George Campbell Painting Corp. v. State, No. Cv 95-0470648s (May 3, 1996)

1996 Conn. Super. Ct. 4109-LL, 17 Conn. L. Rptr. 145
CourtConnecticut Superior Court
DecidedMay 3, 1996
DocketNo. CV 95-0470648S
StatusUnpublished

This text of 1996 Conn. Super. Ct. 4109-LL (George Campbell Painting Corp. v. State, No. Cv 95-0470648s (May 3, 1996)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Campbell Painting Corp. v. State, No. Cv 95-0470648s (May 3, 1996), 1996 Conn. Super. Ct. 4109-LL, 17 Conn. L. Rptr. 145 (Colo. Ct. App. 1996).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION ON MOTION TO DISMISS (No. 104) A. FACTS:

The plaintiff, George Campbell Painting Corporation, entered into several contracts ("Contracts") with the defendant, State of Connecticut1, for the extensive rehabilitation and painting of several bridges. The Contracts specified dates that the work was to be completed. The plaintiff alleges that while sandblasting bridges under the contract, the plaintiff discovered a "blue colored substance (the "Substance") between the coating and the steel substrate." The plaintiff further alleges the Substance was a "metal resin acid compound which physically etched the surface and created a chemical bond with the substrate, and that the Substance must be substantially removed in order to perform the painting required under the Contracts." The plaintiff alleges it immediately notified the defendant of the Substance and that it was relying on Article 1.04.04 of the Department of Transportation's Standard Specifications for roads, Bridges and Incidental Construction Form 814 and Supplemental Specifications to Standard Specifications, July 1992. This suit was commenced as a result of the defendant's alleged failure to agree to an extension of the completion dates and payment of the additional costs incurred.

B. DISCUSSION:

"[A] motion to dismiss is the proper vehicle to attack the jurisdiction of the court. A motion to dismiss essentially asserts that, as a matter of law and fact, the plaintiff cannot state a cause of action that is properly before the court." Third Taxing District v. Lyons, 35 Conn. App. 795, CT Page 4109-MM 803, 647 A.2d 32 (1994). "The doctrine of sovereign immunity implicates subject matter jurisdiction and is therefore a basis for granting a motion to dismiss." Antinerella v. Rioux,229 Conn. 479, 489, 642 A.2d 699 (1994).

The defendant alleges that § 4-61's limited waiver of sovereign immunity does not apply to the plaintiff's second, third, fifth, sixth, seventh and eighth counts. The defendant alleges the second count alleges a tort cause of action; the third count appears to request the court to grant an extension of time for contract performance; the fifth count alleges misrepresentation arising out of the awarding of the contract; the sixth count negligent misrepresentation arising out of the awarding of the contract; the seventh count seeks a declaratory judgment, excusing performance; and the eighth count seeks an injunction and declaratory judgment for the anticipatory breach. Lastly, the defendant alleges the plaintiff has failed to adequately plead the "stringent criteria which would permit an action for injunction."

The defendants motion can be broken down into two categories, (1) tort causes of action, and (2) injunctive and declaratory causes of action. Each category will be discussed in seriatim below.

The general rule regarding sovereign immunity is "the state cannot be sued without its consent." Sentner v. Board ofTrustees, 184 Conn. 339, 342, 439 A.2d 1033 (1981); Horton v.Meskill, 172 Conn. 615, 623, 376 A.2d 359 (1977). However exception by statute and case law exists. Doe v. Heintz,204 Conn. 17, 31, 526 A.2d 1318 (1987). The focus of this case involves § 4-61's exception to sovereign immunity.

1. Tort Causes of Action:

The second count alleges a tort cause of action for the defendant's "outrageous and unconscionable actions, and appears to be seeking punitive damages". The fifth count alleges misrepresentation arising out of the awarding of the contract. The sixth count alleges negligent misrepresentation arising out of the awarding of the contract. These three counts all allege tortious causes of action, but the fundamental nature of the claims are based on the alleged breach of contract by the defendant.

The plaintiff's cause of action is pursuant to § CT Page 4109-NN4-61. The defendant alleges that § 4-61 waives sovereign immunity only for contract actions. § 4-61 states in relevant part,

(a) Any person, firm or corporation which has entered into a contract with the state . . . for the design, construction, construction management, repair or alteration of any highway, bridge . . . may, in the event of any disputed claims under such contract or claims arising out of the awarding of a contract by the commissioner of public works, bring an action against the state to the superior court for the judicial district of Hartford-New Britain for the purpose of having such claims determined . . .

The defendant relies on Ernest Jarvis Co. v. Stateof Connecticut, Department of Transportation, Superior Court, judicial district of Hartford/New Britain at Hartford, Docket No. 297219 (October 31, 1988) (O'Connor, J.), for the proposition that § 4-61 waives the States' sovereign immunity only for breach of contract causes of action, not tort causes of action.

In Duguay v. Hopkins, 191 Conn. 222, 232, 464 A.2d 45 (1983), the court addressed sovereign immunity with the following words: "When the state waives sovereign immunity by statute, however, a party who wishes to sue under the legislative waiver must come clearly within its provisions because `[statutes in derogation of sovereignty should be strictly construed in favor of the state, so that its sovereignty may be upheld and not narrowed or destroyed.]'"

However, the plaintiff relies on Leone ConstructionCo., Inc. v. State, Superior Court, judicial district of Hartford/New Britain, Docket No. 377799 (January 31, 1992) (Walsh, John, J., 6 Conn. L. Prtr. 26, 7 CSCR 297). This case is more recent then Ernest Jarvis Co. and the issue raised is identical to the instant case. In Leone, Judge Walsh specifically revisited ErnestJarvis Co. then concluded:

This court has adopted the view that the modern tendency is to make the fundamental nature of the obligation the test as to whether the action is founded upon either tort or contract. Kaplan v. Merberg Wrecking Corporation, 152 Conn. 405, 410 207 A.2d 732

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horton v. Meskill
376 A.2d 359 (Supreme Court of Connecticut, 1977)
Duguay v. Hopkins
464 A.2d 45 (Supreme Court of Connecticut, 1983)
Sentner v. Board of Trustees of Regional Community Colleges
439 A.2d 1033 (Supreme Court of Connecticut, 1981)
Kaplan v. Merberg Wrecking Corporation
207 A.2d 732 (Supreme Court of Connecticut, 1965)
Saturn Construction Co., Inc. v. State, No. Cv94 0705198 S (Sep. 7, 1995)
1995 Conn. Super. Ct. 10301 (Connecticut Superior Court, 1995)
Doe v. Heintz
526 A.2d 1318 (Supreme Court of Connecticut, 1987)
Krozser v. City of New Haven
562 A.2d 1080 (Supreme Court of Connecticut, 1989)
Antinerella v. Rioux
642 A.2d 699 (Supreme Court of Connecticut, 1994)
Third Taxing District v. Lyons
647 A.2d 32 (Connecticut Appellate Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
1996 Conn. Super. Ct. 4109-LL, 17 Conn. L. Rptr. 145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-campbell-painting-corp-v-state-no-cv-95-0470648s-may-3-1996-connsuperct-1996.