George R. Guscott v. City of Boston

958 F.2d 361, 1992 U.S. App. LEXIS 29998, 1992 WL 55889
CourtCourt of Appeals for the First Circuit
DecidedMarch 25, 1992
Docket91-1887
StatusUnpublished
Cited by2 cases

This text of 958 F.2d 361 (George R. Guscott v. City of Boston) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George R. Guscott v. City of Boston, 958 F.2d 361, 1992 U.S. App. LEXIS 29998, 1992 WL 55889 (1st Cir. 1992).

Opinion

958 F.2d 361

NOTICE: First Circuit Local Rule 36.2(b)6 states unpublished opinions may be cited only in related cases.
George R. GUSCOTT, ET AL., Plaintiffs, Appellants,
v.
CITY OF BOSTON, Defendant, Appellee.

No. 91-1887.

United States Court of Appeals,
First Circuit.

March 25, 1992

Laurie A. Kelly with whom Henry F. Owens, III, and Owens & Associates were on brief for appellants.

John R. Devereaux with whom Steven I. Venezia, Assistant Corporation Counsel, City of Boston Law Department, were on brief for appellee.

Before Torruella, Circuit Judge, Campbell and Bownes, Senior Circuit Judges.

CAMPBELL, Senior Circuit Judge.

George Guscott, Cecil Guscott and Kenneth Guscott a/k/a Long Bay Management Company (Long Bay) appeal from an order entered on July 17, 1991, by the United States District Court for the District of Massachusetts dismissing a complaint for breach of contract against the City of Boston. Finding no reversible error, we affirm.

I.

On August 29, 1982, Long Bay submitted a bid in response to a public advertisement by the United States Department of Housing and Urban Development (HUD) soliciting bids on a distressed housing development known as Brunswick Gardens, located in Boston, Massachusetts. Although only $6,000, Long Bay's bid was the highest bid submitted. Brunswick Gardens was advertised by HUD as consisting of five uncompleted structures on seven parcels making up approximately six acres of land. However, at the time, HUD owned only five of the seven parcels. The remaining two, comprising five of the six acres, had been acquired by the City of Boston (the City) by tax forfeiture, and title remained, as it apparently still does, with the City.

Prior to the solicitation of the bids, HUD and the City were engaged in negotiations between themselves aimed at assembling ("reconstituting") all parcels for public sale by HUD to some third party. For its part, the City sought reimbursement for back taxes outstanding on the properties; various resolutions of this problem were discussed. No formal agreement between HUD and the City was ever drawn; however, a HUD memo dated September 27, 1982, after the bidding, reported that the City had expressed its willingness to accept $7,565.84, or $1,565.84 more than Long Bay's bid of $6,000, as a minimum tax payment. See below. Long Bay, in fact, turned over to HUD a check for this amount. There is no evidence, however, that after receiving the sum, HUD turned it over to the City, or that the City itself ever declared itself satisfied and willing to deed the two parcels to HUD or any purchaser from HUD.

Several mystifying years then elapsed, during which, insofar as the record shows, both HUD and the City seem to have forgotten about the matter altogether. Finally, in 1988, Long Bay sued both HUD and the City in the Massachusetts Superior Court alleging breach of contract and seeking specific performance. Long Bay asked the court to order the City to immediately convey the City's two parcels to HUD and to order HUD, in turn, to convey them to Long Bay. HUD removed the action to the United States District Court pursuant to 28 U.S.C. §§ 1441-1442.

In the district court, Long Bay filed an amended complaint seeking the same remedy. Alternatively, Long Bay alleged that it was the intended third party beneficiary of a

purported contract between HUD and the City which the two parties had failed to carry out.

The City conceded that it had made a tentative agreement to transfer the parcels but asserted the agreement remained subject to unperformed conditions relative to payment and abatement of outstanding taxes. According to the City, it was uncontested that it was never paid the agreed upon back taxes. The City also asserted that the state's approval to abate the balance of taxes on the properties was never obtained.

A jury was finally impanelled on June 24, 1991. On that day, the City submitted a motion to dismiss or in the alternative for summary judgment. The district judge acknowledged that the motion was both sudden and late, but allowed it to be argued two days later in conjunction with proceedings at a pretrial conference held pursuant to Fed. R. Civ. P. 16.

On July 17, 1991, the district court ruled that Long Bay could not obtain specific performance against HUD. Jurisdiction to sue HUD is restricted to the Tucker Act, 28 U.S.C. § 1491(a)(1) and 1346(a)(2), which makes no provision for specific relief and, moreover, requires that damages relief be obtained in the United States Claims Court. On that same day, the district court upon motion of the United States and with the approval of Long Bay, ordered transfer of the action against HUD to the Claims Court pursuant to 28 U.S.C. § 163. At the same time, the district court allowed the City's motion for summary judgment against Long Bay and dismissed the complaint against the City.

Long Bay appeals from the district court's dismissal of the complaint against the City, arguing that summary judgment in favor of the City of Boston was improper because there remained genuine issues of material fact regarding plaintiffs' claim for specific relief against the City under the alleged contract between the City and HUD relative to the City's two parcels. Our review of the district court's grant of summary judgment is plenary. Frazier v. Bailey, No. 91-1477, slip op. at 2 (1st Cir. Feb. 24, 1992); Calvary Holdings, Inc. v. Chandler, 948 F.2d 59, 61 (1st Cir. 1991).

II.

Long Bay's principal theory for recovery against the City is that it was the third party beneficiary of a contract allegedly made between the City and HUD, under which the City had agreed to transfer the two parcels to HUD or its designated purchaser. It is uncontested that Long Bay was the high bidder, and it now contends that it should be able to enforce HUD's contract with the City directly against the latter, securing a conveyance that bypasses HUD and thus renders immaterial HUD's immunity and disappearance from the case.

Third party beneficiary theory holds that when one person enters into a valid contract with another to do some act for the benefit of a third party, that third party [who would enjoy the benefit of the act] may bring a suit for the breach of that contract.1 Long Bay cites § 309(3) of the Restatement (Second) of Contracts which provides that ... "the right of any beneficiary against the promisor is not subject to the promisor's claims or defenses against the promisee or to the promisee's claims or defenses against the beneficiary." Long Bay's reading of § 309 of the Restatement of Contracts is, however, incomplete. Sections 309(1) and (2) constitute exceptions to the broad sweep of § 309(3). These provisions read:

§ 309(1) A promise creates no duty to a beneficiary unless a contract is formed between the promisor and the promisee; and if the contract is voidable or unenforceable at the time of its formation the right of the beneficiary is subject to the infirmity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
958 F.2d 361, 1992 U.S. App. LEXIS 29998, 1992 WL 55889, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-r-guscott-v-city-of-boston-ca1-1992.