General Time Corp. v. Bulk Materials, Inc.

826 F. Supp. 471, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20315, 37 ERC (BNA) 1763, 1993 U.S. Dist. LEXIS 8630, 1993 WL 221258
CourtDistrict Court, M.D. Georgia
DecidedJune 18, 1993
DocketCiv. 92-109-ATH(DF)
StatusPublished
Cited by11 cases

This text of 826 F. Supp. 471 (General Time Corp. v. Bulk Materials, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Time Corp. v. Bulk Materials, Inc., 826 F. Supp. 471, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20315, 37 ERC (BNA) 1763, 1993 U.S. Dist. LEXIS 8630, 1993 WL 221258 (M.D. Ga. 1993).

Opinion

FITZPATRICK, District Judge.

On March 29, 1993, this Court heard oral argument on Defendant Fleet Transport Company, Inc.’s (“Fleet”) motion to dismiss 1 under Federal Rule of Civil Procedure 12(b)(6) on the ground that the Plaintiffs have failed to state a claim upon which relief may be granted. A claim should not be dismissed under Rule 12(b)(6) unless it appears beyond doubt that the plaintiff can prove no set of facts entitling it to relief. Luckey v. Harris, 860 F.2d 1012, 1016 (11th Cir.1988). For the purposes of a motion to dismiss this Court must accept the allegations in the complaint as true. Id.

BACKGROUND

This lawsuit arises out. of Fleet’s spill of trichloroethylene (“TCE”), a listed hazardous *474 substance, onto the ground at Plaintiffs facility in Athens, Georgia. On March 4, 1992, Fleet delivered a bulk shipment of TCE to Plaintiffs plant. During the unloading of the TCE, Fleet’s hose failed and came partially loose from the Fleet tanker to which it was attached. As a result, 500 gallons of TCE sprayed onto Plaintiffs property. Despite prompt emergency response efforts, the spilled TCE was not fully recovered, and remains a continuing source of contribution to groundwater contamination at the site.

As part of the emergency response effort, Fleet Transport consented to an order by the Georgia Department of Natural Resources, Division of Environmental Protection (“GEPD”), to engage in a clean-up effort at the site, and to pay a fine for the spill. Georgia EPD did not require General Time to become a party to the Consent Order since Fleet spilled the TCE. Contemporaneous with the emergency response, General Time voluntarily contracted for removal of the contaminated soil necessary to meet the emergency requirements set by the Georgia EPD, which required contaminated soil to be removed from the site until background readings 20 ppb of TCE were achieved. In order to meet these goals under the time constraints imposed by the Georgia EPD, General Time hired USPCI to remove over 3,200 tons of contaminated soil, which cost over one million dollars. The soil removal, which was an integral part of the emergency response ordered by the State, would not have been required absent the spill.

Fleet repeatedly refused General Time’s subsequent requests to reimburse it for the costs of the soil removal. Consequently, Plaintiff filed this suit asserting claims pursuant to Section 107 and 113 of the Comprehensive Environmental Response Compensation and Liability Act of 1980, as amended by the Superfund Amendments and Reauthorization Act of 1986 (“CERCLA”), 42 U.S.C. § 9610 et seq., the Georgia Hazardous Site Response Act (“GHSRA”), O.C.G.A. § 12-8-90 et seq. as well as state common law claims, for actual and consequential damages arising out of the TCE spill. Additionally, Plaintiff seeks a declaratory judgment pursuant to 28 U.S.C. § 2201, determining the ultimate relative responsibilities for the past and future costs of investigation and remediation of the environmental contamination.

DISCUSSION

Defendant Fleet asserts that Plaintiffs claims for contribution are barred pursuant to 42 U.S.C. § 9613(f)(2) and O.C.G.A. § 12-8—96.1(f) and that Plaintiffs state law claims are pre-empted by CERCLA.

I. 42 U.S.C. § 9613(f)

CERCLA imposes a scheme of liability whereby certain entities (“potentially responsible parties” or “PRPs”) are jointly and severally liable for response costs associated with the clean-up of hazardous materials that have been released into the environment at particular facilities. United States v. Pretty Products, Inc., 780 F.Supp. 1488, 1493 (S.D.Ohio 1991). As originally enacted, CERCLA did not expressly permit a PRP who had incurred response costs to pursue contribution against other PRPs. United States v. Cannons Eng’g Corp., 899 F.2d 79, 92 (1st Cir.1990). In 1986, however, Congress added section 113(f) to CERCLA as part of the Superfund Amendments Reauthorization Act (“SARA”) to provide for an express right of contribution among PRPs. See 42 U.S.C. §§ 9613(f)(1) 2 . Section 113(f)(2) 3 , however, bars an action for contri *475 button for payment of response costs or performance of response actions against PRPs who have settled their liabilities with the United States or a State in an administrative or judicially approved settlement. Cannons Eng’g, 899 F.2d at 92; 42 U.S.C. § 9613(f)(2).

Plaintiff argues that the Consent Order between Fleet and GEPD is not an “administrative or judicially approved settlement” under section 113(f)(2) because: (1) it does not expressly provide for contribution protection under § 113(f)(2); (2) it does not mention CERCLA liability; (3) the statutory procedural requirements .under section 122(i) were not followed; and (4) no notice of or opportunity to be heard on the settlement was provided in violation of General Time’s procedural due process rights.

First, Plaintiff contends that § 113(f)(2) does not bar its claim for contribution because the Consent Order, unlike the Model EPA Consent Decree, does not specifically state that section 113(f)(2) contribution protection is provided. The Court rejects this argument. The language in § 113(f)(2) is unequivocal in its grant of contribution protection to PRPs who settle with a State or the federal government. The statutory language does not require the settlement to specifically refer to section 113(f)(2) or to explicitly confer contribution protection. 4 Moreover, in Comerica Bank-Detroit v. Allen Indus., Inc., 769 F.Supp. 1408 (E.D.Mich.1991), the district court approved a settlement that was silent on the issue of contribution protection. Id. at 1410 (“the State/GM agreement is silent as to contribution protection”). 5 Thus, the absence of any contractual language providing contribution protection does not preclude the operation of § 113(f)(2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Arizona v. Raytheon Company
761 F.3d 1005 (Ninth Circuit, 2014)
Doe v. Bishop of Charleston
754 S.E.2d 494 (Supreme Court of South Carolina, 2014)
Niagara Mohawk Power Corp. v. Consolidated Rail Corp.
291 F. Supp. 2d 105 (N.D. New York, 2003)
Steinmetz v. Toyota Motor Credit Corp.
963 F. Supp. 1294 (E.D. New York, 1997)
Kelley v. Wagner
930 F. Supp. 293 (E.D. Michigan, 1996)
Laidlaw Waste Systems, Inc. v. Mallinckrodt, Inc.
925 F. Supp. 624 (E.D. Missouri, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
826 F. Supp. 471, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20315, 37 ERC (BNA) 1763, 1993 U.S. Dist. LEXIS 8630, 1993 WL 221258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-time-corp-v-bulk-materials-inc-gamd-1993.