George Wise v. Department of Transportation

943 F.3d 1161
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 6, 2019
Docket18-3016
StatusPublished
Cited by4 cases

This text of 943 F.3d 1161 (George Wise v. Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Wise v. Department of Transportation, 943 F.3d 1161 (8th Cir. 2019).

Opinion

United States Court of Appeals For the Eighth Circuit ___________________________

No. 18-3016 ___________________________

George Wise; Matthew Pekar; Uta Meyer; David Martindale; Robert Walker

lllllllllllllllllllllPlaintiffs - Appellants

v.

Department of Transportation, United States; Federal Highway Administration; Arkansas Department of Transportation

lllllllllllllllllllllDefendants - Appellees ____________

Appeal from United States District Court for the Eastern District of Arkansas - Little Rock ____________

Submitted: September 26, 2019 Filed: December 6, 2019 ____________

Before SMITH, Chief Judge, WOLLMAN and ERICKSON, Circuit Judges. ____________

WOLLMAN, Circuit Judge.

This action arises from the widening of Interstate Highway 630 from six to eight lanes from Baptist Hospital to University Avenue (approximately 2.5 miles) within the City of Little Rock, Arkansas (the I-630 project). George Wise and others filed suit against the U.S. Department of Transportation, the Federal Highway Administration (FHWA), and the Arkansas Department of Transportation (Arkansas DOT), alleging violations of the National Environmental Policy Act of 1969 (NEPA), 42 U.S.C. § 4321 et seq., and NEPA’s implementing regulations, 40 C.F.R. §§ 1500- 1508. Wise also filed a motion for a temporary restraining order, seeking to enjoin the defendants from working on the I-630 project. Wise appeals from the denial of injunctive relief, arguing that the district court1 erred in determining that the I-630 project qualified for a categorical exclusion under 23 C.F.R. § 771.117(c)(22). We affirm.

I. Background

NEPA requires federal agencies to prepare an environmental assessment or an environmental impact statement for “major Federal actions significantly affecting the quality of the human environment.” 42 U.S.C. § 4332(2)(C). “NEPA itself does not mandate particular results, but simply prescribes the necessary process.” Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350 (1989). Categories of actions “which do not individually or cumulatively have a significant effect on the human environment and which have been found to have no such effect” do not require an environmental assessment or an environmental impact statement. 40 C.F.R. § 1508.4; see Friends of Richards-Gebaur Airport v. FAA, 251 F.3d 1178, 1185-87 (8th Cir. 2001) (setting forth the regulatory background that allows agencies to “categorically exclude certain types of federal activities from [NEPA’s] case-by-case environmental assessment review”). FHWA has identified certain actions that do not involve significant environmental impacts and thus qualify for categorical exclusion from NEPA’s requirements. See 23 C.F.R. § 771.117. At issue here is the categorical exclusion for projects that take place “entirely within the existing operational right- of-way.” See id. § 771.117(c)(22).

1 The Honorable James M. Moody, Jr., United States District Judge for the Eastern District of Arkansas.

-2- In October 2016, the defendants reported that the I-630 project qualified for a categorical exclusion from NEPA’s environmental assessment or environmental impact statement requirements. The categorical exclusion report outlined the improvements proposed along I-630, including increasing the travel lanes from six to eight and replacing all bridges within the project’s limits. The report noted that the “[e]xisting right of way width varies, ranging from 220 to 400 feet” and explained that the project did not require any “additional permanent right of way.” Arkansas DOT already owned the land that would be used for the I-630 project.

Arkansas DOT issued a press release on July 13, 2018, stating that construction on the I-630 project would begin on Monday, July 16. Wise filed suit and moved for a temporary restraining order two days later. During a status conference held on Friday, July 19, 2018, Wise characterized the demolition of the Hughes Street Overpass as the harm that would be done “between now and Monday,” when the hearing on Wise’s motion for a temporary restraining order would be held. Wise asked the district court to disallow demolition of the overpass and immediately enjoin the defendants from working on the I-630 project. The district court declined to do so, and the Hughes Street Overpass was demolished that weekend.

Keli Wylie, the program administrator of Arkansas DOT’s Connecting Arkansas Program, testified at the hearing on Wise’s motion. She explained that the existing operational right-of-way included traffic lanes and clear zones, “which, in layman’s terms, [are the areas] outside of the shoulder of the roadway[, and] . . . in this case it’s 30 feet beyond the edge of the travel way.” Wylie testified that the existing operational right-of-way was not limited to those areas, however, because it also included “mitigation areas, drainage areas, interchange ramps, anything that we maintain or use for transportation purposes.” She explained that the right-of-way for the I-630 project was clear, but that Arkansas DOT would remove any other trees, if necessary, to complete the project. According to Wylie, the existing operational

-3- right-of-way was “property line to property line”—i.e., the entire 220- to 400-foot expanse owned by Arkansas DOT.

After reviewing the evidence, “particularly the testimony of Keli Wylie,” the district court concluded that Wise had “failed to establish that any part of the I-630 project construction would go outside of the existing operational right-of-way” and that it was therefore reasonable for the defendants to conclude that the project qualified as a categorical exclusion under the regulation. D. Ct. Order of July 27, 2018, at 6. The district court thus denied injunctive relief because, among other things, Wise had not shown he was likely to succeed on the merits of his claim that the defendants violated NEPA.

II. Analysis

We reject the defendants’ argument that we lack jurisdiction over this interlocutory appeal. We have jurisdiction under 28 U.S.C. § 1292(a)(1) because the district court’s order had the practical effect of denying a preliminary injunction. See Abbott v. Perez, 138 S. Ct. 2305, 2319 (2018) (“We have previously made clear that where an order has the ‘practical effect’ of granting or denying an injunction, it should be treated as such for purposes of appellate jurisdiction.”); Sampson v. Murray, 415 U.S. 61, 86-88 (1974) (treating an order labeled a temporary restraining as a preliminary injunction because it had the same practical effect as a preliminary injunction). We also reject Arkansas DOT’s argument that the appeal should be dismissed as moot because the action that Wise sought to enjoin has been completed. Arkansas DOT contends that Wise merely sought to enjoin the demolition of the Hughes Street Overpass. The record and the district court’s order make clear, however, that Wise sought to enjoin any further work on the I-630 project, and Arkansas DOT’s argument to the contrary is misguided.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Missouri v. U.S. Department of Interior
73 F.4th 570 (Eighth Circuit, 2023)
Dakotans for Health v. Kristi Noem
52 F.4th 381 (Eighth Circuit, 2022)
Adventist Health System v. U.S. Dept. of HHS
17 F.4th 793 (Eighth Circuit, 2021)
MPAY Inc. v. Erie Custom Computer
970 F.3d 1010 (Eighth Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
943 F.3d 1161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-wise-v-department-of-transportation-ca8-2019.