Georgia Interfaith Power & Light v. Georgia Power Company

CourtCourt of Appeals of Georgia
DecidedOctober 29, 2019
DocketA19A1426
StatusPublished

This text of Georgia Interfaith Power & Light v. Georgia Power Company (Georgia Interfaith Power & Light v. Georgia Power Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Georgia Interfaith Power & Light v. Georgia Power Company, (Ga. Ct. App. 2019).

Opinion

SECOND DIVISION MILLER, P. J., RICKMAN and REESE, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. http://www.gaappeals.us/rules

October 29, 2019

In the Court of Appeals of Georgia A19A1426. GEORGIA INTERFAITH POWER & LIGHT et al. v. GEORGIA POWER COMPANY.

RICKMAN, Judge.

Following the Georgia Public Service Commission’s (“the PSC”) order

regarding the 17th Georgia Power Company’s Plant Vogtle construction monitoring

report (“VCM”), Georgia Interfaith Power and Light, Inc., Partnership for Southern

Equity, Inc., and Georgia Watch filed petitions for judicial review of a final decision

by the PSC, which were consolidated. The superior court granted Georgia Power

Company’s motion to intervene and subsequently, Georgia Power filed a motion to

dismiss the petitions for lack of jurisdiction.

The superior court granted Georgia Power’s motion to dismiss, finding that the

PSC’s 17th VCM order was not appealable. The appellants contend that the superior court erred by granting Georgia Power’s motion to dismiss.1 For the following

reasons, we affirm in part and vacate and remand in part with direction.

We apply a de novo standard of review to the superior court’s grant of a motion

to dismiss. See Alcatraz Media v. Yahoo, 290 Ga. App. 882, 882 (660 SE2d 797)

(2008). The record shows that in 2009, the PSC approved Georgia Power’s

construction of two new Units, Units 3 and 4, at the already existing Plant Vogtle site.

The order approving Units 3 and 4 required Georgia Power to file semi-annual

monitoring reports with the PSC, and the PSC has conducted multiple VCM

proceedings to consider these reports.

In March 2017, the lead contractor for Units 3 and 4 declared bankruptcy.

Approximately five months later, Georgia Power filed a 17th semi-annual

construction monitoring report. In the filing, Georgia Power requested, inter alia,: that

“the [PSC] approves the new cost and schedule forecast and find[] that it is a

reasonable basis for going forward;” that Georgia Power will “retain[] the burden of

1 The appellants also enumerate as error that the trial court erred by “effectively denying” their request for discovery. This enumerated error, however, is not supported in the appellants’ brief with citation of authority or argument, and thus, we deem it abandoned. See Parekh v. Wimpy, 288 Ga. App. 125, 126 (1) (653 SE2d 352) (2007) (“any enumeration of error which is not supported in the brief by citation of authority or argument may be deemed abandoned”) (citation and punctuation omitted); Court of Appeals Rule 25 (c) (2).

2 proving all capital costs above $5.68 billion were prudent”; “[t]hat while [the] [PSC]

will make no prudence findings in the . . . VCM 17 proceeding . . . the [PSC]

recognizes that the certified amount is not a cap, and all costs that are approved and

presumed or shown to be prudently incurred will be recoverable by Georgia Power”;

and “[t]hat as conditions change and assumptions are either proven or disproven,

[Georgia Power and the other Plant Vogtle owners] and the [PSC] may reconsider the

decision to go forward.”

Subsequently, the PSC issued a procedural and scheduling order to govern the

17th VCM proceeding. The scheduling order outlined two issues to be addressed in

the 17th VCM proceeding: (1) “Whether the [PSC] should verify and approve or

disapprove the expenditures as made pursuant to [the order approving Units 3 and 4]

issued by the [PSC].”; (2) “Whether the [PSC] should approve, disapprove, or modify

[Georgia Power’s] proposed revisions in the cost estimates, construction schedule,

or project configuration and whether the proposed costs are reasonable.”

Following a multiple day hearing on the 17th VCM, the PSC issued an order

finding “that the $542 million invested by Georgia Power within the 17th VCM . . .

reporting period were reasonable and necessary, and are hereby verified and

approved.” The PSC included a caveat that “[t]he [PSC] is only confirming the

3 expenditures made in association with the Vogtle Project during this reporting period

and it does not preclude the [PSC] from subsequently excluding those expenditures

from rate base upon a finding of fraud, concealment, failure to disclose a material

fact, imprudence, or criminal misconduct.” The PSC further found that it was

appropriate to continue with the construction of Units 3 and 4, that Georgia Power’s

revised schedule and cost forecast was reasonable, and that the revised project

management structure was approved.

Additionally, the PSC cautioned that it

[found] as a matter of fact and conclude[d] as a matter of law that no directives or findings in any part of this Order suggest that there is a cost cap or that the [PSC] has approved or disapproved the recovery of any costs from customers. All decisions regarding cost recovery from customers will be made later in a manner consistent with Georgia law and the Stipulation approved by the [PSC] on January 3, 2017 and this decision.[2] The [PSC] further finds that any costs spent up to the revised cost forecast will be deemed reasonable, but will be subject to the findings and presumptions as defined in the Stipulation approved on January 3, 2017. This includes th[at] [Georgia Power] retain[s] the burden of proof on prudency on all capital costs above $5.680 billion.

2 As part of the January 3, 2017 stipulation order, capital costs incurred up to $5.68 billion are presumed to be reasonable and prudent. The burden of proof rests on the party challenging any such costs. Georgia Power bears the burden to show that capital costs above $5.68 billion are reasonable and prudent.

4 The order explained that, “[t]he [PSC] finds that it will continue to conduct

semi-annual VCM reviews and, as appropriate, verify and approve all expenditures

on a semi-annual basis regardless of whether they exceed the original certified

amount.” Further, “[d]uring these VCM reviews, the [PSC] will not determine

prudence, nor will it assure cost recovery to [Georgia Power]. All [PSC] decisions

regarding cost recovery will be made after a prudence review at the end of

construction of Units 3 and 4.”

Following the PSC’s 17th VCM order, the appellants filed petitions for judicial

review, which were consolidated. Georgia Power intervened in the action and filed

a motion to dismiss the petitions for lack of jurisdiction. The superior court granted

Georgia Power’s motion to dismiss, finding both that the 17th VCM order was not

a final order under OCGA § 50-13-19 (a) and that the exception in that provision,

which provides that “[a] preliminary, procedural, or intermediate agency action or

ruling is immediately reviewable if review of the final agency decision would not

provide an adequate remedy,” did not apply to this case. This appeal follows.

1. The appellants contend that “[t]he trial court erred by granting Georgia

Power’s motion to dismiss the case, concluding that it lacked jurisdiction based on

its finding that the 17th VCM Order was not final.” We disagree.

5 Judicial review of an administrative ruling by the PSC is governed by the

Georgia Administrative Procedure Act (“APA”), OCGA § 50-13-1 et seq. Pursuant

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Theo v. Department of Transportation
287 S.E.2d 333 (Court of Appeals of Georgia, 1981)
Carr v. Carr
232 S.E.2d 69 (Supreme Court of Georgia, 1977)
Majanovic v. Georgia Department of Human Resources
294 S.E.2d 669 (Court of Appeals of Georgia, 1982)
Atmos Energy Corp. v. Georgia Public Service Commission
659 S.E.2d 385 (Court of Appeals of Georgia, 2008)
Alcatraz Media, LLC v. Yahoo! Inc.
660 S.E.2d 797 (Court of Appeals of Georgia, 2008)
Parekh v. Wimpy
653 S.E.2d 352 (Court of Appeals of Georgia, 2007)
Wilken Investments, LLC v. PLAMONDON, III
712 S.E.2d 576 (Court of Appeals of Georgia, 2011)
SN International, Inc. v. Smart Properties, Inc.
715 S.E.2d 826 (Court of Appeals of Georgia, 2011)
Ronald Ruth v. Cherokee Funding LLC
802 S.E.2d 865 (Court of Appeals of Georgia, 2017)
Wallace v. Wallace
800 S.E.2d 303 (Supreme Court of Georgia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Georgia Interfaith Power & Light v. Georgia Power Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgia-interfaith-power-light-v-georgia-power-company-gactapp-2019.