Gerli v. Poidebard Silk Manufacturing Co.

31 A. 401, 57 N.J.L. 432, 28 Vroom 432, 1894 N.J. LEXIS 5
CourtSupreme Court of New Jersey
DecidedNovember 15, 1894
StatusPublished
Cited by9 cases

This text of 31 A. 401 (Gerli v. Poidebard Silk Manufacturing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gerli v. Poidebard Silk Manufacturing Co., 31 A. 401, 57 N.J.L. 432, 28 Vroom 432, 1894 N.J. LEXIS 5 (N.J. 1894).

Opinions

[433]*433The opinion of the court was delivered by

Dixon, J.

On March 28th, 1893, C. & E. Gerli, Eratelli & Company, entered into a contract to sell and deliver in New York, to the .Poidebard Silk Manufacturing Company, thirty bales of extra Piva new silk, deliverable, ten bales July 20th to 25th, ten bales August 15th, and ten bales September 1st to 10th, each installment to be paid for sixty days after delivery, at $5.90 per pound. In consequence of the lateness of the new crop it was impossible for the sellers to make delivery of the first ten bales within the time specified, and on July 27th the buyer extended the time for such delivery until August 1st. On that 'date, the impossibility; still continuing, the buyer notified the sellers that it can-/ celed the contract because of the default and would declinej to receive any of the merchandise ordered. On August 15th the new crop of silk had not yet arrived in New York, but it arrived before September 10th. Under these circumstances one of the members of the selling firm assigned the firm’s rights in the contract to Paul Gerli, the plaintiff, and thereupon he brought this suit against the buyer to recover damages arising from the refusal to accept the installments of August 15th and September 1st to 10th. At the trial the justice denied the right to damages for the installment of August 15th, and directed a recovery of the damages as to the installment of September 1st to 10th. On exceptions taken at the trial each party has assigned error.

The errors assigned by the purchaser will first be considered—

First. That the claim for damages was assignable, so as to authorize the assignee to sue thereon in his own name, is clear on the words of the supplement to the Practice act approved March 4th, 1890. Pamph. L., p. 24. It was a chose in action arising on contract.”

Such a chose in action belonging to a partnership may be transferred by a single member of the firm. Story Part., § 101.

[434]*434Second. The contract was fully proved within the statute of frauds. Evidence introduced on behalf of the defendant showed that its general manager had written and signed a memorandum of the order given for the goods, in which were stated all the terms of the proposed contract, and that thereupon the agent of the sellers had sent to the buyer a written acceptance of the order duly signed. Such proof was suffi - cient. Brown St. of F., § 346.

Third. The other exception pressed by the defendant below is that the trial justice denied the right of the buyer to rescind the contract on the non-delivery of the first installment of silk.

The general rule on this subject was thus laid down by this •court in Blackburn v. Reilly, 18 Vroom 290: “In contracts for the sale of goods, to be executed by a series of deliveries and payments, defaults of either party, with reference to one or more of the stipulated acts, will not ordinarily discharge the other party from his obligation, unless the conduct of the party in default be such as to evince an intention to abandon the contract or a design no longer to be bound by its terms.”

In the 'case cited, this rule was enforced against the buyer. In Trotter v. Heckscher, 13 Stew. Eq. 612, this court, and in Otis v. Adams, 27 Vroom 38, the Supreme Court, enforced it against the seller.

That the conduct of the vendors in the present case did not evince an intention to abandon the contract or not to be bound by its terms, appears beyond dispute. They failed to deliver the July installment because it was impossible to do so, offered to deliver other silk which they considered equally valuable, expressed their willingness to come to an equitable arrangement for their default, and, on the first intimation of a purpose on the part of the vendee to rescind the contract, they protested against the right of rescission and insisted that they should be permitted to make the subsequent deliveries. They showed a design the very opposite of repudiation.

bTor do we find anything in this contract or the circumstances of the parties from which it can reasonably be inferred [435]*435-that the parties intended the delivery of each installment of -silk to be a condition precedent to the continuing obligation ■of the contract. So far as appears, the usefulness to the buyer of any installment did not at all depend upon the prompt delivery of prior installments, and full indemnity for ■every default could be secured by action based thereon. So ■that, under the rule before declared, it would seem that the ■attempt to rescind was illegal.

The defendant, however, insists that the rule is not applicable to the present case, because the sellers' fault consisted in failing to do the first thing required to be done in performance of the contract, and Norrington v. Wright, 115 U. S. 188, is cited as an authority for this distinction.

On principle, I do not see that, for such a purpose, the first -act to be done stands upon a different footing from subsequent acts. A default in that does not make it more certain than •do other defaults that the party aggrieved cannot get exactly what he contracted for; for that default, as well as for others, ■he may be compensated by suit, and by that default, as readily as by others, he may obtain an unconscionable advantage if he is entitled to rescind or retain the bargain as self-interest may dictate. As evidence of repudiation or abandonment, 'non-performance of the first thing-required to be done may be more persuasive than if the promisor had partially carried •out his contract-, but, as a basis on which a right of rescission is to be supported, it cannot, merely because it is first in order ■of time, have any greater importance than later defaults.

In Norrington v. Wright, ubi supra, the plaintiff had contracted to ship from Europe to the defendant, in Philadelphia, •one thousand tons of rails in each of the months of February, March, April, May and June. In February he had shipped four hundred tons which the defendant had received and paid for, not knowing that less than the required quantity had been shipped. In March the plaintiff had shipped eight hundred and eighty-five tons, and the defendant, on learning of these deficiencies, declared the contract terminated. The court held that he was justified in doing so.

[436]*436I am not sure that I perceive definitely the principle on which this decision was rested. But the case seems now to-be cited for the following paragraph in the opinion of the court: The seller is bound to deliver the quantity stipulated,, and has no right * * * to compel the buyer to accept a less quantity j * * * and when the goods are to be-shipped in certain proportions monthly, the seller’s failure to-ship the required quantity in the first month gives the buyer-the same right to rescind the whole contract that he would .have had if it had been agreed that all the goods should be-delivered at once.”

I cannot but think that there is here some confusion of thought. If a contract of sale requires the delivery of all the goods at once, and the seller tenders only part at the time-specified, certainly the buyer may refuse to accept the part,, but it is scarcely accurate to say his refusal is based upon a> rescission of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. MONTELUCIA VILLAS, LLC
275 P.3d 607 (Court of Appeals of Arizona, 2012)
Western Grocer Co. v. New York Oversea Co.
28 F.2d 518 (N.D. California, 1928)
Seerup v. Goraczkowski
199 N.W. 94 (Supreme Court of Minnesota, 1924)
Brighton Mills v. Bigelow
283 F. 708 (Third Circuit, 1922)
Empire Rubber Manufacturing Co. v. Morris
72 A. 1009 (Supreme Court of New Jersey, 1909)
Rock Island Sash & Door Works v. Moore, Handley Hdw. Co.
41 So. 806 (Supreme Court of Alabama, 1906)
Sullivan v. Visconti
53 A. 598 (Supreme Court of New Jersey, 1902)
Tufts v. People's Bank & Trust Co.
35 A. 792 (Supreme Court of New Jersey, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
31 A. 401, 57 N.J.L. 432, 28 Vroom 432, 1894 N.J. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gerli-v-poidebard-silk-manufacturing-co-nj-1894.