Gas Serv. Co. v. Kansas Corporation Comm'n

631 P.2d 263, 6 Kan. App. 2d 592, 43 P.U.R.4th 661, 1981 Kan. App. LEXIS 320
CourtCourt of Appeals of Kansas
DecidedJuly 15, 1981
Docket53,146
StatusPublished
Cited by3 cases

This text of 631 P.2d 263 (Gas Serv. Co. v. Kansas Corporation Comm'n) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gas Serv. Co. v. Kansas Corporation Comm'n, 631 P.2d 263, 6 Kan. App. 2d 592, 43 P.U.R.4th 661, 1981 Kan. App. LEXIS 320 (kanctapp 1981).

Opinion

Abbott, J.:

This appeal by The Gas Service Company (Gas Service) centers around the State Corporation Commission’s (Commission) interpretation of K.A.R. 82-1-231(b) (rule 231[b]). Rule 231(b) allows a utility which proposes a change in rates within twelve months after a general rate order to submit simplified schedules with its application provided it is willing to adopt the regulatory procedures, principles and rate of return established in the last general rate case.

Within the preceding twelve months prior to commencing the *593 proceeding presently before us, Gas Service received a general rate order in docket No. 119,314. Two figures which the Commission arrived at in that order are of particular significance in this appeal; Gas Service was allowed 14 percent as the cost of common equity and 8.83 percent as an overall rate of return. Three months later, pursuant to rule 231(b), Gas Service filed its application with the Commission in the case now before us (docket No. 123,786), requesting $7,172,506 in additional gross revenue.

The Commission bifurcated the hearing on the application, dealing first with accounting matters concerning the requested increase in revenues and then with rate design. Rate design is not in issue in this appeal. The Commission employed special staff (the accounting firm of Fox & Company) to investigate the application and present testimony. Gas Service presented testimony that its rate of return after annualization and normalization was 6.18 percent rather than the 8.83 percent authorized. Gas Service’s evidence was that the overall rate of return should increase to 9.21 percent. The staff’s testimony was that the purpose of its examination of the books and records of Gas Service was to assure that the regulatory proceedings, principles and rate of return ordered in docket No. 119,314 had been applied in this case. The staff made certain adjustments, found the test year actual rate of return to be 6.33 percent, and computed the overall rate of return under the proposed increase at 9.13 percent, based on the 14 percent cost of common equity ordered in docket No. 119,314. Gas Service’s witnesses stated they would not dispute any of the staff’s adjustments and so adopted them. The 9.13 percent overall rate of return reduced Gas Service’s request from $7,172,506 to $6,613,452. The Commission rejected a 9.13 percent rate of return and ordered a return of 8.61 percent. It is expected that 8.61 percent would produce $5,383,900, some $1,229,552 less than the staff figures adopted by Gas Service. Assuming all other embedded costs of capital used, the 8.61 percent overall rate of return would provide a 12.4 percent return on common equity. Commissioner Dick dissented to the allowance of 8.61 percent overall rate of return, stating that it was completely inadequate.

Gas Service contends that the order setting the overall rate of return at 8.61 percent is unjust, unlawful, unreasonable and confiscatory. It argues that an increase of $6,613,452 was sup *594 ported by staff testimony and not disputed by any party to the proceeding. It also argues that the Commission cannot depart from the rate of return established in the previous order without having a reasonable basis for doing so and affording the utility with notice and an opportunity to be heard.

At the outset we are faced with the Commission’s contention that this appeal is moot. The mootness argument is based on a subsequent application for a rate increase filed by Gas Service (docket No. 126,922) in which the Commission issued an interim order authorizing additional gross revenues of $2,718,695 for the period June 1, 1981, through September 30, 1981. Gas Service implemented the new rates on June 1, 1981, and the Commission reasons that since an increase in rates arising out of this appeal can operate only prospectively, and the interim rates are producing more than Gas Service complains of not receiving ($2,718,695 received opposed to $1,229,552 involved in this appeal), the issue is moot. We disagree.

First, the Commission issued an interim increase, which is collected under bond and subject to refund under certain conditions. Second, assuming that the increase requested in the case which is presently under consideration by the Commission is superseded by an authorized increase, the order authorizing that increase would not be final until all judicial review is exhausted. If an appellate court were to set aside that order as unreasonable or unlawful, the rates in this case would be left as the authorized ones. We recognize that our opinion in this case probably will have no effect on either Gas Service or the consumers, because the rate schedule here has been superseded by an interim order authorizing Gas Service to collect higher rates than can be provided in this case and thus in the absence of the occurrence of one of the two events described above, any change in rates ultimately authorized in this case would never be collected. We cannot say, however, that the issue is moot in view of the possibility that a determination in the present case could have real, even if short-lived, effects.

The center of controversy in this appeal is rule 231(b), which provides in pertinent part:

“Subject to prior approval by the commission, utilities which propose a change in rates within twelve (12) months after a commission order following a general rate proceeding and investigation, and which are willing to adopt all the regulatory procedures, principles and rate of return established by the commission in such *595 order may submit schedules which eliminate data which is a duplication of information provided in the original schedules.”

Gas Service argues that rule 231(b) binds both the Commission and the utility to the rate of return established in the preceding order. The previously authorized rate of return was 8.83 percent, and Gas Service maintains it was error not to increase the overall rate of return to 9.13 percent. Obviously, 9.13 percent is more than the 8.83 percent authorized in the preceding order. Gas Service seems to argue that these percentages are merely the product of a formula, and rule 231(b) means that the Commission and the applicant must adhere to the same figures used in the preceding case, which were discretionary with the Commission. Gas Service suggests that all figures used in the formula are embedded costs and the only discretionary figure is cost of common equity. In this case, Gas Service argues that the only figure that cannot be changed is the 14 percent allowed as cost of common equity. We do not agree.

Gas Service stated during oral argument that rule 231(b) allows the Commission to adjust the 14 percent cost of common equity figure if the Commission notifies the utility of its intent to do so and a change of circumstances is demonstrated in the record. It points out that the staff and the utility both adopted the 14 percent cost of equity figure from the Commission’s previous order, and there was no evidence presented by either side to dispute or question that figure.

The Commission seems to argue that rule 231(b) is procedural in nature and only the utility is bound by the rule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Island Hi-Speed Ferry, LLC.
852 A.2d 524 (Supreme Court of Rhode Island, 2004)
Kansas Industrial Consumers v. Kansas Corporation Comm'n
42 P.3d 110 (Court of Appeals of Kansas, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
631 P.2d 263, 6 Kan. App. 2d 592, 43 P.U.R.4th 661, 1981 Kan. App. LEXIS 320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gas-serv-co-v-kansas-corporation-commn-kanctapp-1981.