Georgia Power Co. v. Georgia Industrial Group

447 S.E.2d 118, 214 Ga. App. 196, 94 Fulton County D. Rep. 2639, 1994 Ga. App. LEXIS 807
CourtCourt of Appeals of Georgia
DecidedJuly 12, 1994
DocketA94A0726
StatusPublished
Cited by2 cases

This text of 447 S.E.2d 118 (Georgia Power Co. v. Georgia Industrial Group) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Georgia Power Co. v. Georgia Industrial Group, 447 S.E.2d 118, 214 Ga. App. 196, 94 Fulton County D. Rep. 2639, 1994 Ga. App. LEXIS 807 (Ga. Ct. App. 1994).

Opinion

Pope, Chief Judge.

Georgia Power appeals the superior court’s order reversing three orders of the Georgia Public Service Commission (Commission) authorizing Georgia Power to recover through riders or surcharges the costs of certain energy conservation programs and “interruptible service credits” paid to customers to reduce their supply of electricity during peak periods.

The issue in this case is whether such costs may be recovered through riders or whether they must be recovered through base rates utilizing the accounting procedure specified in OCGA § 46-2-26.1 for determining the rates to be charged. This case arose out of the legislature’s passage in 1991 of the Integrated Resource Planning Act (IRP), OCGA § 46-3A-1 et seq. The IRP requires utilities to file long-range energy plans for review and approval by the Commission. OCGA § 46-3A-2. It also requires certification by the Commission before a utility can construct or sell an electric plant, enter into a long-term power purchase, or spend money on “demand-side capacity options” (programs that reduce the demand for electricity). OCGA §§ 46-3A-1 (4); 46-3A-3 (a). The IRP allows a utility to recover, inter alia, its costs for any certified demand-side capacity option and an additional sum as determined by the Commission to encourage the development of such demand-side programs. OCGA § 46-3A-9.

In accordance with the IRP, Georgia Power filed its first integrated resource plan with the Commission in January 1992. Although Georgia Power sought approval of 14 demand-side programs for its residential and commercial and industrial customers at this same time, it subsequently withdrew most of these programs with the intent to resubmit revised programs. In September 1992, Georgia Power filed revised demand-side programs for its residential customers and sought a proposed residential demand-side cost recovery rider to recover the costs of such programs. The rider proposed to pass through to residential customers (except low income customers) the expected program costs through 1993, subject to a true-up against actual program costs in a future proceeding at the end of 1993. Any over or under collection would be used, together with projected costs for 1994, to set the rider for 1994. On October 6, 1992, the Commission suspended the proposed residential rider for a period of five months to allow it ample opportunity to address the issues involved. In De[197]*197cember 1992, Georgia Power filed new demand-side programs for its commercial and industrial (C & I) customers and sought two proposed recovery riders to recover the costs of such programs from its customers. One rider applied to large and the other to smaller C & I customers. The Commission held extensive hearings on both the proposed residential and commercial and industrial programs and riders.

Earlier, the Commission had approved two interruptible service riders pursuant to which Georgia Power would pay customers “inter-ruptible service credits” to reduce the electricity they receive during peak demand. In May 1992, the Commission entered an accounting order authorizing Georgia Power to defer payments as to certain of these credits and deferred a final decision as to Georgia Power’s cost recovery of such payments until it considered Georgia Power’s proposed demand-side programs. On January 4, 1993, the Commission issued Certificate of Public Convenience and Necessity No. GPC-1SS, the first of the three Commission orders in question. The Commission held that Georgia Power should be allowed to recover the costs of its “interruptible service credits” through a rate rider since the credits were relatively new and there would be a time period necessary to determine participation levels and customer responses.

On January 11, 1993, the Commission issued Certificate of Public Convenience and Necessity No. GPC-l-DSM, which approved Georgia Power’s residential demand-side programs and, for a three-year trial period, its residential demand-side cost recovery rider. On August 6, 1993, the Commission issued Certificate of Public Convenience and Necessity No. GPC-2-DSM, which approved the demand-side programs Georgia Power proposed for its C & I customers and the two riders to recover the costs of such programs for a three-year trial period.

Appellee Georgia Industrial Group appealed to the Superior Court of Fulton County that portion of all three orders allowing Georgia Power to recover the costs of its demand-side programs and its “interruptible service credits” through a rider mechanism.1 The. superior court reversed the Commission’s orders, finding that such expenses are recoverable only through the test year rate case procedure prescribed by OCGA §§ 46-2-25 and 46-2-26.1, which was not followed in this case. Georgia Power brought this appeal from the superior court’s order, and we reverse.

1. Georgia Power first argues the superior court erred in finding the Commission’s orders did not comply with OCGA § 46-2-25. Pursuant to that section, before any change to any rate, charge, classifica[198]*198tion, or service can be made, the utility must file notice of the proposed change with the Commission and the public at least 30 days before the proposed change is to take effect. OCGA § 46-2-25 (a). It further provides that the Commission may suspend the application of the proposed change for up to five months during which time it can hold hearings on the proposal. OCGA § 46-2-25 (b). Our review of the record reveals that Georgia Power gave the requisite notice of the proposed riders and that the Commission followed the procedure prescribed by § 46-2-25 in considering such riders. As noted above, the Commission suspended the proposed residential rider for a period of five months pending review, and held extensive hearings on both the proposed residential and commercial and industrial programs and riders. Accordingly, the superior court erred in finding the Commission’s orders violated OCGA § 46-2-25.

2. The crux of Georgia Power’s argument on appeal, however, is that the superior court’s ruling is erroneous because the future test year accounting method set forth in OCGA § 46-2-26.1 only applies to general rate cases, which these proceedings do not involve, and because the IRP (OCGA § 46-3A-9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Georgia Public Service Commission v. Campaign for a Prosperous Georgia
492 S.E.2d 916 (Court of Appeals of Georgia, 1997)
Ga. Pub. Serv. v. Cam. for Pros. Ga.
492 S.E.2d 916 (Court of Appeals of Georgia, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
447 S.E.2d 118, 214 Ga. App. 196, 94 Fulton County D. Rep. 2639, 1994 Ga. App. LEXIS 807, Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgia-power-co-v-georgia-industrial-group-gactapp-1994.