George Cassidy Sons Co. v. State

24 Ill. Ct. Cl. 419, 1963 Ill. Ct. Cl. LEXIS 44
Court of Claims of Illinois·Decided December 20, 1963·No. No. 4868·Published

Opinion

Dove, J.

On April 27, 1959, George Cassidy Sons Company, An Illinois Corporation, filed a complaint seeking an award in the amount of $218,690.58 for damages, extra labor, and material costs incurred in the construction of a new dietary facility at the Kankakee State Hospital.

The complaint recites that the company was awarded contract No. 69662 on June 17, 1957, and that it immediately began construction according to the plans and specifications, which, among other things, provided that the work was to be completed in one year.

Before reciting the difficulties, which occurred on the job, two sections of the specifications should be set forth:

ARTICLE 22
The owner, without invalidating the contract, may make changes by altering, adding to, or deducting from the work, the contract sum being adjusted accordingly. All such work shall be executed under the conditions of the original contract, except that any claim for extension of time caused thereby shall be adjusted at the time of ordering such change.
No change shall be made, unless in pursuance of a written order from the Supervising Architect, stating that the owner has authorized the change, and no claim for an addition to the contract sum shall be valid unless so ordered.
The value of any such change shall be determined in one or more of the following ways:
(a) By estimate and acceptance in a lump sum.
(b) By unit prices, named in the contract, or subsequently agreed on.
ARTICLE 64
The General Contractor shall provide his own fuel, apparatus and heat as necessary for the thawing or heating of frozen ground and material, and, in the case of the latter, sufficient heat shall be maintained until material incorporated in construction has taken final set, and all danger of damage by frost is past. This shall in no case conflict with requirements of protection in Masonry Specifications.
Where available, all necessary steam for properly heating the building, or buildings, under construction will be furnished to the General Contractor at no cost, but the contractor shall pay for, and make all necessary arrangements with the Heating Contractor for all connections to and from the nearest available heating main and returns, and also for the furnishing and connecting of all temporary heating units sufficient to maintain an even temperature of at least 60 degrees in the building, or buildings, under construction. Heating period shall be as follows: Approximately October 1st to May 30th unless conditions warrant otherwise, then the final decision shall be made by the Supervising Architect’s representative in the field.

The plans for this facility were prepared by Samuel A. Lichtmann, associate architect. Shortly after the commencement of the work, claimant noticed certain discrepancies in the plans and drawings. Claimant asked for information regarding’ a retaining wall, and the alternative bid to construct it, also specifications for slabs, column footings, floor gratings, extent of attic floor, foundation pilaster, glazed tile, and ceiling heights for the kitchen and dining room.

Soil borings were furnished, by the State, which proved to be inaccurate, as the water table was higher than reported. As a result, the building was raised six inches, and claimant was directed to make the change. The work was delayed, because of differences of opinion with the associate architect as to the necessity of a retaining wall to keep out the water. Thereafter, the associate architect changed his mind, and ordered the retaining wall.

A series of delays thereafter occurred involving steel sash operations, reinforcing steel, color of tile and fabrication of aluminum entrances. The Division of Architecture finally directed claimant to disregard the selection by the associate architect, and it made the selection.

A dispute developed between the Division of Architecture and the associate architect as to the coursing of the masonry, and it was necessary for claimant to run his masonry out of line. As a result, the labor costs were greatly increased.

Final approval of the shop drawings for structural steel were not received until 4% months after the job was started. During this time claimant had large crews of skilled laborers on hand, and he was obliged to pay “show-up” time in order to keep the men available.

In constructing the building according to the plans and specifications, there was a variance in roof heights, with no provision for closure between the two elevations. This prevented claimant from enclosing the building, so that it could use heat furnished by the State, as provided by Art. 64. As a result, claimant was obliged to furnish heaters and fuel oil to protect the then completed work.

Other prime contracts, which were an integral part of the contract, were not immediately awarded, nor correlated with claimant’s work. It further appears that the plans furnished such contractors were inadequate, or changed so, that, as a result, their inability to do the work caused additional delays to claimant.

Finally, claimant contends that he contracted to build the building in 365 days (June 17, 1957 to June, 1958), but, because of incomplete plans, disagreements between the Division of Architecture and Engineering and the associate architect, and changes of plans, he was delayed until March 31, 1959, a delay of 287 days.

Claimant is asking reimbursement from July 1, 1958 to December 31, 1958, and is not making claim for the period of January 2, 1959 to March 31, 1959.

Respondent’s exhibit No. 1 is a copy of the Departmental Report, dated May 7, 1959. It recites in substance :

“1. During the progress of the work, revisions, corrections, alterations, and additional work were necessary to properly complete the project.
2. Claimant’s complaint about lack of correlation with other prime contractors is true, and their delays delayed the claimant.
3. Inadequacies were found in the plans and specifications.
4. Claimant was ordered to make changes, and to delay work pending decisions on other matters.
5. Department is unable to check the figures quoted in claim, since day costs are not part of its duty. Therefore, it is impossible to estimate cost of additional compensation.
6. The Division of Architecture and Engineering has checked the estimated completion time, and has found that, under normal conditions, this project could have been completed within the allotted time.”

Exhibit No. 3 is claimant’s break-down of increased costs, and is the basis of the claim.

INCREASED COSTS

Superintendent ____ 6,500.00

Rental Equipment Compressor __________ .$ 1,950.00

End Loader _________ . 6,825.00

Free access — add to your briefcase to read the full text and ask questions with AI

George Cassidy Sons Co. v. State, 24 Ill. Ct. Cl. 419, 1963 Ill. Ct. Cl. LEXIS 44 (Ill. Super. Ct. 1963).

24 Ill. Ct. Cl. 419 (George Cassidy Sons Co. v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Fergus v. Brady
115 N.E. 393 (Illinois Supreme Court, 1917)