General Insurance Co. of America v. State Highway Commission

414 P.2d 526, 147 Mont. 450, 1966 Mont. LEXIS 403
CourtMontana Supreme Court
DecidedMay 3, 1966
Docket10898
StatusPublished

This text of 414 P.2d 526 (General Insurance Co. of America v. State Highway Commission) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Insurance Co. of America v. State Highway Commission, 414 P.2d 526, 147 Mont. 450, 1966 Mont. LEXIS 403 (Mo. 1966).

Opinion

MR. JUSTICE JOHN C. HARRISON

delivered the Opinion of the Court.

This is an appeal from the decision of the Honorable Lester H. Loble of the district court of the First Judicial District of the State of Montana in and for the County of Lewis and Clark. The case was tried without a jury.

The action arises out of conflicting claims to funds retained by the state under two highway projects. The United Construction Company, Inc., was the general contractor on both projects. The plaintiff-appellant General Insurance Company of America was surety on both contracts. Susa Construction Company, one of the defendant-respondents, was a sub-contractor *452 on the second of the two contracts, and the other defendant-respondent, the American Casualty Company was the insurer against bodily injury and property damage for United.

The two contracts will be referred to as S-45 which was let in 1958 and formally accepted by the Highway Commission on July 21, 1959, and S-95 which was executed on July 29, 1959, and formally accepted by the Highway Commission on July 18, 1960. The State, by virtue of the contracts has retained $6,-428.49 on S-45 and $7,902.95 on S-95.

At the time General became surety on each contract it took from United an application and agreement of indemnity containing written assignments by United to General of certain items, including the retained funds here in issue, although the contracts contained the following proviso:

Section 08.01, para. 2. “The Commission will not recognize nor accept an advance ‘blanket’ assignment by the contractor to any bank or other third party under the provisions of which all payments due, or to become due, the contractor are proposed to be paid direct to such third party rather than to the contractor. The Commission will recognize a request by the contractor to deposit payments to his credit in any stipulated bank.” In this action the plaintiff-appellant contends that its agreement with United was not a general assignment, and therefore, was not submitted to the Highway Commission for approval.

In addition to the above provisions the contract contained the following pertinent provisions concerning the bond:

Section 09.10 reads as follows:

“The statutory time, ninety (90) days, for filing claims against the contract bond shall date from the day of final acceptance of the Project by affirmative action of The Commission — see Sections 6-401 to 6-404, inclusive, Revised Codes of Montana, 1947, as amended.
“The Commission reserves the right to withhold payment of the contractor’s final estimate until any and all just claims filed *453 with The Commission against the contract bond have been settled. If there are no claims filed within the thirty day period following the formal acceptance of the Project by affirmative action of The Commission, payment of the final estimate will be made.
“Also, should a claim or claims be filed with The Commission against the contract bond after the stipulated thirty day period has expired and the final estimate has not yet been paid, the Commission reserves the right to withhold said finál payment until notice of satisfaction of claim or claims has been received.”

Susa Construction Company sub-contracted for United on project S-95. The sub-contract was made on May 15, 1960, and completed on July 14,' 1960. Susa furnished $1,561.96 worth of materials and $1,119.40 in labor for a total of $2,681.36. Shortly after completion Susa contacted the president of United about being paid for his work and from the conversation he learned that United was unable to pay. He then immediately called the division office of the Highway Department at Glen-dive but received no advice. Susa then wrote a letter to the division engineer listing his material and labor costs. This letter was not acted upon by that office nor was it forwarded to the state office. The division engineer testifying at the trial why he took no action stated he “didn’t recognize it as being a claim, but simply a list of his earnings on the project.” This even though the State Highway Commission had accepted the project on July 18, 1960, thereby beginning the statutory 90 day period for presenting claims against the bond of General. Susa did nothing more about the matter until October 20,1960, two days after the 90 day period, when he again contacted the Glendive office. He was told to call the Helena office of the Highway Commission where he was informed that though the 90 day period had run for claims under the bond he could still file a claim with the Commission against the retained earnings, on deposit. Such a claim was made and received by the Com *454 mission on October 31, 1960. At the time of his claim the State was in possession of $7,902.95 to “liquidate unsatisfied claims” under S-95.

During the period of the last contract S-95, United Construction Company became insolvent and unable to pay for labor and materials furnished. Apparently numerous creditors filed their claims within the 90 day proviso, for between January 9, 1961, and February 7, 1961, General paid out $38,982.25 to labor and material suppliers. It refused Susa’s claim on the grounds it was filed 10 days late even though the State Highway Commission had informed General that Susa’s claim would have to be honored before the State would pay out the remainder withheld to “liquidate unsatisfied claims.”

General obtained an assignment from each of the persons it paid as surety and filed these with the Highway Commission on February 17, 1961, along with notices of the indemnity agreements.

While General devoted much of its argument to the force and effect of its assignments, and to section 08.01, para. 2, concerning “blanket assignments” we find that neither give General a preferential position as to the retained fund.

Susa, in the meantime, sued United and attached the retained percentages on the same day, February 17, 1961, as General filed its assignments.

The facts concerning American Casualty Company arise from the purchase by United of policies covering bodily injury and property damage covering both S-45 and S-95. The amount due was $1,523.72. These policies were purchased in compliance with the insurance requirements contained in the Standard Specifications and had to be filed with the State Highway Commission before the contracts could be approved.

American did not file against the surety bond, but on or about July 30, 1962, commenced action against United and served writs of attachment upon the State Auditor attaching funds retained by the State under the construction contract. *455 General brought this action against defendants in August 1961 and joined American as a party after it levied its attachment.

Neither Susa nor American claim under the surety bond, both admitting that their claims were too late. Rather, they bring their actions under the contract. It is this distinction, that makes our consideration somewhat narrower than all of the bond provisions previously quoted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jenkins v. National Surety Co.
277 U.S. 258 (Supreme Court, 1928)
Bower v. Tebbs
314 P.2d 731 (Montana Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
414 P.2d 526, 147 Mont. 450, 1966 Mont. LEXIS 403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-insurance-co-of-america-v-state-highway-commission-mont-1966.