George P. Rose Sodding & Grading Co. v. Dennis

237 N.W.2d 418, 195 Neb. 221, 1976 Neb. LEXIS 898
CourtNebraska Supreme Court
DecidedJanuary 15, 1976
Docket40140
StatusPublished
Cited by30 cases

This text of 237 N.W.2d 418 (George P. Rose Sodding & Grading Co. v. Dennis) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George P. Rose Sodding & Grading Co. v. Dennis, 237 N.W.2d 418, 195 Neb. 221, 1976 Neb. LEXIS 898 (Neb. 1976).

Opinion

Van Pelt, District Judge.

This is an action brought by plaintiff-appellant, George P. Rose Sodding & Grading Company, against the defendants-appellees, based on an alleged oral contract for the grading and sodding of five lots located in Sarpy County, Nebraska. The District Court sustained the defendants’ demurrers and the plaintiff appeals. There having been no evidentiary trial, the case is before this court on the file and the pleadings.

The last item of labor or material was performed and furnished by the plaintiff pursuant to the oral contract on September 5, 1969. Plaintiff’s original petition and praecipe was filed September 5, 1973. On September 6, 1973, the clerk of the District Court issued summonses for all defendants. Summonses issued for defendants Floyd E. Peterson, Vincent E. Peterson, Robert Kouba, and Sanitary Improvement District No. 43 of Sarpy County, Nebraska, were served on September 7, 1973. Summons issued for the defendant Land Paving Company was served on September 10, 1973. Summonses issued for defendants Dennis and Fontenelle Hills Co., Inc., were not properly served, and their special appearances *223 were subsequently sustained. Alias summonses for those two defendants were issued November 9, 1973.

On September 14, 1973, Land Paving Company demurred. On October 30, 1973, the defendants Floyd E. Peterson, Vincent E. Peter son, and Robert Kouba demurred. On December 7, 1973, the demurrers of Peter-sons, Kouba, and Land Paving Company were sustained, and the plaintiff was given 3 weeks additional time in which to plead. On December 11, 1973, the defendant Dennis filed a demurrer, which was sustained on December 28, 1973, with the plaintiff being given 3 weeks in which to further plead.

On January 16, 1974, the plaintiff filed an amended petition against all defendants. After the overruling of defendants’ motions to strike on December 30, 1974, all defendants, except Land Paving Company, filed a demurrer on January 29, 1975. On February 3, 1975, Land Paving Company filed its demurrer. On February 28, 1975, the District Court sustained all demurrers and dismissed plaintiff’s amended petition. On March 10, 1975, the plaintiff filed a motion for new trial, which was overruled on April 3, 1975.

The plaintiff’s assignment that the District Court erred in sustaining each demurrer and dismissing plaintiff’s amended petition, is based upon the following contentions: (1) The demurrers did not specifically state that the petition shows on its face that the action is barred by the statute of limitations, and a general allegation that the petition does not state facts sufficient to constitute a cause of action does not raise the defense of the statute of limitations; (2) the statute of limitations had been tolled by virtue of the fact that defendants, through fraud and deceit, had induced the plaintiff to refrain from commencing the suit and had lulled him into a false sense of security within the period of the statute of limitations; and (3) because of the fraud previously mentioned, the statute of limitations does not begin to run until the fraud or deceit either was' or *224 reasonably should have been discovered.

Respecting defendants Floyd E. Peterson, Vincent E. Peterson, and Robert Kouba, there is no allegation in the amended petition that they entered into any contract with the plaintiff, orally or in writing. Such an allegation would have been essential, and their demurrer would be good for that reason, even if the demurrers of the other defendants were improper vehicles for raising the defense of the statute of limitations.

Plaintiff’s contention regarding the use of a demurrer to raise the statute of limitations was answered in Schmer v. Gilleland, 185 Neb. 54, 173 N. W. 2d 391, wherein it was held that where a record discloses that an action was not commenced within the time allowed by statute, the petition is subject to demurrer. See, also, Reliance Trust Co. v. Atherton, 67 Neb. 305, 93 N. W. 150; Gorgen v. County of Nemaha, 174 Neb. 588, 118 N. W. 2d 758. Although a specific statement in the demurrer that the petition is barred by the statute of limitations would have been more appropriate, the customary and general allegation that the petition does not state facts sufficient to constitute a cause of action is adequate to raise the defense of the statute of limitations by demurrer. This is true since once the petition alleges facts showing a bar by the statute of limitations, additional facts must be alleged by the plaintiff to show the tolling of the statute, or some other basis for avoiding its effect. If plaintiff fails to allege such facts, as it failed to do in its amended petition, it has, in effect, failed to allege facts sufficient to constitute a cause of action, and the petition is therefore subject to demurrer.

Section 25-206, R. R. S. 1943, provides that an action on a contract, not in writing, expressed or implied, can only be brought within 4 years. Section 25-217, R. R. S. 1943, provides that an action shall be deemed commenced within the meaning of Chapter 25, as to the defendant, at the date of the summons which is served upon him. This has been construed in Schmer v. Gille *225 land, supra, to mean that the action is commenced on the date of the summons, which is properly served upon the defendant. Thus, in the present case, the action was commenced against Sanitary Improvement District No. 43, Floyd E. Peterson, Vincent E. Peterson, Robert Kouba, and Land Paving Company on September 6, 1973, and against Joseph Dennis and Fontenelle Hills Co., Inc., on November 9, 1973.

A cause of action upon an oral contract for work performed accrues, and the statute of limitations begins to run, when the aggrieved party has the right to institute and maintain a lawsuit. Whenever one person may sue another, the cause of action has accrued and the statute begins to run. Bend v. Marsh, 145 Neb. 780, 18 N. W. 2d 106; Weiss v. Weiss, 179 Neb. 714, 140 N. W. 2d 15.

In the instant case the oral contract was for sodding and grading work to be performed. According to the amended petition, the contract was silent as to the time of performance or the time of payment. In such a case the statute would run when the work was performed, which was September 5, 1969. See 17 Am. Jur. 2d, Contracts, § 338, p. 776. Thus, the statute commenced running on said date. In computing the 4-year term pursuant to section 25-2221, R. S. Supp., 1974, by excluding the date of the act after which the period begins to run, and including the last day of the period, the last day of the 4-year period of limitations would be September 5, 1973. Since summonses against all defendants were not properly served until after that date, the causes of action are barred, unless the plaintiff has shown the tolling of the statute.

The plaintiff does not claim that the statute was tolled by any of the statutory grounds set forth in section 25-216, R. R. S. 1943, but relies instead on certain common law equitable' doctrines. In paragraphs five, six, and seven of the amended petition, the plaintiff alleges that it submitted bills for partial payment to *226

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fuelberth v. Heartland Heating & Air Conditioning
307 Neb. 1002 (Nebraska Supreme Court, 2020)
MOTOR CLUD INS. ASS'N v. Fillman
568 N.W.2d 259 (Nebraska Court of Appeals, 1997)
State v. Hirsch
511 N.W.2d 69 (Nebraska Supreme Court, 1994)
St. Paul Fire & Marine Insurance v. Touche Ross & Co.
507 N.W.2d 275 (Nebraska Supreme Court, 1993)
DeSciose v. Chiles, Heider & Co., Inc.
476 N.W.2d 200 (Nebraska Supreme Court, 1991)
Ames v. Hehner
435 N.W.2d 869 (Nebraska Supreme Court, 1989)
Sanitary & Improvement District No. 145 v. Nye
343 N.W.2d 753 (Nebraska Supreme Court, 1984)
Jones v. Johnson
300 N.W.2d 816 (Nebraska Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
237 N.W.2d 418, 195 Neb. 221, 1976 Neb. LEXIS 898, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-p-rose-sodding-grading-co-v-dennis-neb-1976.