General Dynamics - National Steel and Shipbuilding Company

CourtArmed Services Board of Contract Appeals
DecidedJanuary 25, 2021
DocketASBCA No. 61854
StatusPublished

This text of General Dynamics - National Steel and Shipbuilding Company (General Dynamics - National Steel and Shipbuilding Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Dynamics - National Steel and Shipbuilding Company, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) General Dynamics - National Steel ) ASBCA No. 61854 and Shipbuilding Company ) ) Under Contract No. N00024-17-C-4426 )

APPEARANCE FOR THE APPELLANT: William M. Pannier, Esq. Pannier Law, PC Thousand Oaks, CA

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Devin A. Wolak, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE PAUL ON THE PARTIES’ CROSS-MOTIONS FOR SUMMARY JUDGMENT

This is an appeal of a deemed denial by the Navy’s contracting officer (CO) of appellant General Dynamics National Steel and Shipbuilding Company’s (GD) certified claim seeking equitable adjustments in a total amount of $1,933,018.30. The Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, is applicable. Appellant filed a motion for summary judgment, and the Navy submitted a cross-motion. The underlying record is voluminous. We grant the appellant’s motion and deny respondent’s cross-motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS 1

1. On January 24, 2017, the Naval Sea Systems Command, Department of the Navy (NAVSEA) issued Solicitation No. N00024-17-R-4426 (R4, tab 1.01 at 1.05). Contract Line Item (CLIN) No. 001 described the basic work as follows:

The Contactor shall prepare for and accomplish repair and alterations during the Dry-Docking Phased Maintenance Availability (DPMA) onboard USS MAKIN ISLAND (LHD 08) as specified in the statement of work provided herein and in accordance with standard items, work item

1 We cite these facts solely for purposes of resolving the cross-motions. specification package SSP TPPC-LHD8-SWRMC17- CNO1 drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

(R4, tab 1 at 2)

2. The solicitation incorporated by full text NAVSEA Clause 5252.233-9103, DOCUMENTION OF REQUESTS FOR EQUITABLE ADJUSTMENTS (APR 1999); it also incorporated by reference Defense Federal Acquisition Regulation Supplement (DFARS) 252.217-7003, CHANGES (DEC 1991), and DFARS 252.243-7002, REQUEST FOR EQUITABLE ADJUSTMENT (DEC 2012) (R4, tab 1 at 52, 57-58).

3. The solicitation was amended 10 times (R4, tab 1.01, passim).

4. The Navy received two proposals in response to the solicitation; and, on June 6, 2017, it awarded Contract No. N0024-17-C-4426 to appellant in a fixed-price amount of $121,598,483 (R4, tabs 1.11-12).

5. The contract contained several CLINs which were further broken down into work items (R4, tabs 1-2, passim). A typical work item format consisted of five paragraphs: 1) scope, 2) references, 3) requirements, 4) notes, and 5) government furnished materials (GFM). Paragraph 5 typically provided: “All GFM listed in paragraph 5 shall be installed by the requirements invoked in paragraph 3.” GFM is to be listed in accordance with the following categories:

5.1 LLTM 2

5.2 Push MATERIAL

5.3 KITTED MATERIAL

(App. supp. R4, tab 1 at 32) The work items did not place any responsibility on the contractor with respect to fabrication of GFM. Accordingly, GD did not include any such amounts in its proposal (R4, tabs 1-2, passim; tab 1.12, passim).

6. Subparagraph 1.2 of the contract’s scope of work provided:

The Contractor shall accomplish planning and scheduling to ensure a rational, integrated and timely plan for receipt, storage and installation of Government Furnished Material

2 “LLTM” is long lead time material (R4, tab 4 at 4080). 2 as identified in work item specifications, and for accomplishment of production work.

Subparagraph 1.8 of the scope of work stated:

Government Furnished Material (GFM) cited in the solicitation will be shipped to the contractor’s facility. The successful offeror is to coordinate delivery of Government Furnished Material with the Project Manager. Government property permanently removed from a vessel that requires a Property Administrator’s disposition instructions shall be property prepared for shipment and be delivered as directed by the Property Administrator. GFM will be listed in paragraph 5 of the Work Items(s).

(R4, tab 1 at 15-16)

7. The requirements of the Navy’s Joint Fleet Maintenance Manual (JFMM) are applicable to the instant contract. Subparagraph 2.18.2.3 provided:

Late or Defective Government Furnished Property and Information. When a contract obligates the Government to provide GFP and information to a contractor, the Government must provide it by the date specified, or if no date is specified, whenever the contractor reasonably requires it. Failure to do so may entitle the contractor to an equitable adjustment. The GFP or GFI must be suitable for its intended use or purpose when the contractor receives it, unless the contract provides otherwise, or the contractor may similarly be entitled to an equitable adjustment. Late or defective furnished Government property and information ranks second only to constructive change orders as the most frequent basis of claims.

(R4, tab 4 at 4047)

8. Also, subparagraph 4.4.7 stated:

Material Requirements. The contractor shall furnish material required for the performance of any contract unless provided as GFM. Any other material required for performance is Contractor Furnished Material. In contracts it is Government policy, in accordance with

3 reference (h), for contractors to supply all labor and material required for performance of the terms and conditions of the contract. One exception is the Government has the right to provide material as GFM whenever it is determined to be in the best interest of the Government. Long Lead Time Material should be provided as GFM. This material is defined as that which is not commercially or otherwise available to the contractor in time to support the performance schedule. The following material should be considered GFM:

A. Parts unique to or obtainable only through the Government.

B. Standardization material (System Procured Material/Contractor Procured Material for Alterations) (for configuration consistency).

C. LLT Material (including any material not available in time to support production).

D. Parts requiring provisioning of technical documentation (new components not supported in the Navy supply system).

E. Stocked material: In long supply (supplies far in excess of demand), expiring shelf life (material in stock will expire if not used) or Class Maintenance Plan (CMP) programmed material (pre-positioned for special CMP programs).

F. Whenever it is in the best interest of the Government.

(R4, tab 4 at 4080-81) This subparagraph demonstrates that GFM is material with which the Government has a special, if not unique, relationship. As such, it reinforces the notion that the Government should also have a unique role in fabricating such material.

9. On July 5 and July 7, 2017, the Navy issued Requests for Contract Change (RCC’s) 10G through 27G. The RCC’s belatedly required GD to provide 17 work items, comprising over 11,000 line items of material, as CFM rather than GFM (app. supp. R4, tabs 3-20). Each RCC was comprised of a document marked “For Pricing Only” (id.).

4 10. On August 17, 2017, GD informed the Navy of its concerns regarding the issuance and implementation of RCC’s 10G through 27G. Initially, GD stated its concern regarding the lateness of the arrival of GFM materials, noting that this material was to be delivered to the pile 30 days before the ship’s availability. It then noted that the changes involved over 11,000 line items of material. GD also posited a schedule impact of 23 weeks and referenced accumulating costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
General Dynamics - National Steel and Shipbuilding Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-dynamics-national-steel-and-shipbuilding-company-asbca-2021.