Gayton v. Day

178 F. 249, 1910 U.S. App. LEXIS 4497
CourtCourt of Appeals for the Third Circuit
DecidedFebruary 10, 1910
DocketNo. 85 (1,290)
StatusPublished
Cited by7 cases

This text of 178 F. 249 (Gayton v. Day) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gayton v. Day, 178 F. 249, 1910 U.S. App. LEXIS 4497 (3d Cir. 1910).

Opinion

GRAY, Circuit Judge.

The action in the court below was brought by Mrs. E. M. Day, the defendant in error (hereinafter called the plaintiff), against Gayton and Heasley, the plaintiffs in error (hereinafter called the defendants), to recover damages which the plaintiff claimed to have suffered by reason of defendants’ breach of a contract to drill for the plaintiff a certain oil well in the state of Pennsylvania. The trial resulted in a verdict for the plaintiff, and from the judgment on this verdict the defendants have sued out this writ of error.

The undisputed facts appearing in the recoi'd are, that on November 4, 1905, the plaintiff made a contract in writing with the defendants, [250]*250to drill a well for oil or gas on lands leased by the plaintiff, situate in the township of Gaynes, Tioga county, Pa., at such place as might be designated by plaintiff, to the depth of 4,000 feet. The contract provided that drilling should stop at any place that plaintiff might direct by written notice, but that if it were stopped on her notice at a less depth than 2,000 feet, defendants should receive payment as if 2,000 feet had been actually drilled.

For the drilling of the well, the contract provided that the plaintiff should pay the defendants $1 per foot for the first 2,000 feet, $2 per foot for from 3,000 to 3,500 feet, and $5 per foot for from 3,500 to 4,000 feet, these amounts to be paid when said well should have been completed ; and that no sum whatever should become due under the contract if defendants failed to complete said well to the depth of 4,000 feet, unless stopped by plaintiff at a less depth. This contract is set out in full as an exhibit attached to the statement of claim. Under it, the defendants drilled a well to the depth of 4,190 feet, and completed the same by the 17th day of May, 1906, some weeks within the time stipulated for its completion by the written contract. On that day, the plaintiff paid the defendants $9,761.76, the amount due under the contract for the drilling to the depth of 4,100 feet, the 90 feet that was drilled being left for future adjustment. On the 17th day of May, 1906, the said plaintiff made another written contract with the defendants, to continue the drilling of this well from its present depth of 4,100 feet to a depth of 5,100 feet, under certain terms and conditions, among which are the following:

“Party of the first part” (the plaintiff) “shall have the right to stop the drilling at any point after the depth of 4,600 feet shall have been reached by second parties” (the defendants), “but first party shall not have the right to stop said drilling before said depth of 4,600 feet shall have been reached.
“If, in the course of drilling, hard granite, water,, or hard flint shall be encountered which renders it impossible to proceed, or in case it shall become impossible for second parties, with reasonable efforts and skill and with approved tools and apparatus, to continue drilling, that in such case second parties may cease drilling, in which event first xrarty agrees to pay second parties the sum of five dollars per foot for each foot actually drilled.”

This contract concluded with this provision:

“All of the terms and conditions of a certain contract, relating to said well, dated November 4th, 1905, which remain at this date unperformed, shall not in any way be affected by this new agreement.”

This contract is set out in full as an exhibit attached to the statement of claim. Under this contract, defendants, after making necessary changes in the derrick and certain disbursements preparatory to the drilling of a well to this depth, proceeded under this second contract and drilled said well to the depth of 4,740 feet. The defendants in their affidavit of defense allege that when they reached this point, owing to the caving in of the sides of the well, it became impossible, with reasonable efforts and approved tools and apparatus, to continue said drilling, and that they so notified the plaintiff, and that the well was measured to that depth. Defendants further say they used extraordinary efforts and went to large expense in getting the best tools and apparatus that could be found, and used the best skill, in attempt[251]*251ing io clean out said well and drill it to a lower depth, and that it was after exhausting every possible effort and finding it would he impossible to proceed with the drilling-, that the plaintiff was notified of the impossibility of drilling the well any further. Defendants therefore aver in their said affidavit of defense, that the plaintiff is indebted to the defendants for the 610 feet drilled over 4, LOO feet, at $5 per foot, and for $317.60, for work and labor done on the rig and new material furnished by defendants on plaintiff’s account, as per said second contract, making- a total of $3,517.69 claimed of the plaintiff.

Of this claim of set-off, with interest from the 31st day of October, 1906, due notice in writing was served by the defendants upon the plaintiff. Testimony was adduced on behalf of the defendants, tending to support the allegations in their affidavit of defense, as above recited. On the other hand, the plaintiff adduced testimony, tending to prove, as she had alleged, that reasonable skill and approved tools and apparatus were not used by the defendants to overcome the obstruction caused by the caving in of the sides of the well and to complete the well to the required deptli of 5,100 feet.

This issue of fact was, we think, properly and fairly presented to the jury by the learned trial judge, and the assignments of error touching the reception of testimony hearing upon this question and upon the charge of the trial judge in regard thereto cannot he sustained.

We turn, therefore, to what we must consider the serious questions raised by the fifth and eighth assignments of error.

The fifth assignment is based upon an exception to the following language in the general charge delivered to the jury. The language excepted to is as follows:

“I may say to you, gentlemen, that these two contracts aro to be considered •together; wo are unable to separate them and. to say that the first contract had no bearing on the second, because by the terms of the contract, itself (which made the law of the parties) it was agreed, when the contract was entered into, that
“All the terms and conditions of a certain contract relating to said well, dated November 4, IfiOo, which remain at this date unperformed, shall not in any way be affected by this new agreement.”

In this statement of the learned trial judge, we think there is grave error. The two contracts were made at different times, and the second contract, as we view it, was independent of the first. It was made after the first contract had been ftdly completed on both sides. The well had been drilled by the defendants to the depth required by the contract, and all other matters and things to be performed on tlieir part appear, so far as the record shows, to have been done and performed and the full amount to have been paid by plaintiff under the contract, upon the completion of the work, had been so paid. The second contract bore no relation to the first, except in the fact that the work to be done under it commenced where the work under the first contract left off.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Steel Products Corp. v. United States
36 F. Supp. 498 (E.D. New York, 1941)
Franklin Sugar Refining Co. v. Eiseman
139 A. 147 (Supreme Court of Pennsylvania, 1927)
Cotherman v. Oriental Oil Co.
272 S.W. 616 (Court of Appeals of Texas, 1925)
Edgerton v. . Taylor
115 S.E. 156 (Supreme Court of North Carolina, 1922)
North Healdton Oil & Gas Co. v. Skelley
1916 OK 659 (Supreme Court of Oklahoma, 1916)
Henry Oil Co. v. Head
163 S.W. 311 (Court of Appeals of Texas, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
178 F. 249, 1910 U.S. App. LEXIS 4497, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gayton-v-day-ca3-1910.