General Lumber & Supply Co. v. McLellan

200 So. 501, 1941 La. App. LEXIS 62
CourtLouisiana Court of Appeal
DecidedMarch 4, 1941
DocketNo. 2224.
StatusPublished
Cited by5 cases

This text of 200 So. 501 (General Lumber & Supply Co. v. McLellan) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Lumber & Supply Co. v. McLellan, 200 So. 501, 1941 La. App. LEXIS 62 (La. Ct. App. 1941).

Opinion

LEBLANC, Judge.

This is a suit for an alleged balance of $506.03 claimed to be due by plaintiff for building material and supplies furnished to John Comerma who is alleged to have been the duly authorized agent of the defendant herein, duly empowered to act for him in obtaining and purchasing the same.

It is alleged that all of the said material and supplies were used in building and erecting a swimming pool and an addition to a home, and in the repairing and remodeling of certain other buildings, all located upon certain real estate situated in the Parish of St. Tammany, and belonging to the defendant.

Plaintiff alle'ges that the supplies and material were furnished between the dates of July 11, 1938, and December 2, 1938, and on January 13, 1939, through one of its officers, it appeared before L. V. Cooley, Jr., notary public, and subscribed to an affidavit setting forth the indebtedness of the defendant, and had the same recorded in the mortgage records of the Parish of St. Tammany on January 16, 1939.

Plaintiff claims that under the laws of this State, and especially under Act No. 298 of 1926 and its amendments, it has a lien and privilege upon the defendant’s property which is fully described in the petition, having preserved the same by timely recordation of the affidavit for which it paid the recording fee of $1.

The prayer is the usual one for judgment in the amount of the balance claimed, plus the sum of $1, as recording fee, and with recognition of the lien and privilege which is claimed. An itemized statement of the account and a copy of the recorded affidavit are annexed to the petition.

The defendant first filed an exception to the jurisdiction of the Court rationae personae based on plaintiff’s allegation in the petition that he is a resident of the City of New Orleans. The district court sustained the exception as to the demand being prosecuted in personam and reserved plaintiff’s right to continue its suit in rem.

Under reservation of the exception the defendant filed his answer in which he admitted that plaintiff delivered material and supplies to John Comerma, who was an independent contractor. He denies further that Comerma wa’s his agent and empowered to act for him in buying and obtaining the said material and supplies. He further denies that there is a balance due on the said account as alleged and calls for strict proof thereof.

Further answering the defendant admits that the supplies furnished by the plaintiff were used on his property but that they were so used in two separate and distinct contracts which he sets out as follows: The first, entered into during the month of July, 1938, for the construction of a swimming pool, shower and dressing rooms, and for building brick steps in front of his residence, under the terms of which Comerma *503 was to furnish the material and do the work for the price and sum of $3,827. This contract, it is averred, was completed on or before October 4, 1938, and Comerma was paid by_ him in full and the contract terminated. The other was a contract entered into on or about November 4, 1938, for building an extension on his home, putting a strip in the kitchen sink, fixing the toilet in the keeper’s house, repairing galvanized gutters and building dish shelves and trel-leses, all for the sum of $395.14. Defendant alleges, on information and belief, that the material covering the second contract was furnished by plaintiff to Comerma between November 3, 1938, and December 2, 1938, the same amounting to the sum of $166.47 and that he paid Comerma the total amount due under this second contract save and except the sum of $107.14. He further avers that the lien which the plaintiff sues on is invalid, null and void and of no effect except as to that material which was furnished by plaintiff from November 3, 1938, up to and including December 2, 1938, amounting to the sum of $166.47 which latter amount he has tendered the plaintiff but tender was waived.

On the issues as thus presented to it, the district court rendered judgment in favor of the plaintiff and against the defendant, limiting plaintiff’s lien however, to the sum of $167.47. It rejected the remainder of plaintiff’s demand and decreed all costs to be paid by it. Plaintiff thereupon took this appeal.

The contention of the plaintiff in this suit is that there was but one undertaking by this defendant and that related to the improvement of his property as a whole and covered the entire period during which it furnished materials and supplies to his contractor. The defendant on the other hand maintains that there were two separate and distinct contracts, the first of which, as alleged in his answer, had been completed and was terminated in full by payment to and acceptance of such payment by the contractor on October 6, 1938, and the second which arose some two or three weeks afterwards, early in the month of November, and was completed on December 2, 1938. It is contended further that the lien now claimed by the plaintiff having been filed and recorded more than sixty days after the termination of the first contract, cannot avail the plaintiff of any of the rights accorded to the furnisher of material and supplies, as to that contra'ct. It is necessary then in order to properly decide the question at issue, which of these contentions is supported by the testimony in the case.

We find but little difficulty in agreeing with the trial judge that the defendant has clearly sustained his defense of two separate agreements and contracts involving purchases of materials for each, at the time construction was going on under each, and that any lien which might operate against the property must be limited to the supplies and materials furnished on the second contract, as the affidavit filed and recorded to preserve the same, was placed of record beyond the sixty days after the termination of the first contract. It does not seem to be disputed that that is the time limit fixed in the Statute itself.

Plaintiff endeavored to prove its case through the testimony-of Comerma, but as it turned out, his testimony tended largely to support the defense which was presented to its claim for a lien. He says that he solicited the work from the defendant and that he did is clearly shown by his letter of July 16, 1938, addressed to the defendant in New Orleans in which he proposed to furnish material and labor to build the swimming pool according to plans submitted, for the sum of $3,300. Pie later identifies a statement in the form of a bill covering the contract price as stipulated in the letter and some additional work running the total amount to $3,827. This statement is dated October 6, 1938, and it is conceded, as thereon appears, that on that date, he was paid by defendant, the sum of $3,-902, or an amount $75. in excess of the total amount due under the statement. He says himself that the swimming pool had been finished before the house extension job began and that the only work he did on the pool afterwards was to repair the drain pipe, a matter to which we will refer hereafter. He then itemizes another document dated December 2, 1938, which is indicated by its own terms as the contract for building an extension in the defendant’s home and says that that was an entirely different contract from the other. He testifies further that all of the material delivered after November 3, 1938, was used on the second contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daigrepont v. Welch
358 So. 2d 1302 (Louisiana Court of Appeal, 1978)
Albert K. Newlin, Inc. v. Weingarten's Markets Realty Co.
253 So. 2d 594 (Louisiana Court of Appeal, 1971)
Gaston v. Stover
126 So. 2d 360 (Louisiana Court of Appeal, 1960)
Windham Woodwork & Supply Co v. Hopkins
122 So. 2d 106 (Louisiana Court of Appeal, 1960)
WM Bailey & Sons v. Western Geophysical Co.
66 So. 2d 424 (Louisiana Court of Appeal, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
200 So. 501, 1941 La. App. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-lumber-supply-co-v-mclellan-lactapp-1941.