General Plywood Corp. v. S. R. Brunn Construction Co.

511 S.W.2d 905, 1974 Mo. App. LEXIS 1297
CourtMissouri Court of Appeals
DecidedJuly 1, 1974
Docket26535
StatusPublished
Cited by11 cases

This text of 511 S.W.2d 905 (General Plywood Corp. v. S. R. Brunn Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Plywood Corp. v. S. R. Brunn Construction Co., 511 S.W.2d 905, 1974 Mo. App. LEXIS 1297 (Mo. Ct. App. 1974).

Opinion

WASSERSTROM, Judge.

This is a suit by a materialman to impose a mechanic’s lien on a construction project for which it furnished specially made doors and to recover the value of those doors from the subcontractor Hyder Inc., the principal contractor S. R. Brunn *907 Construction Co., and Brunn’s surety, Federal Insurance Co. Brunn in turn filed a third party petition against Farmers & Traders Bank of California, Missouri, seeking to recover from the Bank any sum for which Brunn might be adjudged liable to plaintiff.

After a trial without a jury, the trial court made findings of fact and conclusions of law and entered judgment for $5,625.29 against Hyder and decreed a mechanic’s lien against the property for that amount; a judgment in the sum of $5,625.-29 against Brunn; and judgment against Federal in the amount of $8,108.66. The greater amount of judgment against Federal as compared to that against Hyder and Brunn comes about because of the assessment of statutory penalties for vexatious delay against Federal. The judgment by the circuit court also provided for dismissal of the third party petition by Brunn against the Bank.

The essential issues for determination on this appeal are as follows: 1) Brunn issued a check for $5,474.50 to Hyder which Hyder delivered to the Bank and the proceeds of which were then delivered by the Bank to plaintiff. Although Brunn intended this check to be in payment for the doors now in suit, the proceeds of the check were actually used by plaintiff toward payment for other doors delivered to Hyder for other jobs under different contractors. These facts present the principal question in this case: Is Brunn entitled to have its check treated as payment toward the obligation now in suit? 2) If Brunn is not so entitled, then is the Bank liable to Brunn for breach of an obligation alleged by Brunn to exist by which the Bank was obligated to use the Brunn check solely in payment of the doors ordered for Brunn’s job? 3) Is Federal liable for statutory vexatious delay penalties?

Preliminary to the discussion of those issues on the merits, certain procedural questions need disposition. The first of these is plaintiff’s motion to dismiss the appeal for the failure of the Brunn and Federal appellants’ brief' to comply with the applicable court rules. This motion is a renewal of plaintiff’s objection previously made to the original appellants’ brief. That original brief was withdrawn, rewritten and the present amended appellants’ brief has been substituted. The amended brief still leaves something to be desired, but it is not so inadequate as to warrant the drastic remedy of dismissal of the appeal.

Other procedural points raised by the plaintiff relate to the sufficiency of the pleadings in the trial court to raise the principal issue now argued on this appeal, and the alleged lack of standing of Brunn and Federal to attack that portion of the judgment establishing a mechanic’s lien. It becomes unnecessary to discuss those procedural points in view of our conclusion that irrespective of the validity of those procedural objections, plaintiff is entitled to recover on the merits of the issues to which these procedural matters relate.

I.

The facts underlying this controversy are rather complicated. Brunn had a general contract for the construction of the Beth Shalom Religious Center in Kansas City, Missouri. In connection with that job, Brunn contracted with Hyder for the latter to supply certain millwork and doors. Hyder ordered the doors to be used from plaintiff, but since Hyder was in very bad financial condition, plaintiff was unwilling to ship any merchandise to Hyder except on a cash basis. Accordingly, plaintiff shipped these doors intended for the Beth Shalom job, together with other doors, to California, Missouri, on October 16, 1969, pursuant to a bill of lading delivered to the Bank with draft on Hyder attached. The bill of lading covered car No. SP223263, and this car contained doors for the Beth Shalom job, for the Kansas City Technical job on which J. E. Dunn Construction Co. was the general contractor, and for other jobs.

*908 Hyder did not have the financial resources with which to pay this draft, and he therefore resorted to requests upon the various general contractors to make advance payment for their respective doors so that Hyder might be able to secure a release of the car. In response to Hyder’s request, Brunn did draw and mail to Hy-der on October 23, 1969, its check in the sum of $5,474.50 payable to Hyder and the Bank jointly. As prepared by Brunn, this check had attached, but in detachable form, a remittance advice which stated “For doors only at Beth Shalom Religious Center job.”

Although Brunn did furnish the money for its share of the doors on car SP223263, Dunn, who had a much more valuable shipment of doors in the same car, refused to do likewise. When this refusal became apparent, plaintiff requested a return of its bill of lading and draft, and those documents were returned to plaintiff by the Bank. Nevertheless, the car remained physically at California, Missouri, and negotiations continued between Dunn and plaintiff for an arrangement under which delivery could be made. Finally an agreement was reached under which payment would be made direct by Dunn to plaintiff for the Dunn doors, and the entire carload (including the Brunn doors) was released to Hyder on November 24, 1969. In agreeing to this release, plaintiff relied in part upon its mechanic’s lien rights against the Beth Shalom job into which the Brunn doors were to be utilized.

On November 20, 1969, shortly before the release of car No. SP223263 was effected, plaintiff sent a second car of doors, No. CBQ 49696, to California, Missouri, for delivery to Hyder, but subject to a new and different bill of lading and attached draft. None of the doors on this second car were destined for any Brunn job. However, during all of the long period since delivery to it of the Brunn check, Hyder had continued to hold the check. After arrival of the second car, No. CBQ 49696, Hyder finally took the Brunn check to the Bank on November 26, 1969, and deposited it, with others, so as to create a balance in its account sufficient to cover plaintiff’s new draft. This draft, by then being the only draft outstanding from plaintiff to Hyder, was in the amount of $6,502.96. After making its deposit, Hyder wrote a check for $6,509.46 (the difference between this check and the amount of the draft representing the Bank’s collection charge) to the Bank with the notation thereon “Sight Draft — General Plywood Corporation.” In exchange for that check the Bank issued and delivered its check for $6,502.96, the amount of the second draft, to plaintiff. Upon receipt of this check from the Bank, plaintiff applied the proceeds to the various invoices covering merchandise which had been shipped in car No. CBQ 49696.

Brunn argues that under these facts the proceeds of its check should have been applied in payment for its doors, not in payment for someone else’s doors. It argues that it so intended and made that intention plain, that the Bank was advised of that intention, and that plaintiff must be held to the Bank’s knowledge on principles of agency. It and Federal contend that as a matter of law this application which they say should have been made originally by plaintiff, must now be made judicially.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pony Express Community Bank v. Campbell
206 S.W.3d 399 (Missouri Court of Appeals, 2006)
Glasco Electric Co. v. Best Electric Co.
751 S.W.2d 104 (Missouri Court of Appeals, 1988)
Amish v. Walnut Creek Development, Inc.
631 S.W.2d 866 (Missouri Court of Appeals, 1982)
Templeton v. Sam Klain & Son, Inc.
425 N.E.2d 89 (Indiana Supreme Court, 1981)
Anchor Lumber Co. v. United Exteriors, Inc.
604 S.W.2d 754 (Missouri Court of Appeals, 1980)
Templeton v. Sam Klain & Son, Inc.
400 N.E.2d 1198 (Indiana Court of Appeals, 1980)
Reger Roofing & Siding Co. v. R & H Roofing & Supply Co.
582 S.W.2d 716 (Missouri Court of Appeals, 1979)
A. E. Birk & Son Plumbing & Heating, Inc. v. Malan Construction Co.
548 S.W.2d 611 (Missouri Court of Appeals, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
511 S.W.2d 905, 1974 Mo. App. LEXIS 1297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-plywood-corp-v-s-r-brunn-construction-co-moctapp-1974.