Georgia Power Co. v. East Tennessee Fuel, Inc.

496 F. Supp. 626, 1980 U.S. Dist. LEXIS 13173
CourtDistrict Court, E.D. Tennessee
DecidedAugust 6, 1980
DocketCiv. 3-80-120
StatusPublished
Cited by2 cases

This text of 496 F. Supp. 626 (Georgia Power Co. v. East Tennessee Fuel, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Georgia Power Co. v. East Tennessee Fuel, Inc., 496 F. Supp. 626, 1980 U.S. Dist. LEXIS 13173 (E.D. Tenn. 1980).

Opinion

MEMORANDUM

ROBERT L. TAYLOR, District Judge.

This is a breach of contract case. Plaintiff claims $45,623.49 in penalties by reason of defendant’s alleged failure to deliver to plaintiff coal of the proper BTU value as provided for in the contract. The case was referred to a Special Master, who, having heard proof, has recommended that the Court enter judgment in favor of plaintiff for $45,623.49. We sustain the Special Master’s recommendation.

The contract provided that defendants would deliver to plaintiff coal of certain guaranteed “as received” BTU value. The parties further agreed that plaintiff would pay a “premium” for coal having a higher BTU value, but had the right to assess a “penalty” for coal delivered with a lower BTU value. ' Finally, the contract provided that in the event plaintiff failed to sample or analyze any coal, the coal would be deemed to have the guaranteed “as received” value.

The Court agrees with the Special Master that the “premium/penalty” provision in the contract is no more than an agreed-upon price-adjustment scheme based on actual BTU value of delivered coal. There is nothing ambiguous, burdensome, harsh, or otherwise unjust in these provisions which could serve to relieve the defendant of its contractual obligation.

Plaintiff claims that its analysis revealed that the coal delivered by defendant had a BTU value below that guaranteed in the contract, and notified defendant of its penalty assessment. Defendant’s position, in essence, is that adherence to the sampling and analysis standards recognized by the American Society for Testing and Materials (ASTM standards) is an implied term in the contract; that plaintiff failed strictly to adhere to those standards; and thus that plaintiff is precluded from assessing any penalty.

The Special Master found, as a matter of fact, that the ASTM standards were adhered to by plaintiff, save in two respects, and that the evidence showed that neither of these deviations resulted in any prejudice to defendant. He found that plaintiff’s methods were reasonable in nature and led to reasonably accurate results. The Special Master held that the only implied term in the contract, in this respect, *628 was the requirement that plaintiff exercise good faith and commercial reasonableness in its sampling and testing of coal, and found that in view of the reasonableness of the testing procedures, this requirement had been satisfied.

We hold that the Special Master has accurately stated the law and that his findings of fact are supported by substantial evidence in the record. We also sustain, ratify, and adopt the Special Master’s conclusions with regard to the price-adjustment provision.

Accordingly, it is ORDERED that the report of the Special Master and the recommendation contained therein, be,- and the same hereby are, sustained, ratified, and adopted. It is further ORDERED that judgment enter in favor of plaintiffs in the amount of $45,623.49.

Order Accordingly.

SPECIAL MASTER’S REPORT

This is a contract action brought to recover $45,623.49 in penalties assessed against the defendant for allegedly delivering coal to plaintiff that did not meet the contract specifications. This matter was referred to the undersigned for trial pursuant to 28 U.S.C. § 636(b)(2) and with the consent of the parties. Trial was conducted on June 19 and 20, 1980. A complete transcription of the testimony has been filed with the clerk.

The defendant contends that the plaintiff is not entitled to recover the penalty because (1) it violated the terms of the contract by not sampling the coal properly that it received from the plaintiff and (2) because the plaintiff’s testing procedures which were utilized in assessing the penalties did not comply with recognized, industry-wide standards for the testing of coal.

I. Findings of Fact

1. Plaintiff Georgia Power Company is a public utility corporation which is organized and operated under the laws of the State of Georgia. It is a major supplier of electric service to customers throughout that state. Defendant East Tennessee Fuel, Inc., is a corporation which is organized and operated under the laws of the State of Tennessee and is engaged primarily in the business of brokering coal.

2. On March 11, 1977, the defendant submitted a written bid to the coal procurement agent for Georgia Power Company (Southern Company Services) in which the defendant offered to sell coal to Georgia Power Company. In this bid, the defendant offered to supply the plaintiff with coal which was to have the following quality specifications when received by the plaintiff:

BTU/LB. - 11,750 guaranteed
Moisture - 6.0%
Ash - 14.0%
Sulfur - 2.5%

Georgia Power Company accepted this bid and the parties entered into the contract set forth in plaintiff’s purchase order No. J-9073 dated April 19, 1977. Exhibit 3.

3. The contract provided for the assessment of a penalty or a premium when there was a departure from the guaranteed “as received” BTU value. This provision in the contract allowed for an adjustment in the contract price to compensate the defendant if it delivered coal exceeding the guaranteed BTU value or to compensate the plaintiff if the coal delivered did not meet the guaranteed BTU value. Exhibit 3. The plaintiff notified the defendant that it was assessing penalties against the defendant based on the alleged failure of the coal shipped under the contract to meet the guaranteed BTU value. The plaintiff claims that it is entitled to recover $45,-623.49 in penalties.

4. The provision in the contract which is central to the dispute herein provides as follows:

Samples will be taken of the coal received on this order and an analysis made in our laboratory to determine moisture, ash, sulfur, and BTU content on an “as received” basis. If, however, due to unusual conditions, Georgia Power Company does not sample or analyze any of the coal received on this order, the “as received” BTU value of the coal received *629 will be deemed to be the guaranteed “as received” BTU value quoted by seller as indicated herein.

5. The defendant did not inspect the plaintiff’s testing facilities or make inquiry as to the type of sampling and testing procedures that were to be conducted by Georgia Power before the defendant entered into the contract in question.

6. On May 13, 1977, East Tennessee Fuel submitted a second written bid to Southern Company Services in which it offered to sell the plaintiff an additional quantity of coal. On the basis of this second bid, the parties extended the term of the contract through June and July, 1977.

7. The coal in question was mined from the Nemo seam in Winfield, Tennessee. The defendant began supplying coal to the plaintiff on April 1, 1977 and continued to supply coal through April, May and June and during the first week of July, 1977.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Davis Oil Co.
728 P.2d 1107 (Wyoming Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
496 F. Supp. 626, 1980 U.S. Dist. LEXIS 13173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgia-power-co-v-east-tennessee-fuel-inc-tned-1980.