General Bonding & Casualty Ins. Co. v. McCurdy

183 S.W. 796, 1916 Tex. App. LEXIS 173
CourtCourt of Appeals of Texas
DecidedFebruary 2, 1916
DocketNo. 5567.
StatusPublished
Cited by22 cases

This text of 183 S.W. 796 (General Bonding & Casualty Ins. Co. v. McCurdy) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Bonding & Casualty Ins. Co. v. McCurdy, 183 S.W. 796, 1916 Tex. App. LEXIS 173 (Tex. Ct. App. 1916).

Opinions

On January 27, 1913, W. O. McCurdy and L. W. Franks entered into a building contract, whereby Franks agreed to provide all the materials and perform all work, and deliver the building completed, free of all liens, by June 1, 1913, for $10,445.35, to be paid in installments upon certificates of the architects, Stephenson Heldenfels, but 20 per cent. to be retained until completion of the building and paid within 10 days thereafter. Franks executed a bond guaranteeing the faithful performance of his contract, with the General Bonding Casualty Insurance Company as surety. McCurdy died on June 19, 1913, and his widow, who was the sole devisee under his will, qualified as independent executrix in July, 1913.

The building was completed and accepted by Mrs. McCurdy on September 1, 1913, at which time the sum of $2,081.15 remained unpaid to Franks. Some time after August 20th F. W. Heldenfels, the architect, who personally supervised the construction of the building, in order to make up a statement of the final condition of the job, and to arrive at what Franks owed on the building for material and labor, went around and talked to each of Franks' creditors personally and got "a statement of what they had against the building." In this way it was ascertained that Franks owed more than the portion of the contract price on hand would satisfy. On September 5, 1913, the attorneys for the estate of McCurdy telegraphed the General Bonding Casualty Insurance Company that they had just been informed by Heldenfels, architect for the McCurdy building, that there was $2,081.15 due to Franks, and $3,876.26 in claims due by Franks, making a difference of $1,795.11 which might become a lien on the building, and for the company to give this immediate attention. A reply was telegraphed on the same day as follows: "Architects certainly know the usual custom of prorating funds left on hand." Acting upon this reply, Heldenfels, on September 9th, prorated the $2,081.15 among various creditors of Franks (all of whom, save probably one, were interveners in this suit) paying each approximately 53 3/4 per cent. of his debt, and he informed the creditors if they would file liens for the balance of their claims the McCurdy estate would pay them. Most of the creditors filed statements with the county clerk, *Page 798 seeking to fix a mechanic's or materialman's lien under the statute.

The claims against Franks after the completion of the building and held by interveners in this suit, briefly, were as follows:

(1)   Heldenfels Bros., lumber and
       other material, prosecuted by
       J. C. Wood, assignee of
       Heldenfels Bros. .................................. $1,139 33
(2)   Beeville Windmill  Plumbing
       Co. material ......................................    132 23
(3)   Noble and Woodruff, hauling ........................    223 96
(4)   C. E. French, bricklaying ..........................     53 81
(5)   a. Francis Michot, labor
          and material .................... $14 21
      b. Burrows Hardware Company, material
          Company, material ...............  23 22
      c. S. I. De Loach, plasterer ........  18 69             56 12
(6)   Homer Botts and 14 others, day
       laborers, claims totaling .........................    105 26

Total ......................................... $1,709 71

Each one of the claims represented a balance due after the payment of its pro rata part of the fund of $2,081.15 on September 9th.

Some time after the completion of the building Mrs. McCurdy instituted this suit against Franks and the Bonding Company, alleging that certain of the claimants had filed liens against the property which constituted a cloud on her title, and that others had valid claims that were liens or could be converted into liens, and that she and her deceased husband, as well as their agents and representatives, had faithfully complied with all the obligations imposed upon them in the building contract, and that the entire contract price had been paid. She alleged the facts as to the delay and prayed that the validity of all claims and liens be determined, and that she have judgment for the amount of all such claims and liens as were valid and resulted from the contractor's fault, and that she recover $105 liquidated damage for delay in completion of the building.

Intervener C. E. French sued for $53.81, balance due him for work as a brick mason. His account was filed September 11, 1913. He alleged that within 90 days after accrual of the indebtedness he gave notice to Franks and plaintiff of the amounts and items of the indebtedness. He also alleged that he had a lien as admitted in plaintiff's original petition, and that he had a lien, even though the cost exceeded the contract price, because the owner permitted him to continue his work knowing that Franks was insolvent, and that the cost would exceed the contract price. He also alleged that he was promised by the agents of the owner that his account for labor performed and to be performed would be paid; that he would not have performed said labor if it had not been for such promise.

Interveners Noble Woodruff sued for a balance of $223.96 for hauling material and leveling dirt. Their allegations are the same as those of French.

Francis Michot sued for a balance of $14.21 for material, Burrows Hardware Company, for $23.22, for material, and S. I. De Loach for $18.69, for labor. The first two alleged that they had given notice to Franks and plaintiff of the amounts and items of their claims within 90 days of the accrual thereof, and that each of them filed with the county clerk a verified account within said time. De Loach's allegation of notice and filing of account was the same as that of the other two, except that he alleged he gave notice and filed his account within 30 days after the accrual of the indebtedness. They all alleged estoppel along the lines pleaded by intervener French, as well as that the owner, by her agent, F. W. Heldenfels, expressly promised to pay their claims.

Interveners Homer Botts, J. L. Slusser, Clarence Boss, John Davis, J. W. Nolan, E. J. Canada, J. E. Click, Pete Ahasoy, M. Fernandez, Don Sauseda, Dan Tally, Oscar Bennett, E. J. Book, and F. Baldwin sued to recover small amounts due them for labor, and the Beeville Manufacturing Company, $3.93, for supplies furnished. They sued upon an express agreement by the owner to pay their claims, and also alleged estoppel by reason of the same facts pleaded by the other interveners.

The Beeville Windmill Plumbing Company sued for $132.23, for material. Its petition contained the same allegations as that of French, with the exception that no promise on the part of the owner is relied on.

J. C. Wood, as assignee of Heldenfels Bros., sued to recover a balance of $1,139.33 due for material furnished, alleging the same facts as intervener French for the purpose of showing a lien by estoppel, and also that W. O. McCurdy promised and agreed with F. W. Heldenfels that he would pay for such material as said firm would furnish Franks for use in the construction of the building to be erected by said McCurdy. This intervener also alleged notice in the same general way as intervener French.

Plaintiff's answer to each of such petitions of intervention consisted of general demurrer, special exceptions, denial of every material allegation, and a special reply to the effect that the division of the balance on hand was made by agreement between the owner and all holders of unpaid claims, and that French was a party to such agreement, accepted his part, and is therefore estopped from setting up any further claim against plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trammell Crow Co. No. 60 v. Harkinson
944 S.W.2d 631 (Texas Supreme Court, 1997)
Farah v. Stout
684 A.2d 471 (Court of Special Appeals of Maryland, 1996)
Bennett v. Hood
238 S.W.2d 587 (Court of Appeals of Texas, 1951)
Zachry v. Robertson
210 S.W.2d 466 (Court of Appeals of Texas, 1948)
Shirley-Self Motor Co. v. Canon
166 S.W.2d 155 (Court of Appeals of Texas, 1942)
Alexander v. Stock Yards Nat. Bank of Fort Worth
154 S.W.2d 997 (Court of Appeals of Texas, 1941)
Jackson v. Piper
28 S.W.2d 240 (Court of Appeals of Texas, 1930)
Lassiter v. Bouche
5 S.W.2d 831 (Court of Appeals of Texas, 1928)
Knox v. Brown
8 S.W.2d 280 (Court of Appeals of Texas, 1928)
Lumbermen's Reciprocal Ass'n v. Ryan
299 S.W. 701 (Court of Appeals of Texas, 1927)
First State Bank of Wortham v. Bland
291 S.W. 650 (Court of Appeals of Texas, 1927)
Thos. W. Blake Lumber Co. v. Guaranty State Bank of Woodville
290 S.W. 187 (Court of Appeals of Texas, 1926)
Christopher v. Davis
284 S.W. 253 (Court of Appeals of Texas, 1926)
Donley v. Ardrey
261 S.W. 1059 (Court of Appeals of Texas, 1924)
Alamo Iron Works v. Prado
220 S.W. 282 (Court of Appeals of Texas, 1920)
Richardson v. Terry
212 S.W. 523 (Court of Appeals of Texas, 1919)
McCaslin v. Veasy
199 S.W. 1173 (Court of Appeals of Texas, 1917)
Corbett v. Kingan
166 P. 290 (Arizona Supreme Court, 1917)
Texas Fidelity & Bonding Co. v. Rosenberg Independent School Dist.
195 S.W. 298 (Court of Appeals of Texas, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
183 S.W. 796, 1916 Tex. App. LEXIS 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-bonding-casualty-ins-co-v-mccurdy-texapp-1916.