Genovesia v. Pelham Operating Co.

130 A.D. 200, 114 N.Y.S. 646, 1909 N.Y. App. Div. LEXIS 169
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJanuary 22, 1909
StatusPublished
Cited by4 cases

This text of 130 A.D. 200 (Genovesia v. Pelham Operating Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Genovesia v. Pelham Operating Co., 130 A.D. 200, 114 N.Y.S. 646, 1909 N.Y. App. Div. LEXIS 169 (N.Y. Ct. App. 1909).

Opinion

Ingraham, J. :

The plaintiff’s intestate was in the employ of the defendant George Yassar’s Son & Co., who was engaged in constructing a building in the city of New York, and while thus employed he sustained injuries which resulted in his death. His administratrix served notice on George. Yassar’s Son & Go. under the Employers’ Liability Act (Laws of 1902, chap. 600) stating that the deceased was caused and permitted to fall from an open, unguarded and unprotected elevator through an open, unguarded and unprotected elevator shaft, hoist' or hatchway, caused by the elevator or hoist being started While the deceased was removing a pillar therefrom. No notice seems to have been served upon the Pelham Operating Company. The plaintiff subsequently commenced an action against both defendants, alleging that the accident which resulted in the death of the decedent was caused by the concurring negligence of the defendants, and after a trial there resulted a verdict against both defendants upon which judgment was entered and from which each of the defendants separately appeal.

On the trial it appeared that the defendants, the Yassar Company, who were the employers of the decedent, were the contractors for the mason work for a building and at the time of the accident were constructing the walls which had reached the ninth floor. To carry the building materials from the ground to the several floors at which'it was needed the defendant the Pelham Operating Company had, under a contract with the Yassar Company, installed elevators in the building which were under the charge of one of the Pelhatn Company’s engineers. There were two elevators running side by side through an opening left for that purpose, the cars taking up the whole of the opening with the exception of a space of about a foot between the two elevators. Under the contract the time of this engineer was kept by the employees of the Yassar Company which was turned over to the Pelham Company, and the Pelham Company paid the engineer for the time that he was at work as appeared from these reports, and subsequently under the contract, that money was paid to the Pelham Company by the Yassar Company. At the time of the accident but one of these elevators was in operation. These elevators consisted of open platforms upon which were placed wheelbarrows filled with material [202]*202to be hoisted up, there being room for two wheelbarrows upon each elevator platform. On the morning of February 21, 1908, about half-past eight o’clock, two wheelbarrows, one loaded with mortar and the other with brick, were placed upon this elevator in- the cellar and the elevator was then hoisted to the ninth floor. It was the: decedent’s duty to remove the wheelbarrows from the elevator and wheel them to the points at which the material was needed. After the elevator arrived at the ninth floor the deceased stepped upon the elevator platform and took hold of the handle of the wheelbarrow to wheel it off the platform to the floor of the building. The wheel of the wheelbarrow was on the floor, but before he had time to step off the platform the elevator suddenly descended, upsetting the wheelbarrow which with its contents went down the shaft. The elevator descended to about the fourth floor when it was suddenly . stopped and the deceased was thrown off the platform into the cellar receiving injuries which caused his death. It appeared that a rope was provided which ran up the elevator shaft and was connected with a bell near the engine. One stroke of this bell indicated that the elevator was to be raised, and two strokes that it was to be lowered. The negligence charged against the defendants was a violation of the Labor Law (Laws of 1897, chap. 415, § 20, as amd. by Laws of 189.9, chap. 192, and Laws of 1905, chap. 520) in failing to maintain the guards required around the elevator shaft, and that the defendants were responsible for the negligence'of the engineer in charge of the engine.

So far ás the verdict is based upon a failure to guard the elevator shaft it is quite apparent that such negligence, if it existed, was not the cause of the accident. The deceased did not fall down the elevator shaft from the floor of the building but was on the elevator platform, and the accident was caused by the sudden descent of the elevator platform before he had removed the wheelbarrow from it to the floor of the building. The object of the statute is to - prevent workmen engaged in building operations from falling down elevator shafts from the various floors of buildings in course of construction, and not to prevent a person falling off an elevator platform, as a guard around the shaft could be no possible protection to a "person upon the platform of the elevator. Section 20 of the Labor Law (as amd., supra), provides that the contractors or owners of the building in course of construction shall cause' the [203]*203shafts or openings in each floor to be inclosed or fenced in on all sides by a barrier at least eight feet in height except on two sides which may be used for taking off and putting on materials, and those sides shall be guarded by an adjustable barrier not less than three nor more than four feet from the floor, and not less than two feet from the edge of such shaft or opening. And undoubtedly a failure to comply with this law would be evidence of negligence which would justify a recovery by any person injured because of a failure of the contractors or owners to comply with its provisions ; but where the failure to construct these guards or barriers has no relation to the accident, such failure to comply with the law imposes no liability upon the defendant except the penalty provided by the statute itself. The verdict against the defendants, therefore, cannot be sustained because of a failure to erect these barriers.

The only other negligence of which there is any proof is the negligence of the engineer in starting this elevator without having received any signal that it was to be lowered. It is quite clear, I think, from the evidence that the Yassar Company was not chargeable with the negligence of this engineer. He had been in the employ of the Pelham Company for years, and was furnished by it in connection with the engine which operated the elevators which it also supplied. The contract between the Pelham Company and the Yassar Company was not introduced in evidence, but sufficient appears to show that the Pelham Company furnished the engine and elevators, and the engineer to operate them, for which it received payment from the Yassar Company.. It is quite clear that this did not constitute the engineer the servant of the Yassar Company. From the evidence as it stood, therefore, we think that there was no negligence of the Yassar Company to justify a recovery, and the complaint as to it should have been dismissed.

There then remains the question as to whether the accident was caused by the negligence of the engineer in charge of the engine, and whether the Pelham Company was chargeable with such negligence. It is quite apparent that this accident was caused solely by the lowering of the elevator while the deceased was in the' act of removing the materials upon it. So far as appears these elevators were safe appliances for the purposes for 'which they were used if carefully operated, but any sudden starting of the elevator while the [204]*204workmen were engaged in removing materials from them was an act from which the occurrence of an accident was quite probable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bellantoni v. Thomas & Buckley Hoisting Co.
203 A.D. 412 (Appellate Division of the Supreme Court of New York, 1922)
McConnell v. Thomas & Buckley Operating Co.
148 A.D. 635 (Appellate Division of the Supreme Court of New York, 1912)
Clinton v. Boehm
139 A.D. 73 (Appellate Division of the Supreme Court of New York, 1910)
Buckley v. Beinhauer
136 A.D. 540 (Appellate Division of the Supreme Court of New York, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
130 A.D. 200, 114 N.Y.S. 646, 1909 N.Y. App. Div. LEXIS 169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/genovesia-v-pelham-operating-co-nyappdiv-1909.