George v. Oren Ltd. & Associates

672 P.2d 732, 1983 Utah LEXIS 1148
CourtUtah Supreme Court
DecidedAugust 29, 1983
Docket18359
StatusPublished
Cited by10 cases

This text of 672 P.2d 732 (George v. Oren Ltd. & Associates) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George v. Oren Ltd. & Associates, 672 P.2d 732, 1983 Utah LEXIS 1148 (Utah 1983).

Opinion

HALL, Chief Justice:

Plaintiff Prank R. George, dba George & Son Construction, brought this action to recover sums alleged due for services and materials provided in the installation of improvements upon defendant’s property, and for a lien against the property so served. Defendant Oren Limited & Associates counterclaimed for damages upon the theory that plaintiff’s alleged untimely performance constituted a breach of contract. The trial court entered judgment in plaintiff’s favor, awarding him damages in the amount of $58,482.41 and attorney fees of $2,700, and dismissing defendant’s counterclaim. Defendant seeks reversal of only the money judgment on this appeal.

In May, 1979, the parties entered into a series of written contracts whereby plaintiff agreed to install improvements (curb and gutter, sidewalks, water and sewage lines, and street paving) within a subdivision located in Farmington, Utah. Inasmuch as these improvements were to eventually become the property of Farmington City (hereinafter “the City”), they were designed and inspected by the City.

To guarantee the completion of the improvements, as well as the entire subdivision project, the City required that defendant, as developer, provide a bond in the amount of $269,500, and that the bond be deposited in an escrow account. Funds in this account were released by the escrow *734 holder (American Savings) for the purpose of paying construction expenses only upon the written approval of the City.

Plaintiff commenced installation of the improvements in May, 1979. Approximately one month later (June 6, 1979), he submitted his first bill, which was paid promptly by defendant. Thereafter, he continued to bill defendant on a monthly basis and to receive payments from defendant as billed, until October, 1979. The bill submitted by plaintiff in October for the work performed during the month of September was only partially paid. However, plaintiff received assurances at that time from John W. Sullivan, a partner in the defendant partnership, that the balance would definitely be paid. On the basis of Mr. Sullivan’s assurances, plaintiff continued his work through the months of October and November. He then presented a bill on November 21, 1979, for the balance due from September and for the additional work performed during October and November. This bill was not paid, although again plaintiff received assurances that funds were forthcoming. Plaintiff did not, however, resume installation thereafter.

In May, 1980, Mr. Sullivan tendered to plaintiff a letter addressed to the Farming-ton City Council, authorizing the Council to release such funds from the bond (escrow account) as were owed to plaintiff. Upon presentment of this letter to the City, plaintiff was informed that the bond (escrow) had been exhausted. Thereupon, plaintiff filed a notice of lien against the subdivision property in the amount of $42,687.50. On July 15, 1980, he instituted the present action to recover the amount owing and enforce the lien.

At trial, the evidence clearly showed that at the times of plaintiff’s execution and performance of the contracts in issue, unbeknownst to defendant or any of its individual partners, plaintiff was not licensed to engage in the business of a contractor. Plaintiff therefore acted in violation of U.C.A., 1953, § 58-23-1. 1

The evidence further revealed that although plaintiff had been duly licensed as a contractor from 1957 to 1969, he had failed to renew his license, notwithstanding his continued involvement in the business as a contractor, during an eleven-year period between 1969 and 1980. According to plaintiff’s testimony, his failure to become licensed during this extended period of time was not attributable to inadvertence or negligent oversight, but rather to willful disregard of the State’s licensing requirements. He testified as follows:

Q Any other reason you didn’t license in 1970 or in subsequent years?
A Yes, there was a reason.
Q What was that?
A I didn’t like the bureaucracy that dominated that sort of thing.
[[Image here]]
Q You indicated, Mr. George, you didn’t like the bureaucracy. Why didn’t you like the bureaucracy of the licensing department?
A Well, it was my contention they were revenue raising agencies. They are not a regulator. They don’t know whether I know what I am doing or not.

Plaintiff became relicensed in June of 1980, at which time his performance under the subject contract had ceased. To obtain this license after approximately eleven years of unlicensed status, he had to demon *735 strate his competence anew by taking an examination.

Defendant’s sole contention on appeal is that plaintiff’s failure to comply with the licensing requirements of U.C.A., 1953, § 58-23-1 precludes his right to recover for materials and services provided under the contract.

The general rule in this jurisdiction with respect to the status of unlicensed contractors has been stated thus:

If the purpose of licensing is to protect the public, then the general rule in this State is that the party who does not obtain a license, but is required to do so, cannot obtain relief to enforce the terms of his contract — including payment thereunder — even though there are other penalties imposed against him expressly by statute including criminal sanctions .... And there is no doubt that the purpose of the licensing statute relating to contractors, supra [Section 58-23-1], is protection of the public. [Emphasis added.] 2

This rule is not, however, applied unconditionally. This Court has held that unless it is shown that the party from whom the unlicensed contractor seeks to recover is within the class of persons whom the licensing statute is designed to protect, the rule will not be applied. 3 Thus, the pivotal issue in this case is whether defendant occupied a protected status.

Defendant contends that it was definitely within the protected class and that the general rule, supra, should therefore have been invoked by the trial court to relieve defendant of its obligation to plaintiff under the contract. Defendant points out that this Court has only refused to apply the general rule in two cases, Fillmore Products, Inc. v. Western States Paving, Inc., 4 and Lignell v. Berg, 5 and that the circumstances upon which the Court’s decision rested in those cases are clearly distinguishable from the instant matter.

It is of course plaintiff’s position that defendant was not within the class protected under the licensing statute, and thus, should not be afforded the benefits of the general rule. Plaintiff maintains that the two cases noted above (Fillmore Products and Lignell)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R4 Constructors v. Inbalance Yoga
2020 UT App 169 (Court of Appeals of Utah, 2020)
AGTC Inc. v. CoBon Energy LLC
2019 UT App 124 (Court of Appeals of Utah, 2019)
American Rural Cellular, Inc. v. Systems Communication Corp.
890 P.2d 1035 (Court of Appeals of Utah, 1995)
Govert Copier Painting v. Van Leeuwen
801 P.2d 163 (Court of Appeals of Utah, 1990)
Pacific Chromalox Division, Emerson Electric Co. v. Irey
787 P.2d 1319 (Court of Appeals of Utah, 1990)
Lindstrom v. District Board of Health Panhandle District I
712 P.2d 657 (Idaho Court of Appeals, 1985)
Loader v. Scott Construction Corp.
681 P.2d 1227 (Utah Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
672 P.2d 732, 1983 Utah LEXIS 1148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-v-oren-ltd-associates-utah-1983.