Georgia Power Co. v. United States

633 F.2d 554, 224 Ct. Cl. 521, 1980 U.S. Ct. Cl. LEXIS 239
CourtUnited States Court of Claims
DecidedJuly 16, 1980
DocketNo. 538-77
StatusPublished
Cited by8 cases

This text of 633 F.2d 554 (Georgia Power Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Georgia Power Co. v. United States, 633 F.2d 554, 224 Ct. Cl. 521, 1980 U.S. Ct. Cl. LEXIS 239 (cc 1980).

Opinion

KASHIWA, Judge,

delivered the opinion of the court:

This is a taking claim against the United States, before us on the parties’ cross motions for summary judgment. Georgia Power Company (plaintiff) claims a taking of its electrical powerline easement which, allegedly, is vested 25 feet above full pool elevation of the Clark Hill Reservoir.1 The act complained of is defendant’s failure to regulate mast and antenna heights of recreational sailboats used on the reservoir by the public.

Sometime shortly after 1977 plaintiff raised the power-line at issue to 54 feet above the reservoir’s full pool elevation and now seeks to recover from the United States its costs expended therefor.2 The United States never ordered plaintiff to raise its powerline. Plaintiff did so after a near accident in 1971 and a fatal accident in 1973 in which a passenger in a sailboat was killed when the mast of the sailboat struck plaintiffs powerline. Pursuant to a "hold harmless” provision in plaintiffs easement agree[524]*524ment executed with the United States on December 7, 1951, the Government was not financially liable for the damages resulting from the fatal 1973 accident.3 In addition, a report by defendant disclosed that, as of May 1975, 47 percent of the sailboats permanently moored on the reservoir had masts in excess of 25 feet (with the number predicted to increase).

Plaintiff requested defendant pay for the raising of the powerline. Defendant, acting through the Corps of Engineers, refused, claiming, inter alia, insufficient justification. According to Brigadier General Drake Wilson, Deputy Director of Civil Works:

* * * For the most part, the nonconforming crossings are located in coves and not in the main channels used by the sailboats. Other crossings are located in areas where the practical recreational use of a sailboat is limited by bridges and certain natural constraints.

Prior to the construction of the reservoir, plaintiff was in possession of powerline easements on its Toccoa-Augusta powerline, portions of which traversed land which was subsequently flooded. Negotiations between plaintiff and defendant began in 1945 regarding the status of this Toccoa-Augusta powerline. Rather than condemning the portions of the powerline easements soon to be flooded, by agreement dated February 26, 1951, plaintiff and the United States negotiated a removal and relocation of the powerlines, at the expense of the United States (totaling $232,800). Pursuant to this agreement, on December 7, 1951, plaintiff was given an "easement or right of way” traversing portions of the Clark Hill Dam and Reservoir Project, which was to be "equivalent to the right surren[525]*525dered by [plaintiff] on the land from which the facilities are removed * * *.”4 Thereupon, plaintiff constructed the powerline at a height of 25 feet above the reservoir’s full pool.

Plaintiff argues it possessed a vested property interest in a powerline easement at 25 feet above full pool elevation. Additionally, plaintiff claims defendant’s nonregulation of the height of masts and antennae is a type of "affirmative regulation” constituting permission to use the reservoir by boats which cannot negotiate under the powerline. After consideration of the briefs and oral argument, we hold for defendant and find no taking by the United States.

Even assuming plaintiff did have a vested property interest in a powerline easement at 25 feet above full pool elevation (which we find unnecessary to decide), there was no taking upon which the plaintiff may recover because the interference complained of constituted acts of independent third parties. As such, there is no Fifth Amendment liability on the part of the United States, a rule of law earlier held in a case analogous to the controversy at hand. Minot v. United States, 212 Ct. Cl. 154, 546 F. 2d 378 (1976). See also United States v. General Motors Corp., 323 U. S. 373 (1945).

In Minot the United States had a 34-kilovolt electrical powerline easement over the plaintiffs property. The United States entered into a powerline pooling agreement with the Guam Power Authority (GPA), a public corporation of the Government of Guam, possessing the power of eminent domain and the power to sue and be sued in its own name. This pooling agreement allowed GPA to use the easement possessed by the United States. Subsequently, and without authorization, GPA erected a 115-kilovolt powerline involving, for example, much larger support towers on plaintiffs property. Plaintiff argued GPA’s action amounted to a taking by the United States. The court denied plaintiffs taking claim because (1) the permit issued to GPA by the United States "did not authorize GPA to do anything that the Government had not the common law right to allow it to do,” and (2) any "condemnation” of [526]*526plaintiffs land by GPA’s action was the result of independent local action for which the United States was not liable. 212 Ct. Cl. at 159, 546 F. 2d at 381. Similarly in the instant case, the facts do not reveal any interference by the United States. It was the public boaters — independent third parties — who interfered with plaintiffs use of the powerline.5

At the time the negotiations to relocate plaintiffs power-line were taking place (in the early 1950’s), it was unanticipated by either party that boats with masts tall enough to come in contact with the powerline would ever be used on the reservoir. Also, from the time of these negotiations to the time of the accident, the same regulation containing no restriction on the height of either masts or antennae was in force. In short, there has never been any regulation by the Government of the size of either mast or antenna heights allowed on the reservoir. Although plaintiff argues defendant fixed the height of the powerline at 25 feet, we feel the facts more properly establish that defendant only required a minimum height of 25 feet above full pool elevation.6 Defendant asserts before us that the 25-foot clearance was consistent with the then existing standards of the National Electric Safety Code. Further, it is clear from the December 7, 1951, easement agreement that the risk of the powerline becoming dangerous was allocated solely to plaintiff. Condition 8 of the easement agreement provides:

That the United States shall not be responsible for damages to property or injuries to person which may arise from or be incident to the construction, maintenance, and use of said line.

[527]*527Condition 4 of the easement agreement provides:

That the grantee shall supervise the said line and cause it to be inspected at reasonable intervals, and shall immediately repair any defects found therein as a result of such inspection, or when requested by said officer to repair any defects. Upon completion of the installation of said line and the making of any repairs thereto, the premises shall be restored immediately by the grantee, at the grantee’s own expense, to the same condition as that in which they existed prior to the commencement of such work, to the satisfaction of the said officer.

Also, we find Condition 3, which is reprinted in the margin,7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
633 F.2d 554, 224 Ct. Cl. 521, 1980 U.S. Ct. Cl. LEXIS 239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgia-power-co-v-united-states-cc-1980.