Georgetown Construction Co. v. Moss & Donovan

290 S.W. 1070, 218 Ky. 32, 1927 Ky. LEXIS 107
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedFebruary 1, 1927
StatusPublished
Cited by1 cases

This text of 290 S.W. 1070 (Georgetown Construction Co. v. Moss & Donovan) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Georgetown Construction Co. v. Moss & Donovan, 290 S.W. 1070, 218 Ky. 32, 1927 Ky. LEXIS 107 (Ky. 1927).

Opinion

Opinion of the Court by

Judge Logan

Reversing.

Appellants during- tlie time covered by the contract out o-f which this litigation grew were a firm composed *33 of J. W. Coyle, J. M. Perkins and R. E. Mason and they were eng'aged in the business of constructing public highways in the state of Kentucky under contract with the State Highway Commission. They obtained a contract from the State Highway Commission in the latter part of 1924 to construct certain portions of the public highway between .Georgetown and Owenton, and the next •spring they made a contract with appellees, Moss and Donovan, a firm, composed of Clarence Donovan and Henry Moss, under which contract the appellees were to produce for appellants crushed stone to be used by them in connection with the carrying out of their contract. Under the terms of the contract between appellants and appellees, the appellants were to furnish appellees (1)' rock in the quarry; (2) adequate and suitable engine, crusher, screens and other equipment necessary for the production of said stone; (3) provide and. furnish sufficient trucks or wagons to haul the stone from the crusher as it was crushed; (4) .to pay appellees 73 cents per ton for all stone crushed and delivered.

' While the contract was verbal there seems to be little disagreement as to the general terms of it. There is a sharp disagreement, however, as to the price which was to be paid for the services to be rendered under the contract by appellees. The payment was to be based on the tonnage, and the price per ton which was to be paid by appellants for the crushed stone was 73 cents, but appellees contend that the 73 cents tonnage price covered only, the crushed stone and did not include what is known as “chips;” that appellants were to pay them for the “chips” produced the price of $1.50 per ton. This is denied by appellants, and we believe the most tangible controversy between the parties is over this, one item. It is contended by appellees that after making the contract appellants directed them not to separate the “chips” from the other crushed stone but to run them all through together and the appellants would pay for the “chips” the same as if they had been separated. It is also contended by appellees that appellants refused to furnish the necessary screens or equipment for separating the “chips” from the other crushed stone. It is alleged.by appellees and substantiated by their testimony that they produced 21,749 tons of crushed stone and of this not less than 15% of the total amount of crushed stone *34 would have been “chips” if appellees had 'been allowed to separate the “chips” from the crushed stone, or that there would have been 3,262.35 tons of “chips” if they had been allowed to separate them as it was agreed should be done at the time the contract was made, according to their contention. The total tonnage produced seems to have been slightly modified by the checking up of the State Highway Commission. Appellees contend that they were paid on the basis of 73 cents a ton for the “chips” which-they would have produced and that there was a balance due them on this item of $2,512.00. This may be called the first item in their complaint.

All of this is denied by appellants, who insist that there was no agreement as to “chips” and that the full price which'they were to pay was 73 cents per ton for the entire tonnage produced.

The second item on which appellees base a claim for damage or compensation is that they produced 21,794 tons of crushed stone including the “chips” and that at the price of 73 cents a ton, as contended for by appellants, they should have received $15,876.77, but they were in fact paid only the sum of $15,696.27, leaving a balance due and unpaid of $180.50.

This is denied by appellants, who contend that on a final checking up of accounts it was found that they had overpaid the appellees in the sum of $117.67, for which they make a counterclaim.

A third ground upon which appellees base their cause of action is that appellants failed and refused to furnish sufficient wagons or trucks to haul the stone away from the crusher after it was crushed, and that by reason thereof appellees were compelled to shut down a great portion of the time. This ground was amended, and it was claimed appellees were compelled to shut down or cease operations on account of defective equipment furnished by appellants. Appellees contend that if they had not been compelled to shut down their operations! by, reason of these things they would have produced 8,000 tons additional, of which 15% would have been “chips,” and that their compensation would have been thereby increased $6,764.00.

This is all vigorously denied by appellants, who claim that it was understood at the time the contract was entered into that no claim should be made by either party *35 against the other on account of delays caused by matters incident to the business.

The fourth ground of complaint set up by. appellees is that they furnished three meals each day for the truck drivers employed by appellant during the period covered by the contract, or a total of 1,704 meals, and that appellants agreed to pay a reasonable price therefor, which would be $426.00, and that only $100.00 had been paid, leaving a balance of $326.00.

Appellants claim that there was an agreement as to the meals furnished the truck drivers and that they were to pay $100.00, for these meals, which has been paid.

The fifth and last complaint made by appellees is that by reason of the inadequacy' of the engine furnished by appellants it was necessary to install a motor, and that appellees incurred an additional expense in the way of electric current and other expenses in the sum of $385.00. Appellants admit that the motor was installed, but insist that the operation thereafter was less expensive than, before the installation of the motor.

The total amount which appellees sought to recover by reason of the alleged breaches of the contract was $10,167.50. The issues were made up with the pleadings clearly disclosing each separate issue.

We have examined the evidence with care and it is as conflicting as it is possible for evidence to be. The appellees support their claims by the evidence, and if they are correct and if their witnesses were believed by the jury a verdict in favor of appellees was justified. The evidence was equally strong and in some instances probably stronger for appellants, but the evidence was for the jury, and the fact that we might disagree with the conclusions reached by the jury affords no basis for a reversal of any case submitted to a jury under proper instructions. Such lawsuits as this one are to be determined by juries, and where the evidence is conflicting the verdict of the jury should not be disturbed if the rights of all the parties were fully protected as to the law by the instructions of the court. The instructions in this ease given by the court are numerous and those offered by appellants and refused by the court are still more numerous. While there were a number of issues to be determined by the jury they were not complicated and it was peculiarly within the province of the jury to deter *36

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barnett v. Hagans
445 S.W.2d 839 (Court of Appeals of Kentucky, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
290 S.W. 1070, 218 Ky. 32, 1927 Ky. LEXIS 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgetown-construction-co-v-moss-donovan-kyctapphigh-1927.