This text of 122 F. App'x 604 (General Electric Capital Corp. v. Renew) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Electric Capital Corp. v. Renew, 122 F. App'x 604 (4th Cir. 2004).

Opinion

Affirmed by unpublished opinion. Judge DUNCAN wrote the opinion, in which JUDGE Widener and Judge KING concurred.

Unpublished opinions are not binding precedent in this circuit. See Local Rule 36(c).

DUNCAN, Circuit Judge.

A group of employees of the now bankrupt Spartan International, Inc. (“Spartan”) appeals an order resolving the priority of liens held on Spartan’s assets. Because we agree that the employees’ work at a manufacturing facility in Georgia does not entitle them to a worker’s lien under South Carolina law, we affirm.

I

This proceeding focuses on the assets of Spartan, a company formerly headquartered in South Carolina and primarily engaged in textile manufacturing. Spartan operated textile mills in six locations, four in South Carolina and two in Georgia. The employees who are parties to this action worked at the King Mill manufacturing facility in Augusta, Georgia. With the decline of the domestic textile industry, Spartan became unable to meet its financial obligations and was forced to close its business.

The events leading to this litigation began in May 2001, when Spartan turned over the remainder of its assets to General Electric Capital Corporation (“GE Capital”). GE Capital had previously extended a line of credit to Spartan, secured by substantially all of Spartan’s assets. Spartan was initially placed into involuntary bankruptcy in the United States Bankruptcy Court for the Southern District of Georgia, but after a jurisdictional dispute that led to a change of venue, these proceedings commenced in the Bankruptcy Court for the District of South Carolina.

On August 31, 2001, while the underlying bankruptcy action was still pending in Georgia, GE Capital brought this adversary proceeding requesting a determination of the validity, priority and extent of its liens and security interests over Spartan’s assets. Specifically, GE Capital sought a declaratory judgment that its lien on Spartan’s accounts receivable was superior to the claimed liens of the King Mill *606 employees relating to their former employment at the facility. In their answer and counterclaim of September 21, 2001, the employees argued that they were entitled to statutory worker’s liens for outstanding overtime and vacation pay under South Carolina and Georgia law. See S.C.Code Ann. § 29-11-10 and O.C.G.A. § 44-14-380. Generally speaking, and as discussed in greater detail below, such statutes give employees a lien on the property of their employers for the payment of unpaid wages that is superior to most other liens. On February 6, 2002, the employees moved for partial summary judgment, alleging that these statutory worker’s liens had priority over all other claims on Spartan’s assets, including those of GE Capital.

On May 7, 2002, the Bankruptcy Court denied the motion for partial summary judgment, concluding that employees who work outside the state of South Carolina are not entitled to a lien under S.C.Code Ann. § 29-11-10 and that Spartan’s accounts receivable do not qualify as factory “output” under the same provision. The court later concluded that Georgia law also provides no relief for the employees, as it does not allow attachment of Spartan’s accounts receivable due to their location in South Carolina. These conclusions were incorporated into the court’s November 27, 2002 final order that resolved all issues in the proceeding. The employees appealed this order to the United States District Court, which affirmed the judgment on the core reasoning of the Bankruptcy Court. It is this decision we now review.

II

The employees on appeal focus primarily on the interpretation of the South Carolina worker’s lien statute. They argue that as Georgia employees of Spartan, they are entitled to a lien in South Carolina on all property located in the state under S.C.Code Ann. § 29-11-10. In addition, they contend that accounts receivable are part of a manufacturing facility’s “output,” thus constituting property that can be attached under that statute. Because we find that the South Carolina worker’s lien statute does not apply to workers in out-of-state manufacturing facilities, it is unnecessary for us to determine the scope of the term “output” under the statute. 1

The lower courts’ interpretation of S.C.Code Ann. § 29-11-10 is a question of law that we review de novo. U.S. v. Walters, 359 F.3d 340, 343 (4th Cir.2004). S.C.Code Ann. § 29-11-10 states that:

All employees of factories, mines, mills, distilleries and every kind of manufacturing establishment of this State shall have a lien upon all the output of the factory, mine, mill, distillery or other manufacturing establishment by which they may be employed, either by the day or month, whether the contract be in *607 writing or not, to the extent of such salary or wages as may be due and owing to them under the terms of their contract with the employer, such lien to take precedence over any and all other liens except the lien for municipal, State and county taxes.

By its terms, the statute creates a lien for workers who work in facilities “of this state” that is superior to all non-tax liens. The Bankruptcy and district courts interpreted this language as providing a territorial limitation on the statute’s scope, allowing it to provide such a lien only for employees that work for facilities within the boundaries of South Carolina.

Although the employees’ argument is often less than clear, they assert that the South Carolina legislature’s use of the preposition “of’ in the phrase “of this state,” as opposed to the phrase “in this state,” is both deliberate and significant. According to the employees, the South Carolina General Assembly could easily have limited the availability of workers’ liens to employees located “within” the state had it chosen to do so. The employees urge that the term “within” connotes inclusion within a state or area, whereas the phrase “of this state” is broader. The term “of,” according to the employees, connotes “derivation, origin or source.” Appellants’ Reply Br. at 3. Under this interpretation, employees claim that the availability of a worker’s lien under S.C.Code Ann. § 29-11-10 “encompasses [employees of] all corporations incorporated in South Carolina.” Id. Because the statute does not specify that the property subject to the lien must be located in South Carolina, employees further contend that they could have liens on property produced at out-of-state facilities and kept outside the boundaries of South Carolina.

The employees’ argument is not compelling for two reasons. The first has been definitively articulated by the Supreme Court of South Carolina. In Ex Parte First Pennsylvania Banking and Trust Co., 247 S.C. 506, 148 S.E.2d 373, 374 (1966), it recognized the general principle that “...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
122 F. App'x 604, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-electric-capital-corp-v-renew-ca4-2004.