General Electric Co. v. Deutz AG

129 F. Supp. 2d 776, 2000 U.S. Dist. LEXIS 20534, 2000 WL 1643600
CourtDistrict Court, W.D. Pennsylvania
DecidedJuly 31, 2000
DocketCIV.A. 98-370 ERIE
StatusPublished
Cited by2 cases

This text of 129 F. Supp. 2d 776 (General Electric Co. v. Deutz AG) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Electric Co. v. Deutz AG, 129 F. Supp. 2d 776, 2000 U.S. Dist. LEXIS 20534, 2000 WL 1643600 (W.D. Pa. 2000).

Opinion

MEMORANDUM OPINION

McLAUGHLIN, District Judge.

Plaintiff General Electric Company filed the instant action against Defendant Deutz AG on December 22, 1998. It alleges that Deutz breached section 9.08 of the Commercial Agreement entered into by General Electric, Montoren Werke Mannheim (“MWM”) and Deutz by failing to provide MWM with sufficient funds to enable it to perform its obligations under the agreement. During the pendency of this action, on July 8, 1999, Deutz submitted a claim for arbitration against General Electric with the ICC International Court of Arbitration. It requested that the arbitration *778 court decide, by way of a negative declaratory judgment, that General Electric has no claim against Deutz for breach of section 9.08. Presently pending before the Court is Plaintiffs Motion for a Permanent Injunction. Plaintiff requests that the Court enjoin Deutz from participating in the ICC arbitration proceeding. For the reasons that follow, the motion is granted.

I. BACKGROUND AND PROCEDURAL HISTORY

A. The Parties

Plaintiff General Electric is a company incorporated under the laws of the State of New York (Trial Ex. B at 1). It is in the business of designing and manufacturing locomotives, diesel engines, and certain other products (See id.). Defendant Deutz is a corporation incorporated under the laws of the Federal Republic of Germany. It is principally engaged in the manufacture of engines and industrial plan equipment. MWM, which is not a party to this action, is a corporation incorporated under the laws of the Federal Republic of Germany; it is engaged in the design and manufacture of diesel engines and engine products (See id.).

B. Commercial Agreement

On June 15, 1993, General Electric, MWM and Deutz entered into a “Commercial Agreement” for the mutual cooperative development of an innovative line of diesel engines (See id.). Essentially, MWM agreed to design engines for General Electric and General Electric would then build the engines at its facilities in Pennsylvania (See id.). Under the agreement, MWM was responsible for “all costs and expenses relating to the design, development and testing of the 632 Engine Family and the performance of MWM’s other obligations” and General Electric was responsible “for all its costs and expenses relating to the manufacture and testing of the Additional Prototypes.” (Id. § 1.07). General Electric was also obligated to “contribute DM 23.1 million of the costs of design, development, and testing of the 632 Engine Family.” (Id.)

Deutz, formerly named Klockner-Hum-boldt-Deutz (“KHD”), also had obligations under the agreement. The signature page of the agreement provided, “KHD hereby joins in this Agreement and agrees to become a party to this Agreement for purposes of the obligations set forth in Sections 9.08 hereof and Sections 4.05, 4.06, and 4.07 hereof.” (Id. at 45). Section 9.08 stated that KHD would provide MWM “with sufficient funds, by way of capital contribution, loan, or otherwise, to enable MWM or any such Affiliates to perform all of their respective obligations, commitments, undertakings, and covenants under this Agreement.” (Id. § 9.08). Sections 4.05, 4.06 and 4.07 detailed the parties duties to keep certain information confidential (Id. §§ 4.05, 4.06, 4.07).

Additionally, article seven of the agreement contained an arbitration provision which provided that “[a]ll disputes, controversies, and claims directly or indirectly arising out of or in relation to this Agreement”, if they cannot be resolved by negotiations between the parties, must be submitted to international arbitration (Id. at 36). The arbitrators would then rule on the dispute in accordance with the terms of the agreement and if their decision could not be made by referencing the agreement, they would resolve the dispute by applying Swiss law (Id. at 37).

C.Proceedings in This Court

On December 22, 1998, Plaintiff General Electric filed the instant action against Deutz. The complaint alleged that Deutz had breached section 9.08 of the agreement “[b]y failing to provide MWM with sufficient funds to enable MWM to perform its obligations under the Contract.” (Am.CompLf 44). It alleged that as a result of the breach, General Electric suffered damages in excess of eighty million dollars including “[djelayed deliveries and *779 lost sales” and “[djevotion of substantial internal resources to undertake engineering and other tasks with respect to the 632 Engine Family that should have been performed by MWM.” (Id ¶¶ 39, 46).

Deutz filed a motion to compel international arbitration on April 13, 1999. On December 29, 1999, we denied the motion. We held that the contract was ambiguous as to whether Deutz and General Electric agreed to arbitrate their disputes and that such ambiguity should be resolved by a jury after presentation of extrinsic evidence. On February 10 and 11, 2000, we held a jury trial for that purpose; the jury found that Deutz and General Electric did not agree to arbitrate their disputes. As a result of the verdict, we reaffirmed our denial of Deutz’s motion to compel arbitration on February 28, 2000. Deutz subsequently filed a Motion for New Trial, which we denied on July 28, 2000.

D. Proceedings with the ICC Court of Arbitration

On July 8, 1999, while Defendant’s motion to compel international arbitration was pending with this Court, Deutz submitted a claim for arbitration against General Electric with the International Chamber of Commerce Court of Arbitration (“ICC Court”). Deutz requested that the ICC Court decide, by way of a negative declaratory judgment, that General Electric has no claim against Deutz for breach of Section 9.08. 1

By way of background, under the ICC Rules of Arbitration, the ICC Court of Arbitration is an administrative body attached to the ICC. See Rules of Arbitration of the International Chamber of Commerce (hereinafter “ICC Rules”) Article 1(1). The ICC Court does not itself settle arbitration disputes; rather, it sets the arbitrations in motion by referring them to arbitral tribunals and it ensures that the arbitrations are conducted in accordance with ICC Rules. See id. Article 1(1), App. I Article 1(1). 2

A party ‘hyishing to have recourse to arbitration” may commence the proceedings by submitting a Request for Arbitration to the Secretariat of the ICC Court of Arbitration. See id. Article 4(1). The Request must include, among other things, a statement of the relief sought and the party’s nomination of an arbitrator. See id. Article 4(3). Once it is received, the Secretariat will send a copy of the Request to the other party (the Respondent). See id. Article 4(5).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MacPhail v. Oceaneering International, Inc.
186 F. Supp. 2d 704 (S.D. Texas, 2002)
Younis Bros. & Co. v. CIGNA Worldwide Ins. Co.
167 F. Supp. 2d 743 (E.D. Pennsylvania, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
129 F. Supp. 2d 776, 2000 U.S. Dist. LEXIS 20534, 2000 WL 1643600, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-electric-co-v-deutz-ag-pawd-2000.