George A. Koteen Associates, Inc. v. Fulton Cotton Mills, Inc.

307 F. Supp. 1396, 1970 U.S. Dist. LEXIS 13186
CourtDistrict Court, S.D. New York
DecidedJanuary 16, 1970
DocketNo. 65 Civ. 2054
StatusPublished

This text of 307 F. Supp. 1396 (George A. Koteen Associates, Inc. v. Fulton Cotton Mills, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George A. Koteen Associates, Inc. v. Fulton Cotton Mills, Inc., 307 F. Supp. 1396, 1970 U.S. Dist. LEXIS 13186 (S.D.N.Y. 1970).

Opinion

OPINION, FINDINGS OF FACT and CONCLUSIONS OF LAW

LEVET, District Judge.

The above-entitled action by George A. Koteen Associates, Inc. (“Koteen”) against Fulton Industries Inc., sued herein as Fulton Cotton Mills, Inc. (“Fulton”), for alleged breach of a utility consultant contract was tried before me without a jury on October 16, 1969.

The action was instituted in the Supreme Court of the State of New York, County of New York, and removed to this court upon petition of the defendant.

[1397]*1397The parties have stipulated that, if liability is determined to exist, the amount of damages would be $13,497.43.

Plaintiff, Koteen, is a New Jersey corporation. Defendant, Fulton, is a Georgia corporation. Judge Bryan of this court, in an opinion and order dated June 28, 1967, sustained venue in the Southern District of New York.

After hearing the testimony of the parties, and examining the pleadings, the exhibits and the Proposed Findings of Fact and Conclusions of Law submitted by counsel, I make the following Findings of Fact and Conclusions of Law:

FINDINGS OF FACT

1. At all times hereinafter mentioned, Koteen was engaged in utility rate consultation; and Fulton was engaged in textile manufacturing in Atlanta, Georgia.

2. On October 25, 1960, the defendant signed plaintiff’s standard form of agreement in Georgia, which form was subsequently accepted by plaintiff in New Jersey (see Ex. 1). The contract was prepared by Koteen (SM 117-118). Under the agreement plaintiff was employed as defendant’s “utility rate consultant” for a three-year period.

The service rendered by plaintiff to defendant was to include, among other things, the following:

“RATES AND CONTRACTS: Make a thorough analysis of our rates and contracts under which our electric, gas, water, and steam services are being purchased to determine if we are receiving the most favorable rate schedules available. Also advise how we may take full advantage of all provisions, clauses, and special riders in force.
“AUDIT: Audit our past utility bills which have been paid by us, for a period not to exceed one year. When an audit of prior bills in any specific case is warranted, you will audit those prior bills, going as far back as may be necessary. You will also audit our future bills during the life of this agreement.
« * * *
“APPROVAL AND REPRESENTATION : It is understood that we have the right to approve any recommendations, and that all negotiations are to be handled through us unless we instruct you otherwise.” (Ex. 1)

The provision for payment to plaintiff was as follows:

“WE PAY YOU NO RETAINER OR ADVANCE FEES OF ANY KIND. We do agree to pay you 50% of all rate reductions which are secured through your efforts, for a period of forty-eight (48) months from the date each reduction actually appears on our bills. We also agree to pay you 50% of any refunds secured through your direction and efforts.
“IF NO RATE REDUCTIONS OR REFUNDS ARE SECURED, YOUR SERVICES COST US NOTHING.” (Ex. 1)

3. During the period between December 1960 and November 1961, plaintiff recommended that defendant eliminate or reduce its need for its higher cost “firm” 1 gas supply by installing “suitable” facilities to enable it to utilize substitute fuels during periods when its lower cost “interruptible”2 gas supply might be curtailed (see Pl.Exs. 3, 4, 9, 13; SM 16-19, 70-74, 98-106).3

[1398]*13984. The second proposal, according to Koteen, was “to violate the curtailment and pay the penalty which was being applied” (SM 71). Koteen added that “the rate schedule itself permits a violation of [the] curtailment [provisions of the ‘firm’ gas contract] and provides a penalty clause” (SM 76). As stated by Clarence E. Elsas, president of Fulton between January 1, 1960 and January 1, 1968, the essence of the proposal was that Fulton reduce its “firm” gas commitment and possibly subject itself to penalties which could be imposed by Atlanta if Fulton’s use of “firm” gas were to exceed the commitment (SM 144, 159-160).

5. Defendant, however, did not approve either of these recommendations,4 and neither installed substitute facilities nor risked penalties by violating the “firm” gas curtailment provision. On the contrary, Fulton made a new arrangement with Atlanta, whereby the “firm” gas requirement was reduced to 1500 therms per day with an option to restore the previous minimum of 3000 without any penalty as such; instead, Fulton would make payment at the “firm” rate for any “firm” gas used above the amount of 1500 therms per day. This arrangement became effective in October 1962, with the specific provision that if Fulton found it necessary to go back to 3000 therms per day minimum, Atlanta would amend the contract accordingly without penalty except for the extra gas usage before revision of the contract. After such revision, Elsas said that Fulton was to pay “firm” therm rate on any gas used above the 1500 therms but without further penalties (testimony of Elsas, SM 136, 171-172).

6. The rate, that is, the cost per unit for both “firm” and “interruptible” gas, was not reduced at any time during the period in question5 (see PI. Exs. 23, 24, SM 78). Thus, savings were due solely to a change in operation, not to a reduction in rates. There is no provision in the contract providing for payment to plaintiff in the event of a change in operation by the defendant.

7. The plaintiff has failed to prove by a fair preponderance of the credible evidence that the contract in question provided for payment to plaintiff if defendant achieved savings by a reduction of the “firm” gas commitment rather than by any rate reduction.

DISCUSSION

I.

The facts warrant the conclusion that the plaintiff rendered no serv[1399]*1399ices which resulted in a rate reduction. The language of the contract is unambiguous and no rate reductions were secured within the meaning of its terms.

It is elementary that where the terms of a contract are unambiguous their construction is for the court as a matter of law. National Utility Service, Inc. v. Whirlpool Corp., 325 F.2d 779 (2nd Cir. 1963).

The terms “rates” and “rate reductions” are unambiguous as used in this contract.

In the Random House Dictionary of the English Language (unabridged edition), at page 1192, “rate” is defined as follows:

“1. The amount of a charge or payment with reference to some basis of calculation; a rate of interest on loans.
“2. A certain quantity or amount of one thing considered in relation to another thing and used as a standard or measure; at the rate of 60 miles an hour.
“3. A fixed charge per unit of quantity; a rate of 10 cents a pound.”

A similar definition is found in Webster’s New World Dictionary, College Edition (1964):

“rate, n. [ME., OFr.; L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mutual Life Insurance v. Hurni Packing Co.
263 U.S. 167 (Supreme Court, 1923)
Alcoa Steamship Co. v. United States
338 U.S. 421 (Supreme Court, 1949)
KEY LIFE INSURANCE CO. v. Hodges
128 S.E.2d 367 (Court of Appeals of Georgia, 1962)
Paley v. Barton Savings and Loan Assn.
196 A.2d 682 (New Jersey Superior Court App Division, 1964)
City of Detroit v. Michigan Public Utilities Commission
286 N.W. 368 (Michigan Supreme Court, 1939)
Rentways, Inc. v. O'Neill Milk & Cream Co.
126 N.E.2d 271 (New York Court of Appeals, 1955)
National Utility Service, Inc. v. Thatcher Glass Manufacturing Co.
30 A.D.2d 168 (Appellate Division of the Supreme Court of New York, 1968)
Lenawee County Gas & Electric Co. v. City of Adrian
176 N.W. 590 (Michigan Supreme Court, 1920)
Pollock v. Ohio-Apex, Inc.
136 F. Supp. 712 (S.D. West Virginia, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
307 F. Supp. 1396, 1970 U.S. Dist. LEXIS 13186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-a-koteen-associates-inc-v-fulton-cotton-mills-inc-nysd-1970.