George F. Robertson Plastering Company v. Magidson

271 S.W.2d 538, 1954 Mo. LEXIS 768
CourtSupreme Court of Missouri
DecidedSeptember 13, 1954
Docket43775
StatusPublished
Cited by15 cases

This text of 271 S.W.2d 538 (George F. Robertson Plastering Company v. Magidson) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George F. Robertson Plastering Company v. Magidson, 271 S.W.2d 538, 1954 Mo. LEXIS 768 (Mo. 1954).

Opinion

HYDE, Presiding Judge.

This is an equitable mechanics, lien suit in which plaintiff seeks a lien for $10,003.-20, the amount claimed to be due for lath and plaster work on an apartment building in St. Louis. The trial court entered judgment for plaintiff for this amount and defendants have appealed.

Defendant, Oakland Realty Company, was the owner of the property and defendant Magidson was the general contractor. He also had an interest in the Realty Company and will hereinafter be referred to as defendant. On November 4, 1947, the following proposal was made by plaintiff and accepted by defendant: “We propose to lurnish labor and material for the lathing and plastering according to plans and specifications on the above mentioned building for the sum of $24,867.00. The above price is the guaranteed contract. Work to be done on cost plus 10% Overhead and 10% Profit. Any saving shall be deducted from above contract.” Plaintiff contends that after the work commenced, in December 1947, this contract was abandoned by agreement of the parties and it was agreed that the lath and plaster work should be done on a time and material basis, that is on the cost plus basis stated in the contract.

Thus the principal issue for determination is whether plaintiff is limited to the contract price or can recover the full amount he claims, for labor and material used, on the cost plus basis. On this issue, the trial court found in its decree: “This proposal, the Court finds, was abandoned by the parties thereto and the plaintiff furnished and installed its materials, both lathing and plastering, and furnished the labor to install same, on a quantum meruit basis.” The court entered judgment on this basis for the full amount claimed.

Defendant contends this finding is not supported by substantial evidence, that this Court should find to the contrary and that this finding was outside the issues made by the pleadings. As to this latter contention, defendant says abandonment of the contract was not pleaded by plaintiff either in its petition nor in its reply. However, plaintiff’s petition was on quantum meruit and the contract was set up in defendant’s answer as a defense. A reply to an answer is not now a required pleading unless ordered by the court. (Sections 509.010 and 509.400, statutory references are to RSMo and V.A.M.S.) Furthermore, the issue of whether the original contract applied or whether there was an abandonment of it was fully tried by the parties. See Pleiman v. Belew, 360 Mo. 219, 227 S.W.2d 733. We hold that this issue was properly before the trial court for its decision.

Plaintiff’s evidence was that the plans for the building provided for masonry partition walls, gypsum, concrete block or tile. Defendant wanted to figure on changing these partitions to two inch solid metal lath and plaster. Plaintiff’s president, George F. Robertson, said defendant came to his office with two sheets of floor plans. He made the *540 written proposal of November 4, 1947 on the basis of what those plans showed but said that when the work started he found that the plans actually used for the building were different from -those from which he figured the proposal for lathing and plastering. He said he never again saw the plans from which he'figured the contract -price. (Defendant denied he showed Robertson any different plans.) The first lath.work was begun December 8, 1947. Plaintiff had an agreement with the George Stroup Lathing Company to do the lathing at an agreed price. Robertson said that three or four days after the lathers started Jack Stroup called him to come out and he met there with defendant and George and Jack Stroup. He said the Stroups found that the concrete -columns were out of plumb and the ■beams in the corridors out of level which required them to build false work around them with metal lath, called furring, to make it look the same across the whole wall of the apartment; that partitions had been laid out on the floors differently from the way they were required to build them; that access panels (for deliveries into apartments) had to be set in the metal partitions; that steel door frames (called door bucks) had to be turned around and reset (because of radiators and other obstructions which made it necessary to have the door swing the other way) ) and that this later required them to take down lath and re-lath around them. Robertson testified that, in the presence of defendant, George Stroup said: “We cannot do that kind of work, when we figured two-inch solid partitions throughout this job, at that cost.” Robertson then said he told defendant: “This work is going to cause a lot of labor, and we are just at the start of the job, and if we are going to keep time on each individual change, why, it is going to have you have a foreman -here at al'l times to sign the different orders”; and that defendant then said: “George, you have been doing my work for the last two years. You are fair, you are the fairest man I ever dealt with. You go ahead and do the job on a time and material basis.” He was corroborated by the two Stroups that defendant said to do the work on a time and material basis and there were also other plaintiff’s witnesses who testified to later statements by defendant that plaintiff was doing the work on that basis. Robertson said that, after this agreement, he told the lathers to go ahead and do everything defendant told them to do. Plaintiff’s evidence was that they even set the access panels and changed the door -bucks- themselves without waiting for defendant’s carpenters to do it. George Stroup said: “Well, we figured we were working now on a time and material basis; it didn’t make any difference-what we done, whether we helped his carpenters or his carpenters helped us. We worked together on the job. We had no-dissension with anyone.” Plaintiff’s evidence also showed that defendant late.changed the plastering specifications as to-ceilings and to use plaster instead of tile in. the -bathrooms.

As to the conditions encountered, Jack Stroup said: “We try to build our work plumb so it can receive a normal coat of plaster. Well, I walked into the building and as I was walking through the building I paid particular attention to the work that affects our work. They had steel columns in there laying as much as four inches out of plumb. That is no exaggeration at all;, it is the truth. And then the other trades, especially the electrician, he wasn’t coordinated to do our work, and I protested about it, because he couldn’t keep out of the way of the lathers. * * * The carpenter proceeded to set the door bucks out there and he had a lot of -bucks swinging the wrong way. He had even some of the doors-swinging into the closet instead of on the-outside of it. It necessitated our tearing the-lath off and turning around the bucks, making them more secure so the plasterer could plaster them.” George Stroup said: “We found that due to the change in construction that we -couldn’t lay out the work according, to the drawings. It was- a physical impossibility. * * * Where the other mechanical trades would rough in their work, according to the dimensions, our work would not fit it, and we would have to move-partitions, oh, an inch or two inches or three inches, a varied amount. * * *' We ran into several obstacles where we 'had *541 to change our partitions, and not being able to make the layout.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pecos I, LLC v. Jason S. Meyer
Missouri Court of Appeals, 2022
Jennings v. Chatsworth Apartments Project Ltd.
186 S.W.3d 457 (Missouri Court of Appeals, 2006)
Warrenton Campus Shopping Center, Inc. v. Adolphus
787 S.W.2d 852 (Missouri Court of Appeals, 1990)
Dyer-Bussey Realtors, Inc. v. Wright
647 S.W.2d 215 (Missouri Court of Appeals, 1983)
Austin v. Kansas City General Hospital & Medical Center
570 S.W.2d 752 (Missouri Court of Appeals, 1978)
Romine v. Rex Darnall, Inc.
541 S.W.2d 50 (Missouri Court of Appeals, 1976)
Chandler v. Rosewin Coats, Inc.
515 S.W.2d 184 (Missouri Court of Appeals, 1974)
Gee v. Nieberg
501 S.W.2d 542 (Missouri Court of Appeals, 1973)
Dietrich v. Dietrich
498 S.W.2d 611 (Missouri Court of Appeals, 1973)
HTC CORPORATION v. Olds
486 P.2d 463 (Colorado Court of Appeals, 1971)
Boland v. Dehn
348 S.W.2d 603 (Missouri Court of Appeals, 1961)
Schwartz v. Shelby Construction Company
338 S.W.2d 781 (Supreme Court of Missouri, 1960)
Hartlage ex rel. Hartlage v. Halloran
331 S.W.2d 197 (Missouri Court of Appeals, 1960)
Hillhouse v. City of Aurora
316 S.W.2d 883 (Missouri Court of Appeals, 1958)
Smyth v. City of St. Joseph
297 S.W.2d 578 (Missouri Court of Appeals, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
271 S.W.2d 538, 1954 Mo. LEXIS 768, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-f-robertson-plastering-company-v-magidson-mo-1954.