Georgia Power Co. v. Gillespie

176 S.E. 786, 49 Ga. App. 788, 1934 Ga. App. LEXIS 560
Court of Appeals of Georgia·Decided September 29, 1934·No. 23690·Published·Cited by 10 cases

Opinions

Guerry, J.

This was an action brought by Mrs. Nannie Gillespie in the superior court of Barrow eountjr, seeking to recover damages for the death of her husband, Grady Gillespie, as a result of [789]*789the alleged negligence of the defendant. The trial resulted in a verdict and judgment in favor of the plaintiff. The defendant’s motion for a new trial was overruled. To this ruling the defendant excepted.

It appears that during the early part of the fall of 1929, the Georgia Power Company entered into a contract with the Empire Construction Company whereby the Empire Construction Company agreed to rebuild the electric plant in Winder, Georgia, removing all old wires, poles, and cross-arms, and to erect a new system, putting up new poles, cross-arms, and new wires; that Grady Gillespie, the husband of Nannie Gillespie, was employed by the Empire Construction Company as a ground man or ground helper in the rebuilding of said electric system of the Georgia Power Company; that Grady Gillespie’s duties were to help put up poles, wait upon the other employees, and keep all of the dead wires out of the streets; that he was not employed to climb poles or work on said poles, or to handle live wires, and had worked in this capacity for at least six months. During said construction work, the Georgia Power Company continued to carry on its business of furnishing electric power and service to its customers. It further appears that primary electric lines which contained 2300 volts had been reconstructed on Broad street in the direction of the town of Jefferson as far as New street. Before Gillespie was killed, a primary line ran off Broad street down New street about two blocks to a transformer, where the transformer reduced it to a secondary electric line, which carried 110 to 220 volts, and then went on down New street as a secondary line to a dead end. Gillespie was killed on New street between Broad street and said transformer by half insulated wires which were cut on one end, the cut end falling to the ground. On the afternoon of the 16th of October, 1929, about one o’clock in the afternoon, certain crews of the Empire Construction Company were at work on the wires of the Georgia Power Company on Broad street in the city of Winder, and "one of the linemen cut two secondary wires that connected with the primary wires on Broad street,” and the said employee of the Empire Construction Company let the said wires which they cut fall in said Broad street while being heavily charged with an electric current. An agent of the Empire Construction Company (W. P. Cooley) told Grady Gillespie to move the wires which had been cut out of the street, [790]*790instructing him to tie them around a fire plug, and Grady Gillespie picked up said wires, one in each hand, and was instantly killed by the current of 2300 volts sent through said wires. The cutting of the wires would have stopped the electricity in them, and when they reached the ground 30 feet below they would have been dead and no harm would have been done the deceased but for the fact that the Empire Construction Company had, a short time before, constructed an electric line from -Broad street down Wright street, parallel with New street, and had connected this line up with the transformer on New street beyond where Gillespie picked up the wires, thus letting the current flow into the wires from the opposite direction from which they were cut. The method of connecting the Wright street line with the Broad street line which caused the current to flow into the wires that killed the deceased was putting in two plugs and thus connecting the two lines. The employee of the construction company who cut the wires on New street and told Gillespie to remove said wires testified that if he had known the plugs had been put in on Wright street, he would have had them removed before proceeding with the cutting of the wires on New street.

The Empire Construction Company, it seems to us, was an independent contractor, and, if we do not misconstrue the brief of the defendant in error, her attorneys are also of this opinion. It further appeared that “the entire method and means of doing the work in and around Winder was under the complete supervision and control of the independent contractor, Empire Construction Company, and the Georgia Power Company did not exercise any supervision or jurisdiction at all in the construction or reconstruction of said system. There was not any supervision of the Georgia Power Company or any official of the Georgia Power Company or any force of the Georgia Power Company with reference to the construction or rebuilding, or building of the Winder lay-out of the line and service. The Empire Construction Company pursued its own methods.” “The Georgia Power Company had nothing to do with the work or the carrying on of the work, or inspection of the work at the time it was being carried on by and under the independent contractor, the Empire Construction Company.” “When the job was done it was the job of the Empire Construction Company. The Empire Construction Company adopted the method of doing [791]*791tbe job. The Empire Construction Company instructed the employees how the work should be done.” “The evidence was further undisputed that in carrying on this work the Empire Construction Company could malee any of the lines upon which it was working ‘’dead’ wires, as it saw fit. This would be done by pulling certain plugs, and the jurisdiction over this work and the authority to pull those plugs was entirely under the control of the Empire Construction Company.” “The evidence was that there was a safe way of working on wires carrying 2300 volts; that it was standard practice to work on and with live wires carrying 2300 volts, and that there was a safe way of doing and carrying on such work.”

The plaintiff in his petition alleged: “32. That the Empire Construction Company, the contractor of defendant, was negligent in having petitioner’s husband handle live and dangerous wires charged with 2300 volts of current. 33. That said Empire Construction Company was negligent in not notifying petitioner’s husband that said wires were so charged with 2300 volts. 34. That said Empire Construction Company knew, or could have found out that said wires were so charged. 35. That said Empire Construction Company was negligent in not furnishing petitioner’s husband with insulated gloves and equipment with which to handle live and deadly wires as it had him to handle on the date of his death. 36. That said Empire Construction Company was negligent in not having the current cut off before it had petitioner’s husband move said wires from the street at the time he was killed. 37. That said Empire Construction Company was negligent in not advising petitioner’s husband of the extreme danger of handling wire charged with 2300 volts of current; that said construction company knew that petitioner’s husband knew nothing of the handling of live wires, and that he was only a green farmer who had never done work of that nature before he went to work with them.” These paragraphs were afterwards stricken by amendment but were introduced in evidence by the defendant at the trial. The evidence further disclosed that the line which was cut would have been a dead line except for the fact that what had been a dead end had been connected with the line coming down Wright street, and that this connection was made by the employees of the Empire Construction Company on the morning of the day on which the plaintiff’s husband was killed. This fact was not known by the lineman who cut the wire nor by the [792]*792deceased.

Free access — add to your briefcase to read the full text and ask questions with AI

Georgia Power Co. v. Gillespie, 176 S.E. 786, 49 Ga. App. 788, 1934 Ga. App. LEXIS 560 (Ga. Ct. App. 1934).

176 S.E. 786 (Georgia Power Co. v. Gillespie) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Luther v. Wayne Frier Home Center of Tifton, Inc.
592 S.E.2d 470 (Court of Appeals of Georgia, 2003)
Green v. Moreland
407 S.E.2d 119 (Court of Appeals of Georgia, 1991)
Jenkins v. Georgia Power Co.
668 F. Supp. 1574 (N.D. Georgia, 1987)
Allen v. Cooper
244 S.E.2d 98 (Court of Appeals of Georgia, 1978)
Horn v. C. L. Osborn Contracting Co.
423 F. Supp. 801 (M.D. Georgia, 1976)
Hodge v. United States
310 F. Supp. 1090 (M.D. Georgia, 1969)
Community Gas Co. v. Williams
73 S.E.2d 119 (Court of Appeals of Georgia, 1952)
De Bord v. Proctor & Gamble Distributing Co.
146 F.2d 54 (Fifth Circuit, 1944)
Georgia Power Co. v. Maxwell
183 S.E. 654 (Court of Appeals of Georgia, 1936)