.Supp.3d 43, 55 (D.D.C. 2016).

II.

Getma appeals the district court’s decision, arguing that we should give effect to the annulled award. We will enforce an annulled award only if the annulment is “repugnant to fundamental notions of what is decent and just” in the United States. TermoRio S.A. E.S.P. v. Electranta S.P., 487 F.3d 928, 938 (D.C. Cir. 2007) (quoting Tahan v. Hodgson, 662 F.2d 862, 864 (D.C. Cir. 1981)). Getma has not satisfied that demanding burden.

As an initial matter, the parties debate the applicable standard of review. Getma argues that we should review de novo a district court’s decision to confirm or vacate a foreign arbitral award, while Guinea contends we should review for abuse of discretion. This Circuit has not expressly addressed the standard of review, and our sister circuits have disagreed on the issue. Compare Corporación Mexicana de Mantenimiento Integral, S. De R.L. de C.V. v. Pemex-Exploración y Producción, 832 F.3d 92, 100 (2d Cir. 2016), with Asignación v. Rickmers Genoa Schiffahrtsgesellschaft mbH & Cie KG, 783 F.3d 1010, 1014-15 (5th Cir. 2015). “We need not resolve this question” here, as we would affirm the district court “under either standard.” See de Csepel v. Republic of Hungary, 714 F.3d 591, 606 (D.C. Cir. 2013).

On the merits, there is no dispute that the CCJA is “a competent authority” for purposes of article V(l)(e) of the New York Convention. And for reasons of international comity, we have declined to “second-guess” a competent authority’s annulment of an arbitral award absent “extraordinary circumstances.” TermoRio, 487 F.3d at 936-39 (internal quotation marks omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stati v. Republic of Kaz.
302 F. Supp. 3d 187 (D.C. Circuit, 2018)
Stati v. Republic of Kazakhstan
District of Columbia, 2018

Cite This Page — Counsel Stack

Bluebook (online)
862 F.3d 45, 2017 WL 2883755, 2017 U.S. App. LEXIS 12138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/getma-international-v-republic-of-guinea-cadc-2017.